Fourth Quarter - Finance, Procurement & Performance Reports

Noted Executive 4 papers

AI summaryHigh Peak Cabinet notes a £419,530 underspend on the General Fund for 2025/26, approves reserve movements and carries forward unspent capital budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQ4 2025/26 position noted, reserve movements approved
Money£419,530 underspendGeneral Fund provisional outturn for 2025/26
What happens nextCarry forward capital underspendUnspent capital budget to be carried forward
Who it affectsCouncil finances and residentsAffects budget reserves and capital programme delivery

What was decided

Cabinet noted the fourth quarter 2025/26 financial, procurement and performance position in Appendices A, B and C. Report 2.1

Cabinet approved the proposed reserve movements set out in Appendix A, paragraphs 2.8 to 2.10. Report 2.1

Cabinet noted the carry forward of unspent capital budget as set out in Appendix A, paragraph 5.4. Report 2.1

Why

The report brings together finance, procurement and performance information for the fourth quarter ending 31 March 2026, so members can review how budgets and services are performing. Report 3.1, 3.2, 4.1

Delivery of the council's corporate priorities depends on effective management of performance and financial resources, which this report covers. Report 4.1

What happens next

Officers will progress the £267,080 cumulative efficiency programme shortfall that rolls forward into the next financial year. Report P4

The unspent capital budget will be carried forward into the new financial year as set out in Appendix A. Report 2.1

The money

  • £419,530 General Fund provisional outturn underspend for 2025/26 Report P4
  • £141,480 Efficiencies identified in the year Report P4
  • £267,080 Cumulative shortfall on the efficiency programme rolling forward Report P4
  • £932,448 General Fund Capital Programme underspend for 2025/26 Report P4
  • £18million General Fund Capital Programme budget for 2025/26 Report P4
  • £9.4million Cash investments held at year end Report P4
  • £12.1million External borrowing at year end Report P4
  • £2,187 Net interest income shortfall Report P4
  • £71,034 Sundry debt over 60 days old, covering 67 invoices Report P4
  • £45,223 Sundry debt over 60 days old in the previous year, covering 84 invoices Report P4

Options considered

  • Chosen: Note the Q4 position, approve reserve movements and note the capital carry forward. Recommended in the officer report to keep the council up to date on finances, procurement and performance Report 2.1

Implications

  • Financial: Substantial financial considerations are set out throughout the report, including reserve movements, the efficiency programme shortfall and capital carry forward. Report P4
  • Risk: A number of risks to the financial position are identified and explained in Appendix A.
  • Equalities: The report has been prepared in line with the council's Equality and Diversity policies.
  • Climate: Environmental and sustainability implications are discussed throughout the body of the report.
  • Other: Expenditure and funding for biodiversity net gain is included in the relevant service area forecast outturn.

Who and where

  • Council taxpayers and business rate payers Report P4
  • Staff delivering council services and the efficiency programme Report P4
  • Suppliers involved in the 51 procurement activities in the forward plan Report P4

Timeline

  • 31 March 2026: End of the fourth quarter reporting period Report 3.1
  • 2025/26: General Fund provisional outturn of £419,530 underspend Report P4

Plain English for the jargon

  • General Fund: The council's main revenue account for day to day services.
  • Capital Programme: Planned spending on assets and long term projects, such as buildings or equipment.
  • Efficiency Programme: The council's planned savings and efficiency targets for the year.
  • Treasury Management: Management of the council's cash investments and borrowing.
  • Sundry debt:
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

DECISION: 1. That the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A, B and C and summarised at 3.3 of the covering report be noted. 2. That the proposed reserve movements in Appendix A (Paragraphs 2.8-2.10) be approved. 3. That the carry forward of unspent capital budget as set out in Appendix A (Paragraph 5.4) be noted.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Cabinet

Recommendation

2.1It is recommended that Cabinet: - • Note the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A, B and C and summarised at 3.3 of this covering report • Approve the proposed reserve movements in Appendix A (Paragraphs 2.8- 2.10) • Note the carry forward of unspent capital budget as set out in Appendix A (Paragraph 5.4)

Executive summary

3.1This report summarises the Council’s financial, procurement and performance position considering service activity up to the end of the fourth quarter, i.e. 31 March 2026.

3.2Detailed analysis is provided in Appendix A (Finance), Appendix B (Procurement) and Appendix C (Performance). 3.3 The position can be summarised as follows:

Subject Headline Reference Finance The Finance headlines at the fourth quarter are: Appendix A Performance against Budget • The General Fund provisional outturn for 2025/26 is a £419,530 underspend after allocation of funding and reserves. Efficiency Programme • £141,480 in efficiencies have been identified in the year – the £267,080 cumulative shortfall on the overall programme rolls forward to the next financial year • Capital Programme • The provisional outturn on the General Fund Capital Programme for 2025/26 is £932,448 underspent compared to a budget of £18million Treasury Management • Cash investments held at the end of the year were £9.4million and external borrowing was £12.1million • Net interest income has a shortfall of £2,187 Revenue Collection at 31 March 2026 • Council Tax 98.36% % (98.40% previous year) • Business Rates 98.77% (99.48% previous year) • Sundry debt over 60 days old £71,034 for 67 invoices (£45,223 previous year, 84 invoices) Procurement The Procurement headlines for the Fourth Quarter are: Appendix B • 8 procurement activities were completed • The Procurement forward plan includes 51 procurement activities for completion/start in 2025/26 (including SMDC and Joint (SM/HP) activity) • Procurement performance to 31 March 2026 was 98% Performance The Performance headlines for the Fourth Quarter are: Appendix C • 79% of the key performance indicator targets were met, with 60% maintained or performing better than in the previous year • The Council closed 173 complaints during the year (122 previous year)

4. How this report links to Corporate Priorities

4.1The successful delivery of all corporate priorities is dependent upon the effective management of performance and financial resources, which is the subject of this report. 5. Alternative Options

5.1Detailed analysis is contained within the main body of the report.

6. Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1 for Fourth Quarter Finance, Procurement Performance ReviewAppendix A 214 KB Download
PDF
2 for Fourth Quarter Finance, Procurement Performance ReviewAppendix A 199 KB Download
PDF
3 for Fourth Quarter Finance Procurement Performance ReviewAppendix A 762 KB Download
PDF
Fourth Quarter: Finance, Procurement & Performance ReportsReport 82 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 20 attended
MG
Councillor Mike GledhillChair, present
DP
Councillor Darren PriceVice-Chair, present
CA
Councillor Charlotte AtkinsCommittee Member, apologies
BC
Councillor Bill CawleyCommittee Member, present
DP
Councillor Dave ProudloveCommittee Member, present
MS
Councillor Matt SwindlehurstCommittee Member, present
CW
Councillor Chris WoodCommittee Member, apologies
NY
Councillor Nigel YatesCommittee Member, present
MD
Member Diary SMDCOfficer, expected
AS
Andrew StokesOfficer, expected
MO
Martin OwenOfficer, expected
AE
Anna EastgateOfficer, expected

All 20 on the meeting page

On this subject at High Peak

Search all
  1. Fourth Quarter - Finance, Procurement & Performance ReportsThis decision
  2. Fourth Quarter Finance, Performance and Procurement UpdateNoted
  3. Fourth Quarter Finance, Performance and Procurement UpdateNoted
  4. Fourth Quarter Financial, Performance and Procurement Review 2024/25Noted
  5. Fourth Quarter Finance Performance and ProcurementNoted
  6. Fourth Quarter - Finance, Procurement & Performance ReportsNoted

More from High Peak Cabinet

All decisions
MeetingDecisionOutcome
11 Aug 2026 Forward PlanDECISION: That the be approved for publication. Approved Open
11 Aug 2026 Climate and Nature Delivery Plan Update - Performance Report October 25 to April 26DECISION: That Cabinet approved the performance report set out in Appendix A. Approved Open
11 Aug 2026 Partial Review Staffordshire Moorlands Local PlanDECISION: 1. That the Staffordshire Moorlands Local Plan Partial Review be approved (attached at Appendix A) for a 6-... Approved Open
11 Aug 2026 Adoption of Market Guidance (Development Management)DECISION: That the Guidance attached at Appendix 1 of the report be approved for use by the Council’s Development Man... Approved Open
11 Aug 2026 Exclusion of the Press and PublicDECISION: “That, pursuant to Section 100A(2) and (4) of the Local Government Act, 1972, the public be excluded from t... Decided Open