Resolved – That the application be deferred - to enable more information to be submitted by the applicant on alternative community uses that could be provided for on site and on any attempts that have been made by the applicants to secure a community use for the site .
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report of the Corporate Director of Planning & Community Services
Address SOUTHBOURNE DAY CENTRE 161 ELLIOTT AVENUE RUISLIP
Development: Erection of a two storey building to provide 23 one and two-bedroom apartments, together with associated parking, involving the demolition of existing day centre building (Outline application).
LBH Ref Nos: 66033/APP/2009/1060
Drawing Nos: 20080009/A/P/01 20080009/A/P/02 20080009/A/P/03 Rev. A 20080009/A/P/04 (illustrative flat layouts) 20080009/A/P/05 Rev. A Design and Access Statement (Revised June 2009) Planning Statement Energy Report (September 2009)
Date Plans Received: 23/04/2009 Date(s) of Amendment(s): 23/04/2009 Date Application Valid: 03/06/2009 26/06/2009 07/08/2009 10/08/2009 18/09/2009 1. SUMMARY Outline planning permission is sought for a residential development comprising 16 x 1 bedroom and 7 x 2 bedroom apartments in one, 2 storey block on the former Southbourne Day Centre site.
The site has been identified as being surplus to requirements in accordance with the Council's Final Strategy for Day and Employment Services and there are no national or regional planning objections in principle to the loss of such a use.
There are no adverse impacts upon the visual amenities of the surrounding area, there would be no loss of residential amenity to surrounding occupiers and highway and pedestrian safety impacts are considered to be acceptable. The application is therefore recommended for approval, subject to conditions and S106/S111 Agreements.
2. RECOMMENDATION 2.1 This authority is given by the issuing of this notice under regulation 3 of the Town and Country Planning General regulations 1992 and shall ensure only for the benefit of the land.
2.2That in advance of, or at the time of the grant of planning permission, the Council as applicant enters into a legal agreement under Section 111 of the Local Government Act 1972 with any proposed purchaser of the Council's interest in the site. That agreement to be completed in advance of or at the same date as any conveyance or transfer of any interest or option to acquire any interest in the site.
North Planning Committee - 6th October 2009 PART 1 - MEMBERS, PUBLIC & PRESS 2.3 The Section 111 legal agreement shall require the purchaser immediately or before acquisition of any interest in the site to enter into an agreement under section 106 of the Town and Country Planning Act 1990, section 16 of the Greater London Council (General Powers) Act 1974, and section 111 of the Local Government Act 1972 in a form annexed to the agreement and/or Section 278 of the Highways Act 1980 (as amended) or other appropriate legislation to secure the following:
(i) A financial contribution of £8,161.96 for healthcare facilities. (ii) The developer provides a financial contribution of £46,331 towards, nursery, primary, secondary and Post 16 school places within the locality of the development to satisfy the educational requirements arising from the child yield resulting from the proposal, in accordance with the Supplementary Planning Document on Planning Obligations adopted in July 2008. (iii) A financial contribution towards training initiatives equal to £2,500 for every £1 million build cost. (iv) A financial contribution of £10,000 towards community facilities. (v) A financial contribution of £866.41 towards library facilities and books (vi) provision of affordable housing equivalent to 9% of the total number of habitable rooms, of which at least 70% are to be of social rented tenure. (vi) The applicants pay a sum to the Council equivalent to 2% of the value of contributions for compliance, administration and monitoring of the completed planning (and/or highways) agreement(s). (vii) The applicants pay a sum to the Council of 3% of the value of contributions for specified requirements to project manage and oversee implementation of elements of the completed planning (and/or highways) agreement(s).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.