Chrysalis Programme - Report to Environmental Improvements Panel
AgreedCommittee10 papers
Environmental Improvements Panel agreed this item on Wednesday 10 February 2010. Below is the council's own wording, with the papers it was decided on.
It was agreed that the following bids be met from the Park Security Budget: Ref No. Project £ UX1006 2 ND Uxbridge Scouts 10,000 UX1014 Coney Green Entrance Improvements 17,000 UX1017 Fencing Railings around Butterfly Garden 11,000 UX1018 Fencing Railings at Benbow Way Entrance to Cowley Recreation Ground 8,000 TOTAL 46,000
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
CHRYSALIS PROGRAMME – REPORT TO ENVIRONMENTAL IMPROVEMENTS PANEL Cabinet Member Councillor Douglas Mills
Cabinet Portfolio Improvement, Partnerships and Community Safety
Officer Contact Maggie Allen and Ian Edwards, Deputy Chief Executive’s Office
Papers with report Appendices A, B and C
HEADLINE INFORMATION
Purpose of report To report progress on 2009/10 Chrysalis projects and to recommend remaining projects for the 2010/11 programme.
Contribution to our The Chrysalis programme contributes and supports activities in plans and strategies relation to the Community Strategy, Green Spaces Strategy and the Local Area Agreement.
Financial Cost The Capital Programme 2009/10 includes a budget of £1 million for the Chrysalis Programme, which has been released from the Capital funds and has been fully allocated.
Expenditure to the end of December 2009 was £438k, equivalent to 43% of the total value of the programme (purchase orders have been raised to a value of £328k).
The latest financial report indicates that there could be an overspend of £46,157, which relates primarily to the cost of schemes started in 2008/09, completing in this financial year. However, steps are being taken to reduce this potential overspend and there is a good level of confidence that it will be significantly reduced.
For 2010/11, the MTFF budget includes a bid of £1 million for the Chrysalis Programme. This budget will be subject to Cabinet and full Council approval in February 2010.
Relevant Policy Residents’ and Environmental Services Overview Committee
Ward(s) affected All
PART 1 – MEMBERS, PUBLIC AND PRESS
Environmental Improvements Panel – 1 February 2010 RECOMMENDATION
That the Panel recommend to the Cabinet Member for Improvement, Partnerships and Community Safety to:
1. Note the progress of the 2009/10 schemes; 2. Approve in principle additional projects in the West for the 2010/11 programme; and 3. Agree the exception report to increase the allocation of the Michael Frost Memorial – Pond Improvement (HH0916).
INFORMATION
2009/10 Projects
In general, projects in the 2009/10 programme are progressing well, with the exception of HH0916 The Michael Frost Memorial Park – Pond Improvement.
Exception Report:
The Michael Frost Memorial – Pond Improvement (HH0916) was initially submitted in 2006 by a member of the local community. It was considered again in 2009/10 and approval was given to fund pond improvements to the value of £15,000. However, the most recent quote is £3k higher than the allocated budget. Recommendation is therefore sought to increase the allocation of this budget by £3k to enable implementation and to avoid further delays.
Several other options have been considered, such as:
(1) Only complete works up to the value of £15k: it is felt this could cost more in the long term as it may jeopardise the quality of the work as only one section of the pond would be completed. (2) Improve the pond in phases: the concern is that it may ultimately cost more to delay the overall implementation due to having to deal with repairs as a result of the incompletion. (3) Do not proceed with implementation: the pond could continue to deteriorate and may result in increased costs in the future as well as community dissatisfaction. (4) To reserve the project until next year: due to the frog-mating season, the project could not be implemented until the beginning of 2011; this could have a negative impact on the Council’s ability to deliver on time, to cost and to quality. It is also possible that reserve funding may not be available as environmental funding in the South has already been allocated.
In reference to the financial report, whilst the overall programme is showing an overspend, we also have the ability to adjust the phasing of projects to ensure there is no overspend this year. The preferred option is therefore to increase the allocation to ensure this work can be delivered within the first quarter of 2010.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.