That Cabinet: Note the forecast budget position for revenue and capital as at Month 2. Note the treasury update at Appendix B. Approves the virement of £80k capital budget from ICT Single Development Plan contingency to the Libraries Refurbishment project. Approves the virement of £810k from E&CS to the Major Construction Projects team in PE&CS to fund the first phase of the Primary capital programme to provide sufficient places for September 2010. Notes the addition of £60k grant funding in the E&CS capital programme to fund ICT to support Looked After Children. Agree to the appointment of interim staff at a cost of £400k as set out in Appendix C which it is anticipated can be funded from within existing budgets. Agree in principle to the appointment of 6 consultants for the South Ruislip Scheme at a cost of £226,887 as set out in Appendix D, and delegates the authority to accept tenders for such consultants to the Cabinet Member for Finance and Business Services, in consultation with the Director of Environment, Planning and Community Services. Reasons for decision The reason for the monitoring recommendation was to ensure the Council achieved its budgetary objectives. The report informed Cabinet of the latest forecast revenue and capital position for the current year 2010/11. Cabinet also approved expenditure in relation to its financial controls on individual interim staff and consultants with a projected cost of over £50k. Alternative options considered and rejected None Officers to action: Paul Whaymand / Christopher Neale , Finance and Resources
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
That Cabinet: 1. Note the forecast budget position for revenue and capital as at Month 2. 2. Note the treasury update at Appendix B. 3. Approves the virement of £80k capital budget from ICT Single Development Plan contingency to the Libraries Refurbishment project. 4. Approves the virement of £810k from E&CS to the Major Construction Projects team in PE&CS to fund the first phase of the Primary capital programme to provide sufficient places for September 2010. 5. Notes the addition of £60k grant funding in the E&CS capital programme to fund ICT to support Looked After Children. 6. Agree to the appointment of interim staff at a cost of £400k as set out in Appendix C which it is anticipated can be funded from within existing budgets. 7. Agree in principle to the appointment of 6 consultants for the South Ruislip Scheme at a cost of £226,887 as set out in Appendix D, and delegates the authority to accept tenders for such consultants to the Cabinet Member for Finance and Business Services, in consultation with the Director of Environment, Planning and Community Services.
Cabinet Report – 15 July 2010 INFORMATION Reasons for Recommendations 1. The reason for the monitoring recommendation is to ensure the Council achieves its budgetary objectives. The report informs Cabinet of the latest forecast revenue and capital position for the current year 2010/11.
2. New controls introduced on interim staff require individual interim staff with a projected cost of over £50k to be approved by Cabinet. Agency spend for the year to date shows a 19% reduction from that incurred to the same point last year (which also showed a reduction on the previous year). This has been achieved as a result of continued efforts to review the use of interim staffing given the financial pressures on the authority.
Alternative options considered
3. There are no other options proposed for consideration.
SUMMARY A) Revenue
4. The in year revenue monitoring position as at Month 2 (May) shows that forecast net expenditure for the year 2010/11 is £1,440k more than the budget. This is primarily due to the in-year government grant cuts of £3.6m recently announced which have been treated an exceptional item and are explained in more detail below. The forecast outturn on normal activities is an overspend of £15k. There are a number of significant pressures forecast in services. These primarily relate to pressures that were forecast when the budget was set and are provided for in contingency. However, the demographic pressure on Older Peoples Services is significantly higher at this stage of the year than was provided for in contingency.
5. The monitoring position incorporates the financial impact of the Coalition Government’s announcement on local government in-year grant reductions for 2010/11. The cuts notified are in Area Based Grant (£1.8m), Housing and Planning Delivery Grant (£0.1m), LAA Reward Grant (£1.8m) and LABGI (£0.4m). The net impact of the reductions in grant on the Council’s current year budget is £3.6m and this has been treated as an exceptional pressure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.