Resolved
Resolved – That the application be approved as set out in the officer’s report.
North Planning Committee approved this item on Thursday 5 August 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the application be approved as set out in the officer’s report.
Report of the Head of Planning & Enforcement Services
Address HAREFIELD HOSPITAL HILL END ROAD HAREFIELD
Development: Erection of 1 single storey temporary hospital building and clinical waste bin store, involving demolition of existing temporary office and clinical waste bin store.
LBH Ref Nos: 9011/APP/2010/1120
Drawing Nos: P10-001 P10-004A P10-002 P10-005 P10-003 P20-002 P20-001 P20-003 P30-001 Design and Access Statement Supporting Planning Statement Arboricultural Impact Assessment by GBA
Date Plans Received: 18/05/2010 Date(s) of Amendment(s): Date Application Valid: 10/06/2010 1. SUMMARY Planning permission is sought to replace an existing temporary building with linking corridors, together with the removal and re-siting of a clinical bin store for a limited 2 year period.
The foot print of the proposed temporary building is larger than that of the existing building which it would replace, however it is considered to satisfactorily integrate with the existing building without causing material harm. It should also be noted that the propsed siting is amongst existing buildings which is not considered to result in an adverse impact on the wider area.
With regard to the clinical bin store this would be re-sited between two existing temporary buildings and therefore views of this development would be limited.
It is not considered the proposed development would result in any adverse impact on the Colne Valley Park or the Conservation Area. Furthermore, the development would not result in a disproportionate change or a material increase in the built up appearance of the site and as such it is considered to comply with the all the relevant policies contained in the UDP (Saved Policies September 2007) and the advice contained in PPG2: Green Belts.
Planning permission is sought for a limited 2 years period, as such, it is considered once this has elapsed these buildings can be removed and the land and buildings re-instated, as it is anticipated the development of permanent ward accommodation and other new facilities at Harefield hospital will have progressed.
North Planning Committee - 5th August 2010 PART 1 - MEMBERS, PUBLIC & PRESS 2. RECOMMENDATION APPROVAL subject to the following:
1 NONSC Limited time permission The buildings hereby permitted shall be removed and the land and the existing building restored to their former condition on or before 2 years from the date of this permission, in accordance with a scheme of work submitted to and approved in writing by the Local Planning Authority.
REASON The proposed buildings are not acceptable as a permanent feature of the site, by reason of their design, size and location. The long term retention of these buildings would not make a positive contribution to the character and appearance of Harefield Village Conservation Area, or the Green Belt, and would therefore be contrary to Policies BE4 and OL4 of the Unitary Development Plan (Saved Policies September 2007).
2 NONSC Restriction on use The buildings hereby approved shall be used for purposes solely in connection with the functioning of the Hospital and for no other purpose which is independent of and unrelated to the Hospitals activities.
REASON To ensure that no occupier independent of the Hospital becomes established on the site and to comply with Policy PR20 of the Unitary Development Plan (Saved Policies September 2007).
3 NONSC Strict accordance with plans The development hereby approved shall be carried out in strict accordance with the submitted application documents, except where expressly varied by other conditions of the consent
REASON To maintain control over the development, which is located within the Green Belt and the Harefield Village Conservation Area to comply with Policies OL1, OL4 and BE4 of the Unitary Development Plan (Saved Policies September 2007).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Harefield Hospital, Hill End Road, Harefield, 9011/APP/2010/1120Report | 20 pages | DownloadRead as text |
Follow North Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 May 2021 | To sign and receive the minutes of the previous meeting dated 21 April 2021That the minutes of the meeting dated 21 April 2021 be approved as an accurate record. | Approved | Open |
| 19 May 2021 | Extending Written Representations in Lieu of Physical Speaking RightsRECOMMENDATION (MOTION) That the Committee agreed to permit those parties with valid speaking rights at planning comm... | Agreed | Open |
| 19 May 2021 | 59 Elm Avenue, Eastcote - 60130/APP/2020/4166That the application be refused as per officer’s recommendation. | Refused | Open |
| 19 May 2021 | 77 St George's Drive, Ickenham - 12943/APP/2021/589That the application be refused as per officer’s recommendation. That the application be refused as per officer’s rec... | Refused | Open |
| 19 May 2021 | Telecommunications Windmill Hill, Ruislip Manor - 75613/APP/2021/1383That the application be refused. | Refused | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.