Resolved- 1. That the in year progress against the Internal Audit Plan for 2010/11 and the updated position of those audits undertaken in 2007-8, 2008-9 and 2009-10 be noted.
Audit Committee noted this item on Thursday 10 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved- 1. That the in year progress against the Internal Audit Plan for 2010/11 and the updated position of those audits undertaken in 2007-8, 2008-9 and 2009-10 be noted.
Internal Audit Progress Report
Contact Officer: Helen Taylor Telephone: 01895 556132 REASON FOR ITEM
This report provides the Audit Committee with a summary of Internal Audit (IA) activity in the period from 20 November 2010 to 31 January 2011. This fulfils the requirements of CIPFA’s Code of Practice for Internal Audit in Local Government to bring to Members’ attention periodic reports on progress against planned activity and any implications arising from Internal Audit findings and opinions.
The report also satisfies the Audit Commission requirements to keep Members adequately informed of the work undertaken by Internal Audit and of any problems or issues arising from audits
OPTIONS AVAILABLE TO THE COMMITTEE
To note in-year progress against the Internal Audit Plan for 2010-11, and the updated position of those audits undertaken in 2007-8, 2008-9 and 2009-10.
1. INFORMATION 1.1. In addition to the Annual Report, the Head of Internal Audit produces interim reports to Officers and Members throughout the year. These are approximately quarterly, summarise progress to date and bring to the attention of members any issues of note.
2. Progress against Plan and Follow up Status
2.1There are no significant causes for concern at this time with the levels of assurance being reported to the committee. Only one audit, a junior school, received Limited assurance in the current report and plans are in place to address the weaknesses identified. All other audits had Satisfactory assurance with one audit having Full Assurance.
2.2The current status of this year’s plan in included in Appendix 1.
2.3The progress and status of those carried out in 2007-8, 2008-9 and 2009-10 is included in Appendices 2, 3 and 4.
2.4As anticipated when setting the plan, a number of changes have been made to accommodate the changing needs of the council.
2.5The following audits have been deleted from the current plan.
Audit Committee Date 10 March 2011 PART 1 – MEMBERS, PUBLIC & PRESS Healthy Hillingdon – The Health and Social Care Bill is currently passing through Parliament and this legislation intends to abolish Primary Care Trusts (PCTs) and transfer local health improvement functions from PCTs to local authorities. It would also give local authorities responsibilities for coordinating the commissioning of local NHS services, social care and health improvement. With these major changes coming in, the audit has been deferred until 2011/12.
Carbon Reduction Strategy –The Government has announced changes to the Carbon Reduction Commitment Scheme (CRC) which will delay implementation until 2012.
Utilities – Water – This audit was included in the 2010/11 plan as it was anticipated that management would have implemented an action plan that had a dedicated focus on reducing water usage within the borough agreed following the 2009-10 audit. In planning the 2010-11, it became clear that the recommended actions would not be fully in place until March 2010. The audit has therefore been deferred until 2011-12.
Primary Schools – 5 schools, Belmore Primary, Charville Primary, Harlyn Primary, Field End Junior and Hillside Junior were audited in 2009-10 and were erroneously included in the plan reported to audit Committee in March 2010. Time allocated was utilised in a major investigation.
Taxes Management Act – Generally Her Majesty’s Revenues and Customs request certain information from local authorities under the Taxes Management Act 1970 on an annual basis. However, no information was requested in 2010-11 We have had no indication that HMRC will require this information in future years and have therefore removed it from the audit universe.
2.6During the period, the following audits were added to the plan:-
Agency Car Mileage – Added as there were concerns over how agency car mileage claims were checked and authorised.
Estate Services Contracts – This audit was included in the Hillingdon Homes plan by their internal auditors but was outstanding when Housing Management returned to the Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress ReportReport | 240 KB | DownloadRead as text |
Follow Audit Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Feb 2026 | Minutes of the Meeting held on 18 November 2025That the minutes of the previous meeting be agreed as a correct record | Agreed | Open |
| 10 Feb 2026 | Counter Fraud Progress ReportThat the Audit Committee noted the for 2025/26 Quarter 3 | Noted | Open |
| 10 Feb 2026 | Counter Fraud Operational WorkplanThat the Audit Committee noted the Counter Fraud Annual Operational Plan for 2026/27 | Noted | Open |
| 10 Feb 2026 | Work ProgrammeThat the Audit Committee noted the dates for Audit Committee meetings | Noted | Open |
| 18 Nov 2025 | Minutes of the Meeting held on 28 August 2025That the minutes of the previous meeting be agreed as a correct record | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.