Resolved
Resolved – That the application be approved as set out in the officer’s report and addendum.
North Planning Committee approved this item on Tuesday 15 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the application be approved as set out in the officer’s report and addendum.
Report of the Head of Planning & Enforcement Services
Address 1-8 (INCLUSIVE), BREAKSPEAR MEWS BREAKSPEAR ROAD NORTH HAREFIELD
Development: Regularisation of building work that has already been carried out within Units 1 and 2, involving the removal of two courtyard dormers and completion of the car ports.
LBH Ref Nos: 7902/APP/2009/2480
Drawing Nos: Design and Access Statement 113/2009/01A 113/2009/05A 113/2009/02A 113/2009/03A 113/2009/04A 113/2009/06A
Date Plans Received: 16/11/2009 Date(s) of Amendment(s): Date Application Valid: 01/12/2009 1. SUMMARY This application seeks to reglarise the planning situation relating to numbers 1 and 2 Breakspear Mews, as the works were not carried out in accordance with the approved drawings attached to planning permission ref: 7902/D/96/1275.
The remedial works include the removal of 2 dormer windows facing onto the courtyard above the uncompleted car ports and completion of the car ports to provide 4 covered parking spaces, as per the original consent. The application also seeks to retain the variations to the approved scheme involving the retention of 5 court yard dormers and modifications to the roof, to provide one additional bedroom in the roof space of each unit. Given that the application site falls within the curtilage of the Grade I Listed Building, Listed Building Consent is also required for the proposal.
The principle of residential development on this site has already been established by virtue of the Secretary of State's grant of planning permission, for the conversion of Breakspear Stables to 6 residential units. The impact of the proposals on the Green Belt compared with the previous approval will be negligible, whilst the proposed modifications would not result in a detrimental impact on the street scene, on the setting of the Grade 1 listed Breakspear House or the Harefield Village Conservation Area.
It is not considered that the proposal would detract from the amenities of neighbouring occupiers, whilst the proposed development would provide good living conditions for all of the affected units.
No objections are raised on highway grounds. The proposed access arrangements and parking provision will remain the same as the approved scheme.
Should the current modifications be approved, it is considered that the current breach in planning control would have been addressed and there will be no requirement to pursue further enforcement action in relation to Units 1 and 2.
North Planning Committee - 15th March 2011 PART 1 - MEMBERS, PUBLIC & PRESS 2. RECOMMENDATION APPROVAL subject to the following:
1 NONSC Non Standard Condition This planning permission is granted subject to the following stipulations:
(i) A timetable for the substantial completion of the development permitted by this decision notice shall be submitted for the approval in writing by the Local Planning Authority within 3 months of the date of this notice of planning permission; (ii) The timetable for the substantial completion of the development hereby permitted by this decision shall not exceed a 6 month period from the date of the Local Planning Authority's approval of the timetable, to the last day of the substantial completion of the development permitted by this decision notice. (iii) If within 6 months of the date of this planning permission, the Local Planning Authority refuse to approve or do not determine the timetable within the prescribed period, a valid appeal shall have been made to the Secretary of State; (iii) If an appeal is made in pursuance of (iii) above, the development herby permitted by this decision shall be substantially completed in accordance with the time table approved by the Secretary of State.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
1-8 (Inclusive), Breakspear Mews, Breakspear Road North, Harefield 7902/APP/2009/2480Report | 138 KB | DownloadRead as text |
Follow North Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 May 2021 | To sign and receive the minutes of the previous meeting dated 21 April 2021That the minutes of the meeting dated 21 April 2021 be approved as an accurate record. | Approved | Open |
| 19 May 2021 | Extending Written Representations in Lieu of Physical Speaking RightsRECOMMENDATION (MOTION) That the Committee agreed to permit those parties with valid speaking rights at planning comm... | Agreed | Open |
| 19 May 2021 | 59 Elm Avenue, Eastcote - 60130/APP/2020/4166That the application be refused as per officer’s recommendation. | Refused | Open |
| 19 May 2021 | 77 St George's Drive, Ickenham - 12943/APP/2021/589That the application be refused as per officer’s recommendation. That the application be refused as per officer’s rec... | Refused | Open |
| 19 May 2021 | Telecommunications Windmill Hill, Ruislip Manor - 75613/APP/2021/1383That the application be refused. | Refused | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.