That Cabinet agree to modify the date for meeting the condition of obtaining planning permission, from 15th April 2011 to a new date of 1st July 2011. Reasons for decision Cabinet noted that its decision last year on statutory proposals to enlarge several primary schools, including Whitehall Infant and Junior Schools, was conditional on obtaining planning permission. Cabinet therefore agreed to extend the date for planning permission to deliver the school expansion programme on time. Alternative options considered and rejected Cabinet could have decided not to extend the conditional date and thereby put at risk the provision of sufficient primary school places in the Uxbridge North, Uxbridge South and Brunel wards. Officer to action: Terry Brennan -Planning Environment, Education & Community Services
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
That Cabinet agree to modify the date for meeting the condition of obtaining planning permission, from 15th April 2011 to a new date of 1st July 2011.
INFORMATION
Reasons for recommendation
In November 2010, Cabinet conditionally approved statutory proposals to enlarge several primary schools, including Whitehall Infant and Junior Schools. In accordance with school organisation regulations, each proposal was approved on condition of obtaining planning permission. The date for this condition to be met by was set as April 15th 2011 for each proposal.
However, there is now a risk that the Whitehall Infant and Junior School proposals may not meet this condition by the required date. It is therefore necessary to seek a modification to that condition. The recommendation is to set a later date of July 1st 2011.
Cabinet Report – 17 March 2011 Alternative options considered / risk management
The condition of obtaining planning permission must be met by April 15th 2011. This now carries a risk, and if the condition is not modified then the statutory proposals could be challenged and could become invalid. In such circumstances there could be a risk of insufficient primary school places in the Uxbridge North, Uxbridge South, and Brunel wards.
In accordance with school organisation regulations, permission can be sought from the original decision maker (Cabinet) to review a condition and modify the date for that condition to be met.
Comments of Policy Overview Committee(s)
None at this stage.
Supporting Information
1. The proposals for the Whitehall schools have been controversial, drawing substantial local opposition. Many issues can be resolved at the planning application stage. Carefully addressing each concern has contributed to the delay in submitting the final planning application, and this delay has created the risk of missing the conditional date for obtaining planning consent.
2. Paragraph 4.76 of the school organisation regulations ('Expanding a Maintained Mainstream School by Enlargement or Adding a Sixth Form') explains that the decision maker can amend conditions upon request from the proposers. Such a request is contained in this report.
3. The reasons for enlarging Whitehall Infant and Junior Schools were contained in the report to Cabinet on 18th November 2010, following a period of statutory consultation. The proposals were approved, with three separate conditions each to be met by April 15th 2011:
(a) that the Office of the Schools Adjudicator approves a variation to the school's published admission number for September 2011. (The final OSA decision on this condition will be announced in early March 2011. In the meantime, the OSA has now approved the principle of the expansion, following an appeal by the schools).
(b) that the relevant admissions authority determines a higher published admission number for September 2012. (As the OSA has upheld the council's decision to expand the schools, this condition will be met because the Local Authority is the admissions authority).
(c) that the necessary planning permissions are granted. (There is now a risk that this condition will not be met by the required date).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.