That Cabinet: 1. Notes the progress made on phases 1a, 1, 2 and 3 of the primary schools capital programme of works; 2. Instructs officers to progress with Phase 2 expansions detailed in this report to Stage D, within capital released approved at Cabinet on 26 May 2011; 3. Delegates authority to the Leader of the Council and Cabinet Member for Finance, Property and Business Services, in consultation with the Deputy Chief Executive and Director of Planning, Environment, Education and Community Services to place a building contract for Phase 2A temporary units within granted capital release and; 4. Agrees to release £2,443K of capital funds in order to progress recommendation 3 above. Reason for decision Cabinet welcomed the update on the primary school capital programme and noted that the Council was on track to deliver sufficient primary school places for local children over the short, medium and long term. Cabinet made a number of decisions to provide the necessary authority, flexibility and resources to progress Phase 2 and also noted the latest position on all other phases of the programme , in particular the new schools proposed at Lake Farm and RAF Uxbridge. The Leader of the Council and Cabinet Member for Finance, Property and Business Services agreed to refer to Cabinet their joint delegation to approve the release of capital funds. Alternative options considered and rejected Cabinet could have decided to delay or not progress aspects of the building programme , which would have impacted upon the Council’s ability to provide sufficient school places. Officer to action: Boe Williams- Obasi , Planning, Environment, Education and Community Service Urgency Provisions This report had been circulated less than 5 working days before the Cabinet meeting and was agreed by the Chairman to be considered as urgent.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Officer Contact Boe Williams-Obasi Planning, Environment, Education and Community Services
Papers with report This report is linked to item 14 which is included within Part 2 of the Cabinet agenda.
HEADLINE INFORMATION
Cabinet receives regular update reports to progress the primary school capital programme. Members will be pleased to note that the Council is on track to deliver sufficient primary school places for local children over the short, medium and long term
In this report, Cabinet is being asked to note the progress on Phase 1, 1a and 3 and also make decisions to:
1. Progress with Phase 2 expansions to stage D; 2. Delegate authority to Cabinet Members to award contracts for Phase 2A temporary units and; 3. Approval additional capital release funds.
Contribution to our Investment in primary schools to adequately address the impact of plans and strategies population increase within the Council on existing school places. This project also forms part of the Hillingdon Improvement Programme.
Financial Cost This report seeks £2,443k capital release to progress provision of temporary primary provision for September 2012 and provides an update on the wider £128m primary school expansion programme
Relevant Policy Education and Children’s Services Overview Committee
Ward(s) affected All wards will benefit from the primary schools programme.
Cabinet Report – 27 October 2011 RECOMMENDATIONS
That Cabinet:
1. Notes the progress made on phases 1a, 1, 2 and 3 of the primary schools capital programme of works;
2. Instructs officers to progress with Phase 2 expansions detailed in this report to Stage D, within capital released approved at Cabinet on 26 May 2011;
3. Delegates authority to the Leader of the Council and Cabinet Member for Finance, Property and Business Services, in consultation with the Deputy Chief Executive and Director of Planning, Environment, Education and Community Services to place a building contract for Phase 2A temporary units within granted capital release and;
4. Agrees to release £2,443K of capital funds in order to progress recommendation 3 above*1.
INFORMATION
Phase 1 (Permanent Expansions)
Phase 1 of the Primary School Capital Programme comprises expansion projects at 6 schools. 4 school expansion projects are currently on-site:
• Brookside Primary • Cranford Park Primary • Colham Manor Primary • William Byrd Primary
There has been some slippage moving forward the construction due to a 4 week delay in steel procurement at the outset. This does not present a critical operational issue for the schools, as the space will still be provided ahead of the start of the term it is needed for.
The remaining 2 schools - Grange Park Infant and Junior and Whitehall Infant and Junior - are currently being revisited at the planning application stage following further discussions with the schools involved. The aim is to commence on site with these projects in December 2011/ January 2012.
*1 The Leader of the Council and Cabinet Member can refer to Cabinet their joint delegation to approve all capital release.
Cabinet Report – 27 October 2011 • Pinkwell • Rosedale
Phase 1A of Rosedale, Harlyn, Highfield, Glebe and Belmore have all now been completed and the schools were fully operational for the start of the new September term.
Planning consent for the temporary classrooms has already been granted for both Pinkwell and Rosedale. The opening ceremony for Rosedale School took place on 6 September with very positive feedback from the school and governing body on programme delivery.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.