Month 7 2011/12 Revenue and Capital Monitoring Report

Noted Executive 1 paper

CABINET noted this item on Thursday 15 December 2011. Below is the council's own wording, with the papers it was decided on.

Item449

Resolved

That Cabinet: 1. Note the forecast budget position for revenue and capital as at Month 7 2. Note the treasury Month 7 update at Appendix B 3. Approve the retaining of agency staff as detailed in Appendix C 4. Approve the rephasing of capital budgets 5. Delegate authority to the Leader of the Council and Cabinet Member for Finance, Property and Business Services, in consultation with the Deputy Chief Executive and Corporate Director of Planning, Environment, Education and Community Services, to appoint consultants for the Supported Housing Programme in order to action the Cabinet decision of 28 July 2011. Reasons for decision Cabinet received an update on the Council’s strong financial position and made a number of necessary decisions in relation to agency staff, the re-phasing of the Council’s capital programme and consultancy approvals to progress the Supported Housing Programme . Alternative options considered and rejected None. Officer to action: Paul Whaymand , Central Services
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to CABINET, 24 pages

Recommendations

That Cabinet:

1. Note the forecast budget position for revenue and capital as at Month 7 2. Note the treasury Month 7 update at Appendix B 3. Approve the retaining of agency staff as detailed in Appendix C 4. Approve the rephasing of capital budgets

INFORMATION Reasons for Recommendations 1. The reason for the monitoring recommendation is to ensure that the Council achieves its budgetary objectives. The report informs Cabinet of the latest forecast revenue and capital position for the current year 2011/12.

2. Recommendation 4 seeks authority to rephase capital budgets, forming the basis for the 2012/13 capital programme and remove budgets previously allocated to cancelled projects.

Cabinet – 15 December 2011 Alternative options considered

3. There are no other options proposed for consideration.

SUMMARY A) Revenue

4. The in year revenue monitoring position as at Month 7 (October) shows that forecast net expenditure for the year 2011/12 is £2,349k less than the budget, a £288k improvement on Month 6. There is a £99k forecast underspend on directorate budgets comprising a pressure of £998k (£182k adverse movement) in SCH&H, offset by a £209k underspend (£127k favourable movement) in PEECS, a £305k underspend (£53k favourable) in Central Services and a £583k (£40k favourable) underspend on contingency. The remaining overspend is offset by the projected underspend in capital financing costs of £2,250k (£250k favourable) due to budgets set aside in advance for schools capital financing and other priority projects, which are not forecast to be needed in this financial year.

5. Although the budget position is showing an underspend there are still significant budgetary risks remaining. The Government consulted over the summer on potentially further top-slicing local authority revenue support grant to fund a national shortfall in funding for Academy schools. The consultation indicated that they were considering applying this top-slice in the current financial year as well as ongoing. If the Government go ahead with top-slicing in-year this could worsen the current year’s budget position by up to £1.3m.

6. The balances brought forward at 31st March 2011 were £17,022k. £1,793k of this sum was applied in support of the 2011/12 budget as part of the budget strategy, as agreed at Council Tax setting. The forecast balances as at 31st March 2012 are £17,578k (an improvement of £288k on month 6), as a result of the budgeted drawdown from balances (-£1,793k) and the forecast in-year underspend (£2,349k).

B) Capital

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Month 7 2011/12 Revenue and Capital Monitoring ReportReport 24 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
RP
Councillor Raymond PuddifootChair, present
DS
Councillor David SimmondsVice-Chair, present
JB
Councillor Jonathan BiancoCommittee Member, present
KB
Councillor Keith BurrowsCommittee Member, present
PC
Councillor Philip Corthorne MIPDCommittee Member, present
HH
Councillor Henry HigginsCommittee Member, present
DM
Councillor Douglas MillsCommittee Member, present
SS
Councillor Scott Seaman-DigbyCommittee Member, present

On this subject at Hillingdon

Search all
  1. Month 7 2011/12 Revenue and Capital Monitoring ReportThis decision
  2. Council Budget 2019/20: Revenue and Capital Monitoring - Month 4Noted
  3. Council Budget: 2018/19 Revenue and Capital Month 4 Budget Monitoring ReportNoted
  4. Council Budget - 2015/16 Month 6 Revenue and Capital Budget MonitoringNoted
  5. Council Budget - 2015/16 Month 5 Revenue and Capital Budget MonitoringNoted
  6. Council Budget - Month 6 Revenue and Capital monitoringNoted

More from Hillingdon CABINET

All decisions
MeetingDecisionOutcome
19 Nov 2026 Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt... Approved Open
19 Nov 2026 Strategic Review of Library Services and Future Delivery ModelThat Cabinet: 1) Approves the launch of the Strategic Review of Library Services and Future Delivery Model, the devel... Approved Open
19 Nov 2026 Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T... Agreed Open
19 Nov 2026 Old Vinyl Factory, Hayes: Conservation Area AppraisalThat Cabinet: 1) Duly considers the public consultation responses to the draft Appraisal for The Old Vinyl Factory Co... Approved Open
19 Nov 2026 Carers Strategy UpdateThat Cabinet: 1) Note the report and agree that officers bring forward an annual progress report to Cabinet on suppor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies