Land at 37 - 45 Ducks Hill Road, Northwood 59214/APP/2013/848
RefusedPlanning1 paper
Major Applications Planning Committee refused this item on Thursday 13 June 2013. Below is the council's own wording, with the papers it was decided on.
Resolved – That the application be refused for the following reasons:- The proposal, by reason of its position, size, scale, bulk and design would result in a visually obtrusive development that would be detrimental to the character and appearance of the overall development and to the amenities of the occupier of Plot 7 by reason of visual intrusion, overdomination and loss of outlook. The proposal is thus contrary to Policy BE1 of the Hillingdon Local Plan: Part One - Strategic Policies (November 2012) and Policies BE13, BE19 and BE21 of the Hillingdon Local Plan: Part Two - UDP Saved Policies (November 2012).
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report to Major Applications Planning Committee, 21 pages
Report of the Head of Planning, Sport and Green Spaces
Address LAND AT 37-45 DUCKS HILL ROAD NORTHWOOD
Development: Variation of Condition 4 (Approved Drawings) to allow study/games room to be provided for Plot 8 within the roofspace of the detached triple garage serving Plots 6, 7 and 8, involving replacement of a hip end with a gable roof, installation of two rear dormers and an external staircase of planning permission granted 16/11/10, ref. 59214/APP/2010/1776: Erection of 8 detached and 6 semi-detached dwellings with associated access, parking and landscaping.
LBH Ref Nos: 59214/APP/2013/848
Drawing Nos: 1834/PL07 Rev. C 1834/PL14 1834/PL15 1834/PL16 1834/PL17 DS19080901.04 Rev. B Design & Access Statement Transport Statement dated 20/07/10 Tree Survey Report, dated 28/08/09 Arboricultural Assessment and Arboricultural Method Statement, dated 15/10/10 Phase 1 Ecological Survey, June 2010 Phase 2 Ecological Survey (Bat and Reptiles), August 2010 Low and Zero Carbon Technologies Options Appraisal, Final Report, July 2010 Land Registry Documents Letter dated 07/10/10 Reptile Mitigation Strategy to address the requirements of Condition 26 of Planning Permission 59214/APP/2010/1776, dated October 2012 1834/PL302 1834/PL13 1834/PL01 Rev. C 1834/PL02 Rev. B 1834/PL03 Rev. A 1834/PL04 Rev. A 1834/PL05 Rev. B (Detached garage elevations have been superseded by 1834/PL302) 1834/PL08 Rev. A 1834/PL09 Rev. A 1834/PL10 Rev. B 1834/PL00 Rev. A 1834/PL11 Rev. A 1834/PL12 Rev. A Agent's letter dated 05/04/13
Date Plans Received: 05/04/2013 Date(s) of Amendment(s): 25/08/2010 Date Application Valid: 09/04/2013 21/10/2010 12/10/2010
Major Applications Planning Committee - 13th June 2013 PART 1 - MEMBERS, PUBLIC & PRESS 05/04/2013 18/10/2010 22/10/2012 26/10/2010 30/07/2010
1. SUMMARY This application seeks to vary Condition 4 (Approved Plans) to allow the roof of the detached triple garage serving Plots 6, 7 and 8 to be gable ended, as opposed to being hipped and for two small dormers to be installed on the eastern (rear) elevation with the enlarged roof space providing a study/games room serving Plot 8 which would be accessed by an external staircase on the southern side elevation.
It is considered that the changes would not materially affect the character and appearance of the area and the amenities of adjoining residential properties would not be adversely affected. The application is recommended for approval. 2. RECOMMENDATION That subject to no additional responses being received that raise relevant material planning considerations that have not already been considered in this report, delegated powers be given to the Head of Planning, Sport and Green Spaces to grant planning permission, subject to the following:
(i) A financial contribution of £117,713 for education facilities and places (ii) A financial contribution of £11,678.51 for healthcare facilities and places. (iii) A financial contribution of £20,000 towards community facilities/the public realm. (iv) A financial contribution of £1,239.70 towards libraries. (v) A financial contribution towards training initiatives equal to £2,500 for every £1 million build cost. (vi) The applicants pay a sum to the Council of 5% of the value of contributions for specified requirements to project manage and oversee implementation of elements of the completed planning (and/or highways) agreement(s). (vii) The applicant shall agree to the full and complete costs to undertake the necessary works, as identified by the Council, for off site highway works, including: a) Junction improvements to the site access with Ducks Hill Road (viii) Agreement that if the applicant implements this permission, they will not implement permission 59214/APP/2005/951 or any part there of.
2. That in respect of the application for planning permission, the applicant meets the Council's reasonable costs in the preparation of the S106 Agreement and any abortive work as a result of the agreement not being completed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Major Applications Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.