Budget Planning Report for Residents Services 2014/15
NotedScrutiny1 paper
Residents, Education and Environmental Services Policy Overview Committee noted this item on Wednesday 31 July 2013. Below is the council's own wording, with the papers it was decided on.
That: The January 2014 Budget report be provided as early as possible within the existing schedule. Andy Evans provide the breakdown of the £30m balances that the Council held and what proportion of this was made up of savings from Residents Services. The Committee noted the 2014/15 Budget Planning Report.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report to Residents, Education and Environmental Services Policy Overview Committee, 4 pages
BUDGET PLANNING REPORT FOR RESIDENTS SERVICES 2014/15
Contact Officer: Andy Evans Telephone: 01895 250994
REASON FOR ITEM
This is the first opportunity for the Policy Overview Committee to discuss the current stage of development of budget planning work with regard to Residents Services (excluding Housing & Education). Within the context of the Council’s overall financial position, this paper sets out the main financial issues facing the Group’s services and the work being undertaken to respond to them. This paper gives a strategic context in which the detailed proposals to be discussed at Policy Overview Committee meetings in January 2014 will need to be considered.
OPTIONS AVAILABLE TO THE COMMITTEE
It is recommended that the Committee notes the development of the financial planning process undertaken to date and comments as appropriate on the response to the issues being developed by the Group.
INFORMATION
1 This is the first of two opportunities within the planning cycle for the Policy Overview Committee to consider issues relating to budget planning for 2014/15. The focus of this report is the major issues that have been identified through the service and financial planning process for Residents Services. The report to be considered in January 2014 will set out the detailed budget proposals for the Group, those proposals having been included in the report to Cabinet on the Medium Term Financial Forecast (MTFF) on 19 December 2013.
Corporate Summary
2 While the focus of the discussion for the Policy Overview Committee should be the specific services within its remit, it is important that this discussion is conducted in the context of the overall corporate financial position.
3 The Comprehensive Spending Review 2010 set out the financial challenge facing local government over the following four year period, the last of which is 2014/15. Whilst the initial assessment of the CSR suggested that the cuts were heavily front loaded in the first two years, it has since become apparent that the estimates on which the CSR was based were over optimistic and the period of austerity will continue for a significantly longer period, potentially until 2018 or later. The budget report to Council in February 2013 identified the savings requirement for 2014/15 as £17.0m and work is currently underway to refresh this figure. Whilst the finance settlement announced in December 2012 was for a two year period, the figures for 2014/15 were indicative rather than confirmed at that time. The budget in March introduced a further 1% cut for 2014/15, however, until the final settlement is announced towards the end of the year the final funding position will not be clarified.
4 In addition, there is significant other uncertainty within the budget for next year both from changes introduced in 2013 and from the ongoing welfare reforms:
• The responsibility of public health transferred to local government on 1 April 2013 and significant work remains outstanding in the allocation of that funding. • Council Tax benefit was abolished on 1 April 2013 and replaced with a local Council Tax Reduction scheme with a 10% cut in funding. The new scheme has only been in operation for just over 3 months and so the impact on Council Tax revenue is unclear. • The retention of business rates commenced in April 2013 giving local authorities a stake in the generation of additional business rates income. However, the system is sensitive to changes in the rateable value of the Borough and at this early stage of the year it is not easy to predict the impact on next year’s funding. • Central Government are introducing significant Welfare Reforms including Universal Credit, under occupancy and the Benefit Cap all of which are forecast to impact significantly on Council services and on budgets. Early indications of budget pressures are starting to emerge in Month 2 monitoring. • A reform of education funding is also expected, but details on this scheme are not yet available.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Residents, Education and Environmental Services Policy Overview Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.