The Arena, Stockley Park, Stockley Road, West Drayton 37800/APP/2013/161
RefusedPlanning1 paper
Major Applications Planning Committee refused this item on Wednesday 7 August 2013. Below is the council's own wording, with the papers it was decided on.
That subject to the Mayor not directing the Council under Article 6 of the Town and Country Planning (Mayor of London) Order 2008 to refuse the application, or under Article 7 of the Order that he is to act as the local planning authority for the purpose of determining the application; AND subject to the Environment Agency formally withdrawing their objection, delegated powers be given to the Head of Planning, Green Spaces and Culture to grant planning permission subject to the conditions set out in the officer’s report and any additional conditions and/or informatives which may be required by the Mayor or the Environment Agency. 2. That subject to the changes in the Addendum sheet circulated at the meeting, additional Condition requiring provision of 1 electric vehicle charging point and amendment to Condition 16 to ensure spaces were allocated to the various retail users.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report to Major Applications Planning Committee, 29 pages
Report of the Head of Planning, Sport and Green Spaces
Address THE ARENA, STOCKLEY PARK STOCKLEY ROAD WEST DRAYTON
Development: Development of Stockley Arena to provide additional office accommodation, including a single-storey extension to the central rotunda and to the southern wing to create a new second floor, together with a two-storey extension above the existing refuse storage and deliveries area to the north.
LBH Ref Nos: 37800/APP/2013/161
Drawing Nos: Heritage Statement - December 2012 Transport Statement - January 2013 Air Quality Assessment - January 2013 Planning Statement - January 2013 Planning Review - January 2013 Energy Statement - 22/02/2013 SBEM L2A Compliance Report - 22/02/2013 198-102 P1 198-001 P2 198-002 P1 198-003 P1 198-004 P1 198-005 P1 198-006 P1 198-007 P1 198-008 P1 198-101 P1 198-103 P1 198-104 P1 198-105 P1 198-106 P1 198-107 P1 198-108 P1 198-109 P1 198-110 P1 198-111 P1 198-112 P1 Design and Access Statement - December 2012
Date Plans Received: 23/01/2013 Date(s) of Amendment(s): Date Application Valid: 06/03/2013 1. SUMMARY The application seeks planning permission for the development of Stockley Arena to provide additional office accommodation, including a single-storey extension to the central rotunda and to the southern wing to create a new second floor, together with a two-storey extension above the existing refuse storage and deliveries area to the north.
It is not considered that the proposed development would result in an unacceptable impact on the visual amenities of the site or on the openness of the Green Belt. It is not considered that the development would lead to such a significant increase in traffic that
Major Applications Planning Committee - 7th August 2013 PART 1 - MEMBERS, PUBLIC & PRESS refusal could be justified on highway grounds. The proposal is considered to comply with relevant Local Plan and London Plan policies and, accordingly, approval is recommended subject to referral of the application to the Mayor of London. 2. RECOMMENDATION That subject to the Mayor not directing the Council under Article 6 of the Town and Country Planning (Mayor of London) Order 2008 to refuse the application, or under Article 7 of the Order that he is to act as the local planning authority for the purpose of determining the application; AND subject to the Environment Agency formally withdrawing their objection, delegated powers be given to the Head of Planning, Green Spaces and Culture to grant planning permission subject to the following conditions, and any additional conditions and/or informatives which may be required by the Mayor or the Environment Agency:
1 COM3 Time Limit The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
REASON To comply with Section 91 of the Town and Country Planning Act 1990.
2 COM4 Accordance with Approved Plans The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 198-001 P2, 198- 002 P1, 198-003 P1, 198-004 P1, 198-005 P1, 198-006 P1, 198-007 P1, 198-008 P1, 198-101 P1, 198-102 P1, 198-103 P1, 198-104 P1, 198-105 P1, 198-106 P1, 198-107 P1, 198-108 P1, 198-109 P1, 198-110 P1, 198-111 P1, 198-112 P1 and shall thereafter be retained/maintained for as long as the development remains in existence.
REASON To ensure the development complies with the provisions Hillingdon Local Plan: Part Two Saved UDP Policies (November 2012) and the London Plan (July 2011).
3 COM5 General compliance with supporting documentation The development hereby permitted shall not be occupied until the following has been completed in accordance with the specified supporting plans and/or documents:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Major Applications Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.