School Capital Programme Update - Part 1

Noted Executive 1 paper

CABINET noted this item on Thursday 24 October 2013. Below is the council's own wording, with the papers it was decided on.

Item858

Resolved

That Cabinet: Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme. Approve the inclusion of Grange Park drainage works to the School Condition Works Programme. Reasons for decision Cabinet received an update on the primary school capital programme and good maintenance of the school estate. Alternative options considered and rejected Cabinet could have decided not to include Grange Park drainage works to the School Condition Works Programme. Officer to action: David Murnaghan – Residents Services
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to CABINET, 9 pages

SCHOOL CAPITAL PROGRAMME – UPDATE (PART 1)

Cabinet Members Councillor Jonathan Bianco Councillor David Simmonds

Cabinet Portfolios Finance, Property & Business Services Deputy Leader of the Council / Education & Children’s Services

Officer Contact David Murnaghan Residents Services

Papers with report Accompanying report in Part 2 of this agenda and appendix 1.

Access to This report detailing progress on the school capital Information programme is public. However, any commercially sensitive information will be included in the private part of the agenda.

HEADLINE INFORMATION

Summary This report provides an update on the Primary School Expansion Programme Phases 1, 2, 3 and 4 and the School Condition Programme.

Contribution to our Investment in primary schools to adequately address the impact plans and strategies of the population increase, within the London Borough of Hillingdon on existing school places. This project also forms part of the Hillingdon Improvement Programme.

Financial Cost The current forecast of the Primary Schools Capital Programme is £146,779k compared to budget of £159,391k. This shows a funding surplus of £12,612k. This is due to favourable tender returns and the uncommitted sum on a one extra form of entry. It should be noted that there are costs risks within the overall programme which may impact on this figure as the construction works progress.

Relevant Policy Education and Children’s Services Overview Committee

Ward(s) affected All wards.

Cabinet – 24 October 2013 RECOMMENDATIONS

That Cabinet:

1. Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme.

2. Approve the inclusion of Grange Park drainage works to the School Condition Works Programme.

INFORMATION

School Places Forecast

The demand for school places in Hillingdon is rising and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates and new house building. In the three months since 1st June 2013 there has also been an unprecedented increase in the number of new families moving into the Borough; almost a four-fold increase compared to the same time last year.

The increased number of new families moving into the Borough is increasing the demand for school places in all primary school year groups in certain locations across the Borough. Officers are monitoring the number of new ‘in-year’ applications for primary school places on a daily basis. In Hillingdon it is predicted that the pressure for primary school places will move into secondary schools by 2016/2017.

The latest ten-year forecast for school places in Hillingdon is being finalised and will be reported to Cabinet in the autumn. The report to Cabinet will set out a proposed plan for meeting the forecast need over and above the existing successful schools expansion programme. This will include options for ensuring the provision of additional secondary school places.

Phase 1 - Permanent Expansions

Phase 1 of the Primary School Expansion Programme (PSEP) consists of the expansion of 8 schools. Construction works at Brookside, Colham Manor, Cranford Park and William Byrd were completed for September 2012. Construction at a further 3 schools Whitehall Infants, Grange Park Infants and Grange Park Juniors were completed for September 2013. Whitehall Juniors is the last school in this phase of work is due to be completed in 2014.

Whitehall Junior

Work is continuing at the Whitehall Junior School and is scheduled to complete the remaining works in 2014.

Grange Park Infant School New Kitchen

The school has raised concerns about the reach requirements for some of the smallest children and they have elected to offer a cold-meal service in the interim. Officers from Environmental Health have visited the school and confirmed that, subject to a suitable management plan, a hot

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
School Capital Programme Update: Part 1Report 9 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 13 attended
RP
Councillor Raymond Puddifoot MBEChair, present
DS
Councillor David SimmondsVice-Chair, present
JB
Councillor Jonathan BiancoCommittee Member, present
KB
Councillor Keith BurrowsCommittee Member, present
PC
Councillor Philip Corthorne MCIPDCommittee Member, present
DM
Councillor Douglas MillsCommittee Member, present
SS
Councillor Scott Seaman-DigbyCommittee Member, apologies
CF
Charles FrancisSecretary, expected
SM
Steven MaidenSecretary, expected
GO
Gill OswellSecretary, expected
DW
Danielle WatsonSecretary, expected
NW
Nadia WilliamsSecretary, expected

All 13 on the meeting page

On this subject at Hillingdon

Search all
  1. School Capital Programme Update - Part 1This decision
  2. School Capital Programme UpdateNoted
  3. School Capital Programme UpdateNoted
  4. School Capital Programme UpdateNoted
  5. School Capital Programme UpdateNoted
  6. School Capital Programme UpdateNoted

More from Hillingdon CABINET

All decisions
MeetingDecisionOutcome
19 Nov 2026 Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt... Approved Open
19 Nov 2026 Strategic Review of Library Services and Future Delivery ModelThat Cabinet: 1) Approves the launch of the Strategic Review of Library Services and Future Delivery Model, the devel... Approved Open
19 Nov 2026 Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T... Agreed Open
19 Nov 2026 Old Vinyl Factory, Hayes: Conservation Area AppraisalThat Cabinet: 1) Duly considers the public consultation responses to the draft Appraisal for The Old Vinyl Factory Co... Approved Open
19 Nov 2026 Carers Strategy UpdateThat Cabinet: 1) Note the report and agree that officers bring forward an annual progress report to Cabinet on suppor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies