London Borough of Hillingdon
CABINET, Thursday 19 December 2013 at 7.00pm

School Capital Programme Update

Refused Executive 1 paper

CABINET refused this item on Thursday 19 December 2013. Below is the council's own wording, with the papers it was decided on.

Item886

Resolved

That Cabinet n ote the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme. Reasons for decision Cabinet received its monthly update on London’s largest school building programme, aimed at ensuring that every child in the London Borough of Hillingdon would have a quality place at a local school. Alternative options considered and rejected None. Officer to action: David Murnaghan – Residents Services
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to CABINET, 8 pages

SCHOOL CAPITAL PROGRAMME – UPDATE (PART 1)

Cabinet Members Councillor Jonathan Bianco Councillor David Simmonds

Cabinet Portfolios Finance, Property & Business Services Deputy Leader of the Council / Education & Children’s Services

Officer Contact David Murnaghan Residents Services

Papers with report None

HEADLINE INFORMATION

Summary This report provides an update on the Primary School Expansion Programme Phases 1, 2 and 3 and the School Condition Programme.

Contribution to our Investment in primary schools to adequately address the impact plans and strategies of the population increase, within the London Borough of Hillingdon, on existing school places. This project also forms part of the Hillingdon Improvement Programme.

Financial Cost The current forecast of the Primary Schools Capital Programme is £146,513k compared to budget of £159,391k. This shows a funding surplus of £12,878k. This is due to favorable tender returns and the uncommitted sum on a one extra form of entry. It should be noted that there are cost risks within the overall programme, so the figure may change as the construction phase begins.

Relevant Policy Children, Young People and Learning Overview Committee

Ward(s) affected All wards.

Cabinet – 19 December 2013 RECOMMENDATIONS

That Cabinet:

1. Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme.

INFORMATION

School Places Forecast

The demand for school places in Hillingdon is rising and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates, new house building and families moving into the Borough.

The increased number of new families moving into Hillingdon is increasing the demand for school places in all primary school year groups in certain locations across the Borough. Officers are monitoring the number of new ‘in-year’ applications for primary school places closely which seems to have fallen and stabilised to usual levels over the last month.

The latest ten-year forecast for school places in Hillingdon has been updated and shows levels of rising demand for school places, consistent with previous reports to Cabinet. There is a need for additional primary bulge year classes for September 2014 in a small number of areas in the Borough and Officers are finalising recommendations to meet this need. The forecast also predicts the need for additional secondary school places from September 2016 onwards. Officers are currently appraising secondary school sites for potential expansion and will report back findings to the Leader of the Council in the first instance, for an agreed way forward. Officers are also finalising proposals for consideration to meet the need for the provision of child care places for disadvantaged two-year olds from September 2014 onwards.

Phase 1 - Permanent Expansions

Phase 1 of the Primary School Expansion Programme (PSEP) consists of the expansion of 8 schools. The main expansion works have been completed at 7 schools. Whitehall Juniors is the last school in this phase of work and is scheduled to be completed in 2014.

Whitehall Junior

The scheme consists of two additional classrooms, one WC facility, a new kitchen block and an extension to the existing assembly hall. The steel frames have been erected and brick work on both the hall and the kitchen are progressing well.

Grange Park Infant and Junior

Remedial works continue at Grange Park Infants, primarily addressing heating and ventilation issues in the nursery and kitchen/dinning areas. Officers are working closely with phase 1 consultants and Leadbitter to resolve these issues when they arise.

Cranford Park Drainage Remedial Works

Cranford Park School has experienced foul water drainage problems, which occurred after remodelling and repairing the existing system. A solution has been found and the contractor

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
School Capital Programme UpdateReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hillingdon

Search all
  1. School Capital Programme UpdateThis decision
  2. School Capital Programme UpdateNoted
  3. School Capital Programme UpdateNoted
  4. School Capital Programme UpdateNoted
  5. School Capital Programme UpdateNoted
  6. School Capital Programme UpdateNoted

More from Hillingdon CABINET

All decisions
MeetingDecisionOutcome
19 Nov 2026 Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt... Approved Open
19 Nov 2026 Strategic Review of Library Services and Future Delivery ModelThat Cabinet: 1) Approves the launch of the Strategic Review of Library Services and Future Delivery Model, the devel... Approved Open
19 Nov 2026 Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T... Agreed Open
19 Nov 2026 Old Vinyl Factory, Hayes: Conservation Area AppraisalThat Cabinet: 1) Duly considers the public consultation responses to the draft Appraisal for The Old Vinyl Factory Co... Approved Open
19 Nov 2026 Carers Strategy UpdateThat Cabinet: 1) Note the report and agree that officers bring forward an annual progress report to Cabinet on suppor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies