That Cabinet: Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme. Approve in principle for Officers to proceed with work on the: · Delivery of Specialist Resource Provision (SRP) accommodation to meet the additional demand for places in September 2014; · Delivery of Special Schools bulge year accommodation to meet the additional demand for places in September 2014; · Feasibility for the proposed construction of a new Primary School in the West Drayton/ Yiewsley area. Delegate authority to the Leader of the Council and Cabinet Member for Finance, Property and Business Services, in consultation with Deputy Chief Executive and Director of Residents Services, to approve which schools will be taking the additional SRP and bulge year accommodation and make all necessary procurement and financial decisions, including the appointment of consultancies, development of tender proposals and placing of building contracts in order to deliver the schemes outlined in recommendation 2. Note the requirement to spend £55,000 on site investigation surveys and internal fees for the Special Schools bulge year accommodation. Note the requirement to spend £110,000 on site investigation surveys and internal fees for the new Primary School in the West Drayton/ Yiewsley area. Reasons for decision Cabinet received its monthly update on London’s largest school building programme, aimed at ensuring that every child in the London Borough of Hillingdon would have a quality place at a local school. A number of initial decisions to progress the delivery of bulge year accommodation were made, along with feasibility studies in relation to the proposed new primary school in the West Drayton / Yiewsley area of the Borough, which the Deputy Leader of the Council announced at the meeting would, pending further feasibility studies, be on the Laurel Lane School Site. Alternative options considered and rejected None. Officer to action: David Murnaghan – Residents Services
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Cabinet Members Councillor Jonathan Bianco Councillor David Simmonds
Cabinet Portfolios Finance, Property & Business Services Deputy Leader of the Council / Education & Children’s Services
Officer Contact David Murnaghan Residents Services
Papers with report Appendix 1: Summary of Phase 2 works
HEADLINE INFORMATION
Summary This report provides an update on the Primary School Expansion Programme Phases 1, 2 and 3 and the School Condition Programme.
Contribution to our Investment in primary schools to adequately address the impact plans and strategies of the population increase within the London Borough of Hillingdon on existing school places. This project also forms part of the Hillingdon Improvement Programme.
Financial Cost The current forecast of the Primary Schools Capital Programme is £146,516k compared to budget of £159,394k. This shows a funding surplus of £12,878k. This is due to favorable tender returns and the uncommitted sum on a one extra form of entry. It should be noted that there are cost risks within the overall programme, so the figure may change as the construction phase begins. The costs of £55k for the temporary accommodation will be met from the existing Phase 3A budget of £3.6m. The £110k from the £10m budget (included in Phase 3 budget of £32,740k) allocated to the new Primary School in the West Drayton/Yiewsley. Both are subject to capital release.
Relevant Policy Children’s, Young People and Learning Overview Committee
Ward(s) affected All wards.
Cabinet – 23 January 2014 RECOMMENDATIONS
That Cabinet:
1. Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme.
2. Approve in principle for Officers to proceed with work on the:
a. Delivery of Specialist Resource Provision (SRP) accommodation to meet the additional demand for places in September 2014;
b. Delivery of Special Schools bulge year accommodation to meet the additional demand for places in September 2014;
c. Feasibility for the proposed construction of a new Primary School in the West Drayton/Yiewsley area.
3. Delegate authority to the Leader of the Council and Cabinet Member for Finance, Property and Business Services, in consultation with Deputy Chief Executive and Director of Residents Services, to approve which schools will be taking the additional SRP and bulge year accommodation and make all necessary procurement and financial decisions, including the appointment of consultancies, development of tender proposals and placing of building contracts in order to deliver the schemes outlined in recommendation 2.
4. Note the requirement to spend £55,000 on site investigation surveys and internal fees for the Special Schools bulge year accommodation.
5. Note the requirement to spend £110,000 on site investigation surveys and internal fees for the new Primary School in the West Drayton/Yiewsley area.
INFORMATION
School Places Forecast
The demand for school places in Hillingdon is rising and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates, new house building and families moving into the Borough.
The latest ten-year forecast for school places in Hillingdon has been updated and shows levels of rising demand for school places, consistent with previous reports to Cabinet. The forecast predicts the need for a number of bulge year group classes for September 2014 and additional secondary school places from September 2016 onwards. Officers are currently appraising secondary school sites for potential expansion and will report back findings to the Leader of the Council in the first instance, for an agreed way forward. Officers are also preparing proposals for consideration to meet the need for the provision of child care places for disadvantaged two-year olds from September 2014 onwards.
Cabinet – 23 January 2014 Bulge Year Classes for September 2014
Primary Schools
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.