Resolved
That the Health and Wellbeing Board notes the update report.
Health and Wellbeing Board decided this item on Thursday 6 February 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Health and Wellbeing Board notes the update report.
HILLINGDON CCG FINANCIAL RECOVERY PLAN UPDATE REPORT
Relevant Board [name removed](s)
Organisation Hillingdon Clinical Commissioning Group
Report author John Halsted: Interim QIPP Director
Papers with report Appendix - Summary of Progress Against Plan
1. HEADLINE INFORMATION
Summary This report provides an update on Hillingdon CCG’s progress with its Financial Recovery Plan for 2013-2016. The CCG’s Financial Recovery Plan forms an integral part of its 2013/14 Operating Plan, as agreed by the Health and Wellbeing Board (HWBB) at its February 2013 meeting and as approved by the Hillingdon CCG Governing Body at its May 2013 meeting. It also aligns closely with the Hillingdon CCG Out of Hospital Strategy.
The Financial Recovery Plan forms a subset of total CCG budgets and it should be noted that, whilst delivery of this Plan contributes to the financial position, it does not represent the final overall position. Overall, HCCG is projecting a smaller deficit than set at the beginning of the financial year.
Current expectations are for the CCG to deliver the majority of its £11m Recovery Plan targets by March 2014. However, there is a risk of underperformance of c £2.5 million (22% of the overall Plan) based on current activity figures. A number of remedial actions have been put in place to seek to reduce this forecast under- performance.
Contribution to plans Joint Health & Wellbeing Strategy and strategies
Financial Cost The Financial Recovery Plan reflects the position of Hillingdon CCG at the time of writing. Changes to funding streams and national policy impact on assumptions within the Financial Recovery Plan and the Plan has been refreshed for 2014/15 to reflect these changes.
Relevant Policy N/A Overview & Scrutiny Committee
Ward(s) affected All
Health and Wellbeing Board report – 6 February 2014 2. RECOMMENDATION
The Board is asked to note this update.
3. INFORMATION
Supporting Information
3.1CCG Recovery Plan 2013/14
The CCG set its budget for 2013/14 on the basis of achieving a series of financial savings targets between April 2013 and March 2016. The target for this year is £11 million, rising to £14.5 million in each of the two following years, or £40 million over the combined three years. A deficit budget of £12.15m was set for 2013/14.
The Recovery Plan – or QIPP Programme (Quality, Innovation, Productivity and Prevention) – contains 5 main programmes, with the savings target in 2013/14 shown against each: 1. Unscheduled Care (£3 million) 2. Planned Care (£3.7 million) 3. Long Term Conditions (£0.4 million) 4. Prescribing (£2.4 million) 5. Mental Health & Community Services (£1.7 million)
Each programme contains a number of separate schemes, with the overall objective of achieving faster access to care in an emergency, and improved pathways of care for all users of services, and bringing access to high-quality care in line with best practice in London and nationally. In addition to the schemes above, the CSU (Commissioning Support Unit) is responsible for ensuring contractual requirements are rigorously applied and challenges made appropriately.
The four underlying principles behind the CCG’s financial planning, and the Governing Body’s approach to integrated commissioning, are for the Financial Recovery Plan to deliver local financial and service stability over the next 3 years, and to be: 1. Clinically led and supported by GP commissioners 2. Informed by engagement with the public, patients and local authority 3. Robust and transparent in its process, and underpinned by a sound clinical evidence base 4. Consistent with current and prospective patient choice
Achievement of our commissioning priorities is linked to achievement of the Quality Premium (a payment CCGs receive in the following year if certain targets are achieved). Delivery is tracked weekly through our Programme Management Office (PMO), and monitored through monthly assurance meetings by NHS England.
3.2Progress to date
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AppendixAppendix | 49 KB | Download |
PDF |
Hillingdon CCG Financial Recovery Plan Update ReportReport | 69 KB | DownloadRead as text |
Follow Health and Wellbeing Board at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Jun 2026 | To approve the minutes of the meeting on 18 March 2026That the minutes of the meeting held on 18 March 2026 be agreed as a correct record. | Agreed | Open |
| 17 Jun 2026 | 2026/27 Better Care Fund UpdateThat: the 2026/27 Better Care Fund Plan as described in the report be approved, including the proposed financial arra... | Approved | Open |
| 17 Jun 2026 | Occupational Therapy Service UpdateThat the content of the report be noted. | Noted | Open |
| 17 Jun 2026 | Board Planner & Future Agenda ItemsThat the Board Planner be agreed subject to the addition of the following reports: 9 September 2026 - SEND JSNA; and ... | Agreed | Open |
| 18 Mar 2026 | To approve the minutes of the meeting on 2 December 2025That the minutes of the meeting held on 2 December 2025 be agreed as a correct record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.