That Cabinet: Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme and the School Conditions Programme. Delegate authority to the Deputy Chief Executive and Corporate Director of Residents Services, in consultation with the Leader of the Council and Cabinet Members for Education and Children’s Services & Finance, Property and Business Services, to make all necessary decisions to implement Government policies relating to Universal Infant Free School Meals and Child Care Places for Two Year Olds, as set out in the report. Note the requirement for an additional £30,000 to complete the options appraisal for the new school in West Drayton. Reasons for decision Cabinet received its monthly update on London’s largest school building programme, aimed at ensuring that every child in the London Borough of Hillingdon would have a quality place at a local school. Decisions were made to implement recent Government initiatives in relation to Infant Free School Meals and Child Care Places. Alternative options considered and rejected None. Officer to action: David Murnaghan – Residents Services
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Cabinet Members Councillor Jonathan Bianco Councillor David Simmonds
Cabinet Portfolios Finance, Property & Business Services Deputy Leader of the Council / Education & Children’s Services
Officer Contact David Murnaghan Residents Services
Papers with report Appendix 1: Summary of Phase 2 works
Access to This report detailing progress on the school capital Information programme is public. However, any commercially sensitive information will be included in the private part of the agenda.
HEADLINE INFORMATION
Summary This report provides an update on the Primary School Expansion Programme Phases 1, 2 and 3 and the School Condition Programme.
Contribution to our Investment in primary schools to adequately address the impact plans and strategies of the population increase within the London Borough of Hillingdon on existing school places. This project also forms part of the Hillingdon Improvement Programme.
Financial Cost The current forecast of the Primary Schools Capital Programme is £146,516k compared to a budget of £159,394k. This shows a funding surplus of £12,878k. This is due to favorable tender returns and uncommitted sum on a one extra form of entry. It should be noted that there are cost risks within the overall programme, so the figure may change as the construction phases begin.
Relevant Policy Children’s, Young People and Learning Overview Committee
Ward(s) affected All wards.
Cabinet – 13 February 2014 RECOMMENDATIONS
That Cabinet:
1. Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme and the School Conditions Programme.
2. Delegate authority to the Deputy Chief Executive and Corporate Director of Residents Services, in consultation with the Leader of the Council and Cabinet Members for Education and Children’s Services & Finance, Property and Business Services, to make all necessary decisions to implement Government policies relating to Universal Infant Free School Meals and Child Care Places for Two Year Olds, as set out in the report.
3. Note the requirement for an additional £30,000 to complete the options appraisal for the new school in West Drayton.
INFORMATION
School Places Forecast
The demand for school places in Hillingdon has been rising and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates, new house building and families moving into the Borough. This demand is predicted to move into secondary schools. Officers are appraising secondary school sites for potential expansion and will report back findings to the Leader of the Council in the first instance, for an agreed way forward. Officers have also been preparing proposals for consideration to meet the need for child care places for disadvantaged two-year olds from September 2014 onwards.
Special Educational Needs (SEN) - Bulge Classes for September 2014
Analysis of future demand of school places for children with special educational needs has previously been reported to Cabinet. The analysis shows the need in Hillingdon is rising, in line with the growing number of children in the Borough. From recent discussions with some schools, there are opportunities to provide additional local pupil places for September 2014. Officers are progressing arrangements for these additional places and will seek approval from the Leader of the Council (as agreed at the January Cabinet meeting) to agree which schools will be taking the accommodation and the final scope of the works, prior to implementation.
Universal School Meals
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.