CABINET, Thursday 13 February 2014 at 7.00pm

School Capital Programme Update - PART 1

Noted Executive 1 paper

CABINET noted this item on Thursday 13 February 2014. Below is the council's own wording, with the papers it was decided on.

Item923

Resolved

That Cabinet: Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme and the School Conditions Programme. Delegate authority to the Deputy Chief Executive and Corporate Director of Residents Services, in consultation with the Leader of the Council and Cabinet Members for Education and Children’s Services & Finance, Property and Business Services, to make all necessary decisions to implement Government policies relating to Universal Infant Free School Meals and Child Care Places for Two Year Olds, as set out in the report. Note the requirement for an additional £30,000 to complete the options appraisal for the new school in West Drayton. Reasons for decision Cabinet received its monthly update on London’s largest school building programme, aimed at ensuring that every child in the London Borough of Hillingdon would have a quality place at a local school. Decisions were made to implement recent Government initiatives in relation to Infant Free School Meals and Child Care Places. Alternative options considered and rejected None. Officer to action: David Murnaghan – Residents Services
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to CABINET

SCHOOL CAPITAL PROGRAMME – UPDATE (PART 1)

Cabinet Members Councillor Jonathan Bianco Councillor David Simmonds

Cabinet Portfolios Finance, Property & Business Services Deputy Leader of the Council / Education & Children’s Services

Officer Contact David Murnaghan Residents Services

Papers with report Appendix 1: Summary of Phase 2 works

Access to This report detailing progress on the school capital Information programme is public. However, any commercially sensitive information will be included in the private part of the agenda.

HEADLINE INFORMATION

Summary This report provides an update on the Primary School Expansion Programme Phases 1, 2 and 3 and the School Condition Programme.

Contribution to our Investment in primary schools to adequately address the impact plans and strategies of the population increase within the London Borough of Hillingdon on existing school places. This project also forms part of the Hillingdon Improvement Programme.

Financial Cost The current forecast of the Primary Schools Capital Programme is £146,516k compared to a budget of £159,394k. This shows a funding surplus of £12,878k. This is due to favorable tender returns and uncommitted sum on a one extra form of entry. It should be noted that there are cost risks within the overall programme, so the figure may change as the construction phases begin.

Relevant Policy Children’s, Young People and Learning Overview Committee

Ward(s) affected All wards.

Cabinet – 13 February 2014 RECOMMENDATIONS

That Cabinet:

1. Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme and the School Conditions Programme.

2. Delegate authority to the Deputy Chief Executive and Corporate Director of Residents Services, in consultation with the Leader of the Council and Cabinet Members for Education and Children’s Services & Finance, Property and Business Services, to make all necessary decisions to implement Government policies relating to Universal Infant Free School Meals and Child Care Places for Two Year Olds, as set out in the report.

3. Note the requirement for an additional £30,000 to complete the options appraisal for the new school in West Drayton.

INFORMATION

School Places Forecast

The demand for school places in Hillingdon has been rising and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates, new house building and families moving into the Borough. This demand is predicted to move into secondary schools. Officers are appraising secondary school sites for potential expansion and will report back findings to the Leader of the Council in the first instance, for an agreed way forward. Officers have also been preparing proposals for consideration to meet the need for child care places for disadvantaged two-year olds from September 2014 onwards.

Special Educational Needs (SEN) - Bulge Classes for September 2014

Analysis of future demand of school places for children with special educational needs has previously been reported to Cabinet. The analysis shows the need in Hillingdon is rising, in line with the growing number of children in the Borough. From recent discussions with some schools, there are opportunities to provide additional local pupil places for September 2014. Officers are progressing arrangements for these additional places and will seek approval from the Leader of the Council (as agreed at the January Cabinet meeting) to agree which schools will be taking the accommodation and the final scope of the works, prior to implementation.

Universal School Meals

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
School Capital Programme Update: PART 1Report 125 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 13 attended
RP
Councillor Raymond Puddifoot MBEChair, present
DS
Councillor David SimmondsVice-Chair, present
JB
Councillor Jonathan BiancoCommittee Member, present
KB
Councillor Keith BurrowsCommittee Member, present
PC
Councillor Philip Corthorne MCIPDCommittee Member, present
DM
Councillor Douglas MillsCommittee Member, present
SS
Councillor Scott Seaman-DigbyCommittee Member, present
CF
Charles FrancisSecretary, expected
SM
Steven MaidenSecretary, expected
GO
Gill OswellSecretary, expected
DW
Danielle WatsonSecretary, expected
NW
Nadia WilliamsSecretary, expected

All 13 on the meeting page

On this subject at Hillingdon

Search all
  1. School Capital Programme Update - PART 1This decision
  2. School Capital Programme UpdateNoted
  3. School Capital Programme UpdateNoted
  4. School Capital Programme UpdateNoted
  5. School Capital Programme UpdateNoted
  6. School Capital Programme UpdateNoted

More from Hillingdon CABINET

All decisions
MeetingDecisionOutcome
19 Nov 2026 Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt... Approved Open
19 Nov 2026 Strategic Review of Library Services and Future Delivery ModelThat Cabinet: 1) Approves the launch of the Strategic Review of Library Services and Future Delivery Model, the devel... Approved Open
19 Nov 2026 Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T... Agreed Open
19 Nov 2026 Old Vinyl Factory, Hayes: Conservation Area AppraisalThat Cabinet: 1) Duly considers the public consultation responses to the draft Appraisal for The Old Vinyl Factory Co... Approved Open
19 Nov 2026 Carers Strategy UpdateThat Cabinet: 1) Note the report and agree that officers bring forward an annual progress report to Cabinet on suppor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies