That Cabinet: 1. Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme and the School Conditions Programme. 2. Agrees to progress plans for a new 5FE Junior School on Council land adjacent to the existing the Laurel Lane School, noting that planning consent, changes to rights of way and land appropriation permissions are being sought. 3. Approve the provision of Specialist Resource Provision (SRP) unit and an additional modular classroom unit at Cherry Lane Primary School. 4. Ratify a Cabinet-level decision taken by the Leader of the Council on 18 June 2014, under interim executive arrangements, in relation to the appropriation of Land at Laurel Lane, West Drayton. Reasons for decision Cabinet received an update on the primary and secondary school capital programmes and made a number of decisions to progress the provision of sufficient school places, including those relating to the proposed new school on the Laurel Lane site. Alternative options considered and rejected Cabinet could have decided to delay or not progress aspects of the school capital programmes, which would have impacted upon the Council’s ability to provide sufficient school places. Officer to action: David Murnaghan – Residents Services
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
1. Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme and the School Conditions Programme.
2. Agrees to progress plans for a new 5FE Junior School on Council land adjacent to the existing the Laurel Lane School, noting that planning consent, changes to rights of way and land appropriation permissions are being sought. Recommendations continued overleaf...
Cabinet – 19 June 2014 3. Approve the provision of Specialist Resource Provision (SRP) unit and an additional modular classroom unit at Cherry Lane Primary School.
INFORMATION
School Places Forecast
The demand for school places in Hillingdon has been rising in recent years and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates, new house building and families moving into the Borough. This demand is moving into secondary schools. Officers are working on updating the school places forecast using the latest data from the Greater London Authority (GLA) received in April. The GLA are now forecasting slightly higher birth rates and larger household sizes in Hillingdon than previously expected. Officers are analysing the forecast by each pupil place planning area in Hillingdon and will report findings to Members in early July.
Phase 1 - Primary Schools Permanent Expansions
Phase 1 of the Primary School Expansion Programme consists of the expansion of 8 schools. The main expansion works have now been completed at all 8 schools.
Whitehall Juniors
Whitehall Juniors, the final school in this phase of works, achieved practical completion on 22 May. The additional accommodation will not be required until 2015 which is when the additional pupils move up from the infant school.
Grange Park Infant and Junior Remedial Works
Playground resurfacing was carried during the Easter holiday break but to an unacceptable standard. This was addressed during the May half-term break. Further items to be investigated include water ingress to the New Teaching Block, ramp repair and anti-bird / debris netting fitted over the exposed Gas Absorption Heat Pump in the Nursery School.
Grange Park Infant Basement
Flow meters have been installed to monitor water consumption at key points within the school, to ascertain whether a fractured main is contributing to the water ingress. Further water sample analysis carried out, point once more to ground water ingress.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.