That: a) the Community Infrastructure Levy Charging Schedule and the Planning Obligations Supplementary Planning Document be adopted as Council policy; b) the proposed instalments policy for CIL payments be approved; and c) the current Planning Obligations Supplementary Planning Document be withdrawn following the adoption of the revised Planning Obligations Supplementary Planning Document.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
1.1This report seeks approval to adopt the Council's Community Infrastructure Levy Charging Schedule and Replacement Planning Obligations Supplementary Planning Guidance (SPD).
1.2In February 2012, Cabinet agreed that Hillingdon's Community Infrastructure Levy Draft Charging Schedule could be submitted to the Secretary of State for formal examination. The hearing associated with the Examination took place on 1 October 2013. The Examiner's report was published in February 2014 and concluded that the Charging Schedule be approved, subject to the following modifications: • Amend Table 3.1 to clarify that the rate for large format retail only applies outside of designated town centres. Include maps in the Charging Schedule identifying the town centres. • Amend the description of the rate for large format retail so that it only applies to A1 uses in Table 3.1 and paragraph 2.3. • Delete references to a Sui Generis rate from Table 3.1, paragraph 2.3, paragraph 5.6 and paragraph 5.7.
1.3On 24 April 2014 Cabinet resolved to approve the Charging Schedule with the modifications recommended by the Examiner and an associated revised version of the Council's Planning Obligations SPD. Formal adoption of the Charging Schedule and the revised Planning Obligations SPD is now being sought.
RECOMMENDATIONS: That:
(a) the Community Infrastructure Levy Charging Schedule and the Planning Obligations Supplementary Planning Document be adopted as Council policy (both documents are available in the Group Offices and on line at: http://modgov.hillingdon.gov.uk/ieListDocuments.aspx?CId=117&M Id=1953&Ver=4;
(b) the proposed instalments policy for CIL payments be approved and
(c). the current Planning Obligations Supplementary Planning Document be withdrawn following the adoption of the revised Planning Obligations Supplementary Planning Document.
Council – 10 July 2014 INFORMATION
2. Hillingdon's Community Infrastructure Levy Charging Schedule
2.1Taking account of the Examiner's recommendations, the charging rates that are recommended for adoption per square metre of new development are as follows:
Use Type Proposed CIL rate (per square metre) Large format retail (A1 greater than 1,000 square £215 metres outside of designated town centres Offices £35
2.2The Draft Charging Schedule submitted for Examination stated that the Council will implement an instalments policy to assist in the payment of CIL charges. The following instalments policy, which has been prepared following research into existing policies being applied elsewhere, was approved by Cabinet on 24 April 2014:
Payment period and Amount of CIL Liability Number of Instalments Amounts Total amount payable within Any amount less than No instalments 60 days of commencement of £250,000 development £250,000payable with 60 days of commencement of Amounts more than development. £250,000 but less than or Two instalments equal to £500,000 Balance payable within 60 days of commencement of development. £250,000 payable within 60 days of commencement of development. Amounts greater than Three instalments Balance payable in two £500,000 further instalments of equal amount within 120 and 180 days of commencement of development.
2.3In anticipation of the CIL being adopted, officers are currently putting in place the necessary processes to collect the CIL charges. This involves modifications to the processes and procedures currently used to collect
Council – 10 July 2014 the Mayoral CIL. It is expected that collections can commence on 1 August 2014.
3. Amendments to the Charging Schedule
3.1Before approving the adoption of the Charging Schedule and revised Planning Obligations SPD, Council is asked to note that Cabinet approved the following action on 24 April 2014, which stated that it:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
West London Waste Plan Regulation 19That: the publication and consultation of the Proposed Submission (Regulation 19) West London Waste Plan, as attached...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.