That Cabinet: 1. Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme and the School Conditions Programme and; 2. Delegate full authority to the Leader of the Council and Cabinet Member for Finance, Property and Business Services, in consultation with Deputy Chief Executive and Director of Residents Services, to make all necessary procurement and financial decisions, including the appointment of consultancies and the placing of building contracts for the selected Secondary School sites considered suitable for expansion. Reasons for decision Cabinet received an update on the Council's major primary and secondary school capital expansions programmes, noting the substantial works undertaken over the last few months on both existing and new schools sites. Cabinet also put in place the necessary delegated decision-making to make further progress on secondary school expansion over the coming months. Alternative options considered and rejected Cabinet could have decided to delay or not progress aspects of the school capital programmes, which would have impacted upon the Council’s ability to provide sufficient school places. Officer to action: Bobby Finch, Residents Services Classification: Public The report relating to this decision by the Cabinet is available to view on the Council's website or by visiting the Civic Centre, Uxbridge.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Cabinet Members Councillor Jonathan Bianco Councillor David Simmonds
Cabinet Portfolios Finance, Property & Business Services Deputy Leader of the Council / Education & Children’s Services
Officer Contact Bobby Finch, Residents Services
Papers with report Appendix 1: Summary of phase 2 and 3 construction works
HEADLINE INFORMATION
Summary This report provides an update on the Primary School Expansion Programme Phases 1, 2 and 3, the School Condition Programme and other school capital works.
Contribution to our Putting our Residents First: plans and strategies Our Built Environment; Our People; Financial Management
Investment in schools to adequately address the impact of the population increase within the London Borough of Hillingdon on existing school places. This project also forms part of the Hillingdon Improvement Programme.
Financial Cost The current forecast of the existing Primary Schools Capital Programme is £146,391k inclusive of £1,000k for Special Resources Provision. The Secondary Schools Expansions/Replacement forecast is £150,000k, with an additional £13,500k for phase 4 of New Primary Schools Expansion.
Relevant Policy Children, Young People and Learning Overview Committee
Ward(s) affected All wards
RECOMMENDATIONS That Cabinet:
1. Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme and the School Conditions Programme and; 2. Delegate full authority to the Leader of the Council and Cabinet Member for Finance, Property and Business Services, in consultation with Deputy Chief Executive and Director of Residents Services, to make all necessary procurement and financial decisions, including the appointment of consultancies and the placing of building contracts for the selected Secondary School sites considered suitable for expansion.
Cabinet – 23 October 2014 INFORMATION 1. PRIMARY SCHOOLS
School Places Forecast
The demand for school places in Hillingdon has been rising in recent years and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates which the GLA are now predicting to be slightly higher than they previously forecast, new house building and families moving into the Borough. Overall, at primary school level, the need for additional school places has largely been met by the successful school places expansion programme to date.
The latest forecast for school places indicates a residual need for up to three additional forms of entry in the north of the Borough over the next 2-3 years. This additional demand is largely a result of pupils from outside the Borough travelling to primary schools in Hillingdon (an equivalent of 2 FE from Harrow travelling to schools in the East Ruislip area and 1 FE from Hertfordshire attending schools in the Northwood area). Officers are developing recommendations for consideration by Members in October to meet this need.
Phase 2 - Primary Schools Permanent Expansions
Phase 2 of the Primary School Expansion Programme will permanently expand 18 schools and add a bulge year to an additional school. To date expansion works have been completed at 14 schools. The remaining 5 schools are scheduled to be completed in 2014 and 2015. Appendix 1 provides a brief summary of the works being carried out for each scheme as well the current status.
Works Completed During September 2014
Rosedale: The remaining areas in the new 2FE school and nursery have been completed and handed over to the school. The installation of the new kitchen is being carried out separately by the school using funding they have received from another source.
Works to be Completed During the 2014/2015 Academic Year
The following is the remaining construction works in Phase 2 which are scheduled to be completed during the 2014/2015 academic year:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.