That Cabinet: 1. Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme and the School Conditions Programme. 2. Note the work undertaken to date to identify those secondary schools that may be suitable for expansion. Reasons for decision Cabinet received an update on the Council's school capital expansion and condition programmes, noting the substantial works undertaken over the last few months on both existing and new schools sites to improve the quality of learning and provide a school place for every child. Cabinet noted the good progress being made on identifying new sites for secondary education expansion. Alternative options considered and rejected Cabinet could have decided to delay or not progress aspects of the schools programmes, which would have impacted upon the Council’s ability to provide sufficient school places. Officer to action: Bobby Finch, Residents Services Classification: Public The report relating to this decision by the Cabinet is available to view on the Council's website or by visiting the Civic Centre, Uxbridge.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
1. Note the progress made with Phases 1, 2 and 3 of the Primary School Expansion Programme and the School Conditions Programme.
2. Note the work undertaken to date to identify those secondary schools that may be suitable for expansion.
Cabinet – 20 November 2014 INFORMATION 1. PRIMARY SCHOOLS
School Places Forecast
The demand for school places in Hillingdon has been rising in recent years and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates which the GLA are now predicting to be slightly higher than they previously forecast. Demand for new school places is arising due to new house building and families moving into the Borough. Overall, at primary school level, the need for additional school places has largely been met by the successful school places expansion programme to date.
The latest forecast for school places indicates a residual need for up to three additional forms of entry in primary schools in the north of the Borough over the next 2-3 years. This additional demand is largely a result of pupils from outside the Borough travelling to primary schools in Hillingdon (an equivalent of 2 FE from Harrow travelling to schools in the East Ruislip area and 1 FE from Hertfordshire attending schools in the Northwood area). Officers are currently developing proposals to meet this need for Members to consider, which is likely to include the provision of bulge year classes and permanent expansions.
Phase 1: Permanent Expansion of Existing Primary Schools
With the exception of some residual remedial works the main expansion works have now been completed at all 8 schools.
Phase 2 - Primary Schools Permanent Expansions
Phase 2 of the Primary School Expansion Programme will permanently expand 18 schools and add a bulge year to an additional school. To date expansion works have been completed at 16 schools. The remaining 3 schools are scheduled to be completed in 2014 and 2015. Appendix 1 provides a brief summary of the works being carried out for each scheme as well the current status.
A number of the completed projects will require some remedial works to be carried out by the contractors during the next few months.
Works Completed During October 2014
Hillingdon: The remaining construction works which included the lift installation have been completed. All the additional accommodation constructed as part of the expansion works are now available for the school to use.
Harlyn: The car park and the remaining external works have now been completed and have been handed over to the school to occupy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.