That Cabinet n ote the progress made with primary and secondary school expansions and the school condition programme. Reasons for decision Cabinet received its monthly update on London’s largest school building programme, aimed at ensuring that every child in the London Borough of Hillingdon would have a quality place at a local school. It was noted that good progress was being made across both primary and secondary sectors, along with resource provision for those with Special Educational Needs. Alternative options considered and rejected None. Officer to action: Bobby Finch, Residents Services Classification: Public The report and any background papers relating to this decision by the Cabinet are available to view on the Council's website or by visiting the Civic Centre, Uxbridge.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Cabinet Members Councillor Jonathan Bianco Councillor David Simmonds
Cabinet Portfolios Finance, Property & Business Services Deputy Leader of the Council / Education & Children’s Services
Officer Contact Bobby Finch, Residents Services
Papers with report Appendix 1: Summary of phase 2 and 3 construction works
HEADLINE INFORMATION
Summary This report provides an update on the primary and secondary school expansions, the school condition works programme and other school capital works.
Contribution to our Putting our Residents First: Our Built Environment; Our People; plans and strategies Financial Management
Investment in schools to adequately address the impact of the population increase within the London Borough of Hillingdon on existing school places. This project also forms part of the Hillingdon Improvement Programme.
Financial Cost The current forecast of the existing Primary Schools Capital Programme is £143,228k inclusive of £796k for Special Resources Provision. An additional £13,500k is forecast new primary school expansions (Phase 4). The Secondary Schools Expansions/Replacement forecast is £150,000k.
Relevant Policy Children, Young People and Learning Overview Committee
Ward(s) affected All wards.
RECOMMENDATIONS That Cabinet note the progress made with primary and secondary school expansions and the school condition programme.
Cabinet – 22 January 2015 INFORMATION 1. PRIMARY SCHOOLS
School Places Forecast
The demand for school places in Hillingdon has been rising in recent years and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates which the GLA are now predicting to be slightly higher than they previously forecast. Demand for new school places is arising due to new house building and families moving into the Borough. Overall, at primary school level, the need for additional school places has largely been met by the successful school places expansion programme to date.
Phase 2 - Primary Schools Permanent Expansions
Phase 2 of the Primary School Expansion Programme will permanently expand 18 schools and add a bulge year to an additional school. To date, expansion works have been completed at 16 schools. The remaining 3 schools are scheduled to be completed in 2015. Appendix 1 provides a brief summary of the works being carried out for each scheme as well as the current status.
A number of the completed projects will require some remedial works to be carried out by the contractors during the next few months.
Projects to be Completed during the 2014 / 2015 Academic Year
The following remaining construction works in Phase 2 are scheduled to be completed during the 2014 / 2015 academic year.
Cherry Lane, Multi Use Games Area (MUGA): A planning application for the revised location for the MUGA was submitted during December 2014. Subject to planning approval, the MUGA is scheduled to be installed during the summer term in 2015.
Glebe: The contractor was originally scheduled to complete the external works in August 2014; however, this has now been revised to a 2015 completion. This revised date includes the substantial remedial works required on the new school building as well as the completion of the external works.
Hermitage: The construction of the new single storey classroom block is progressing well and is due to be completed during February 2015. This will be followed by the removal of the remaining temporary classrooms and the completion of external works. The project is due to be completed in April 2015.
Phase 3 - New Primary Schools
Phase 3 of the Primary School Expansion Programme consists of the construction of 3 Form of Entry (FE) Primary Schools on Lake Farm and the St Andrew’s Park (former RAF Uxbridge) sites both of which are now complete, as well as a further new 3 FE Primary School on land adjacent to Laurel Lane School due for completion in 2015.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.