Resolved
That the application be approved as per officers recommendations, subject to an additional informative relating to ensuring the lift is kept open and available for use .
Major Applications Planning Committee approved this item on Thursday 5 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the application be approved as per officers recommendations, subject to an additional informative relating to ensuring the lift is kept open and available for use .
Report of the Head of Planning, Sport and Green Spaces
Address HAYES AND HARLINGTON STATION STATION ROAD HAYES
Development: Application under Schedule 7 of the Crossrail Act 2008 for the approval of Plans and Specifications associated with the erection of a new station building, external lift shaft, footbridge with lift shafts, extension of platforms 2/3 and 4/5 with canopy modifications, new waiting room to Platform 4/5 and associated lighting. LBH Ref Nos: 10057/APP/2014/4338
Drawing Nos: WSN1B-ALL-DRG-AEA-000270 Rev A03 WSN1B-ALL-DRG-AEA-000271 Rev A02 WSN1B-ALL-DRG-AEA-000273 Rev A02 WSN1B-ALL-DRG-AEA-000278 Rev A03 WSN1B-ALL-DRG-AEA-000280 Rev A03 WSN1B-EAR-DRG-AEA-000011 Rev A08 WSN1B-EAR-DRG-AEA-000260 Rev A02 WSN1C-EAR-DRG-BEN-000250 Rev P02 WSN1C-EAR-DRG-BEN-000251 Rev P02 WSN1C-EAR-DRG-BEN-000252 Rev P02 WSN1C-EAR-DRG-BEN-000253 Rev P02 WSN1C-EAR-DRG-BEN-000254 Rev P02 WSN1C-EAR-DRG-BEN-000255 Rev P02 WSN1C-EAR-DRG-BEN-000256 Rev P02 WSN1C-EAR-DRG-BEN-000257 Rev P02 WSN1C-EAR-DRG-BEN-000258 Rev P02 WSN1C-EAR-DRG-BEN-000259 Rev P02 WSN1C-EAR-SKT-BEN-000005 WSN1C-EAR-SKT-BEN-000006 WSN1C-EAR-SKT-BEN-000007 WSN1B-CNS-PLD-NCA-000012 Rev A01 Written Statement for Information HIL/3/4/NR Design and Access statement HIL/3/4/NR
Date Plans Received: 09/12/2014 Date(s) of Amendment(s): Date Application Valid: 09/12/2014 1. SUMMARY The principle of the development has been established under the Crossrail Act 2008, however Schedule 7 requires the Local Planning Authority to approve details in relation to the erection of a new station building, external lift shaft, footbridge with lift shafts, extension of platforms 2/3 and 4/5 with canopy modifications, new waiting room to Platform 4/5 and associated lighting.
These construction arrangements contribute to improving the linkages within London and the overall regeneration objectives of the area in compliance with London Plan (July 2011) Policies, and it is recommended that the Plans and Specification submission for permanent works under Crossrail Act 2008, Schedule 7 be approved. 2. RECOMMENDATION
Major Applications Planning Committee - 5th March 2015 PART 1 - MEMBERS, PUBLIC & PRESS APPROVAL subject to the following: INFORMATIVES
1 1.Induction loops should be specified to comply with BS 7594 and BS EN 60118-4, and a term contract planned for their maintenance.
2.Care must be taken to ensure that overspill and/or other interference from induction loops in different/adjacent areas does not occur.
3.Flashing beacons/strobe lights linked to the fire alarm should be carefully selected to ensure they remain within the technical thresholds not to adversely affect people with epilepsy. 2 We expect that as part of the development there should be access and signage improvements to enhance the connectivity between the station and the towpath.
3. CONSIDERATIONS
3.1Site and Locality Hayes and Harlington Station is located on Station Road to the south of Hayes Town Centre. The railway line runs east to west with the current station building located on the Station Road bridge, which crosses the railway running north to south. Access to Platforms 4 and 2/3 is gained from two sets of staircases within the Station Building.
Access to Platform 1 is gained via a staircase directly from Station Road located immediately south of the bridge parapet on the eastern flank. This staircase also provides access to the station car park. A further footbridge, to the eastern end of the station, connects Platforms 2/3 and 4/5. In addition, a subway runs from Blyth Road to the west, under Station Road, and provides further access to Station Approach.
Hayes and Harlington Station contains five Platforms. Platform 1 is the southernmost platform, followed by island Platform 2/3. The majority of Platform 4 is a single faced Platform with the remainder comprising an island platform with Platform 5.
A secondary station building is located on Platform 4 and contains a currently unused ground level platform access.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Hayes and Harlington, Station Road, Hayes 10057/APP/2014/4338Report | 151 KB | DownloadRead as text |
Follow Major Applications Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Oct 2023 | To sign and receive the minutes of the previous meetingThat the item be deferred to the meeting of the Hillingdon Planning Committee on 01 November 2023. | Deferred | Open |
| 11 Oct 2023 | West Drayton Leisure Centre - 75127/APP/2023/1646That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 11 Oct 2023 | The Barn Hotel, Ruislip - 7969/APP/2023/1833That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 14 Sep 2023 | To sign and receive the minutes of the previous meetingThat the minutes of the meeting dated 26 July 2023 be agreed as an accurate record. | Agreed | Open |
| 14 Sep 2023 | Pets at Home, Elystan Business Centre, Springfield Road.That the application be approved | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.