That Cabinet n ote the progress made with primary and secondary school expansions and the school condition programme. Reasons for decision Cabinet received its monthly update, tracking progress on London’s largest school building programme which would invest over £300m in new local education facilities by 2020. This would ensure that every child in the London Borough of Hillingdon would have a quality place at a local school. Alternative options considered and rejected None. Officer to action: Bobby Finch, Residents Services Classification: Public The report relating to this decision by the Cabinet is available to view on the Council's website or by visiting the Civic Centre, Uxbridge.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Cabinet Members Councillor Jonathan Bianco Councillor David Simmonds
Cabinet Portfolios Finance, Property & Business Services Deputy Leader of the Council / Education & Children’s Services
Officer Contact Bobby Finch, Residents Services
Papers with report Appendix 1: Summary of phase 2 and 3 construction works
HEADLINE INFORMATION
Summary This report provides an update on the primary and secondary school expansions, the school condition works programme and other school capital works.
Contribution to our Putting our Residents First: Our Built Environment; Our People; plans and strategies Financial Management
Investment in schools to adequately address the impact of the population increase within the London Borough of Hillingdon on existing school places. This project also forms part of the Hillingdon Improvement Programme.
Financial Cost As at Month 10 the forecast of the existing Primary Schools Capital Programme is £142,938k inclusive of £796k for Special Resources Provision. An additional £13,500k is forecast for new Primary School Expansions (Phase 4). The Secondary Schools Expansions and Replacement forecast is £150,000k.
Relevant Policy Children, Young People and Learning Overview Committee
Ward(s) affected All wards.
RECOMMENDATIONS That Cabinet note the progress made with primary and secondary school expansions and the school condition programme.
Cabinet – 19 March 2015 INFORMATION 1. PRIMARY SCHOOLS
School Places Forecast
The demand for school places in Hillingdon has been rising in recent years and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates which the GLA are now predicting to be slightly higher than they previously forecast. Demand for new school places is arising due to new house building and families moving into the Borough. Overall, at primary school level, the need for additional school places has largely been met by the successful school places expansion programme to date.
Phase 2 - Permanent Primary Schools Expansions
Phase 2 of the Primary School Expansion Programme will permanently expand 18 schools and add a bulge year to an additional school. To date expansion works have been completed at 16 schools. The remaining 3 schools are scheduled to be completed during 2015.
Appendix 1 provides a brief summary of the works carried out for each scheme as well as the current status. A number of the completed projects will require some remedial works to be carried out by the contractors during the next few months.
Updates on Projects Completing in 2015
Hermitage Primary School: The construction of the new single storey classroom block has been completed. The contractor has now started work on the completion of the remaining external areas which includes the removal of the temporary modular classroom units.
Cherry Lane Primary School, Multi Use Games Area (MUGA): Planning consent has been granted for the MUGA which is scheduled to be installed during the summer term in 2015 following the completion of the Specialist Resource Provision.
Glebe Primary School: The contractor was originally scheduled to complete this project in 2014; however this has now been revised to a 2015 completion. This revised date includes the substantial remedial works required on the new school building as well as the completion of the external works.
Phase 3 - New Primary Schools
New 3 FE Primary School on the Land Adjacent to Laurel Lane Primary School
Following on from the completion of the foundations of the steel frame in December 2015, work on the infill to the steel frame and construction of the roof are close to being completed. In addition the first stage of the installation of the mechanical and electrical services has started.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.