That Cabinet note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects. Reasons for decision Cabinet received its monthly update, tracking progress on London’s largest school building programme which would invest over £300m in new local education facilities by 2020. This would ensure that every child in the London Borough of Hillingdon would have a quality place at a local school. Alternative options considered and rejected None. Officer to action: Bobby Finch, Residents Services Classification: Public The report and any background papers relating to this decision by the Cabinet are available to view on the Council's website or by visiting the Civic Centre, Uxbridge.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Cabinet Members Councillor Jonathan Bianco Councillor David Simmonds
Cabinet Portfolios Finance, Property & Business Services Deputy Leader of the Council / Education & Children’s Services
Officer Contact Bobby Finch, Residents Services
Papers with report Appendix 1: Summary of phase 2 and 3 construction works
HEADLINE INFORMATION
Summary This report provides an update on the primary and secondary school expansions, the school condition works programme and other school capital works.
Contribution to our Putting our Residents First: plans and strategies Our Built Environment; Our People; Financial Management
Investment in schools to adequately address the impact of the population increase within the London Borough of Hillingdon on existing school places. This project also forms part of the Hillingdon Improvement Programme.
Financial Cost As at Month 12 the forecast of the existing Primary Schools Capital Programme is £142,768k inclusive of £796k for Special Resources Provision. An additional £13,500k is forecast for new Primary School Expansions (Phase 4). The Secondary Schools Expansions and Replacement forecast is £150,000k.
Relevant Policy Children, Young People and Learning Overview Committee
Ward(s) affected All
RECOMMENDATIONS That Cabinet note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects.
Cabinet – 21 May 2015 INFORMATION 1. PRIMARY SCHOOLS
School Places Forecast
The demand for school places in Hillingdon has been rising in recent years and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates which the GLA are now predicting to be slightly higher than they previously forecast. Demand for new school places is arising due to new house building and families moving into the Borough. Overall, at primary school level, the need for additional school places has largely been met by the successful school places expansion programme to date, with some residual excess demand forecast in the north of the borough. Work has commenced on the next refresh of the pupil forecast.
Phase 2 - Permanent Primary Schools Expansions
Phase 2 of the Primary School Expansion Programme will permanently expand 18 schools and add a bulge year to an additional school. To date expansion works have been completed at 16 schools. The remaining 3 schools are scheduled to be completed during 2015. Appendix 1 provides a brief summary of the works carried out for each scheme as well as the current status.
Updates on Projects Completing in 2015
Hermitage Primary School: The construction of the new single storey classroom block has been completed. The contractor is continuing to work on the completion of the remaining external areas which includes the removal of the temporary modular classroom units. The project is scheduled to be completed at the end of May 2015.
Cherry Lane Primary School, Multi Use Games Area (MUGA): The installation of the MUGA has been completed. As this was the last stage of the expansion of Cherry Lane Primary School all construction works at this school have now been completed.
Glebe Primary School: The main construction works at the school have now been completed. The substantial remedial works required on the new school building have now started and are currently planned to be completed by the end the school summer holiday.
Phase 3 - New Primary Schools
St Martin's CoE Primary School
The construction of the new school continues to progress well and remains on programme to be completed by the start of the new school year in September 2015. The scaffolding is starting to be taken down as the brick work is now fully complete and the contractor has now moved on to applying the external render. The internal partition walls as well as the Mechanical and Electrical first fix have now been completed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.