That Cabinet: 1. Note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects. 2. Delegate to the Deputy Chief Executive and Corporate Director of Residents Services, in consultation with the Leader of the Council and Cabinet Member for Finance, Property and Business Services the authority to proceed with the preferred design option for each individual project in the Phase 4 of the Primary School Expansion Programme. Reasons for decision Cabinet received its monthly update, tracking progress on London’s largest school building programme which would invest over £300m in new local education facilities by 2020. This would ensure that every child in the London Borough of Hillingdon would have a quality place at a local school. Cabinet approved the necessary delegated authority to progress Phase 4 of the programme. Alternative options considered and rejected None. Officer to action: Bobby Finch, Residents Services Classification: Public The report relating to this decision by the Cabinet is available to view on the Council's website or by visiting the Civic Centre, Uxbridge.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Cabinet Members Councillor David Simmonds CBE Councillor Jonathan Bianco
Cabinet Portfolios Deputy Leader of the Council / Education & Children’s Services Finance, Property & Business Services
Officer Contact Bobby Finch, Residents Services
Papers with report Appendix 1: Summary of school construction projects
HEADLINE INFORMATION
Summary This report provides an update on the primary and secondary school expansions, the school condition works programme and other school capital works.
Contribution to our Putting our Residents First: Our Built Environment; Our People; plans and strategies Financial Management
Investment in schools to adequately address the impact of the population increase within the London Borough of Hillingdon on existing school places. This project also forms part of the Hillingdon Improvement Programme.
Financial Cost As at Month 2 the Schools Capital Programme budgets have been adjusted to reflect forecast spend following 2014/15 cost underspends and rephasing adjustments. The forecast of the existing Primary Schools Capital Programme is £141,747k, inclusive of £816k for Special Resources Provision.
An additional £219k has been allocated for the Hearing Impairment Resource Base at Vyners School. A further £13,500k is forecast for new Primary School Expansions (Phase 4). The Secondary Schools Expansions and Replacement forecast is £150,000k.
Relevant Policy Children, Young People and Learning Overview Committee
Ward(s) affected All wards.
Cabinet – 23 July 2015 RECOMMENDATIONS That Cabinet:
1. Note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects.
2. Delegate to the Deputy Chief Executive and Corporate Director of Residents Services, in consultation with the Leader of the Council and Cabinet Member for Finance, Property and Business Services the authority to proceed with the preferred design option for each individual project in the Phase 4 of the Primary School Expansion Programme.
INFORMATION 1. PRIMARY SCHOOLS
School Places Forecast
The demand for school places in Hillingdon has been rising in recent years and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates which the GLA are now predicting to be slightly higher than they previously forecast. Demand for new school places is arising due to new house building and families moving into the Borough. Overall, at primary school level, the need for additional school places has largely been met by the successful school places expansion programme to date, with some residual excess demand forecast in the north of the borough. Work is now well underway on the next refresh of the pupil forecast.
Phase 2 - Permanent Primary Schools Expansions
Phase 2 of the Primary School Expansion Programme permanently expanded 18 schools and added a bulge year to an additional school which totals 19 schools. These expansion works have been completed with only remedial works at Glebe Primary School outstanding. Appendix 1 provides a brief summary of the works carried out for each scheme as well as the current status.
Glebe Primary School
The main construction works at the school have now been completed. The remaining substantial remedial works required on the new school building which have been started are currently planned to be completed by the end the school summer holiday.
Phase 3 - New Primary Schools
St Martin's CoE Primary School
The construction works are close to be finished with a scheduled completion date of the first week in August. The building will then be handed over to the school the following week. A 'topping out' ceremony attended by representatives from the Frays Academy Trust, project team, contractor, senior council officers and Cabinet Members was held on 7 July.
Cabinet – 23 July 2015 Phase 4 - Primary School Expansions
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.