That Cabinet: 1. Note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects. 2. Approve the 2015/16 School Condition Programme of works as outlined in this report. 3. Delegate autho rity to the Deputy Chief Executive and Corporate Director of Residents Services in consultation with the Leader of the Council and Cabinet Member for Finance, Property and Business Services to make any required changes to the school condition programme of works such as the addition or removal of individual projects. Reasons for decision Cabinet received its regular update on London’s largest school building programme which would invest over £300m in new local education facilities by 2020. This would ensure that every child in the London Borough of Hillingdon would have a quality place at a local school. In addition to this, Cabinet approved the forthcoming School Condition Programme, improving the existing fabric of a number of schools in the Borough. Alternative options considered and rejected Cabinet could have determined proposals for alternative school condition works. Officer to action: Bobby Finch, Residents Services Classification: Public The report and any background papers relating to this decision by the Cabinet are available to view on the Council's website or by visiting the Civic Centre, Uxbridge.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
1. Note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects.
/recommendations continued overleaf...
Cabinet – 21 January 2016 School Condition Programme
2. Approve the 2015/16 School Condition Programme of works as outlined in this report.
3. Delegate authority to the Deputy Chief Executive and Corporate Director of Residents Services in consultation with the Leader of the Council and Cabinet Member for Finance, Property and Business Services to make any required changes to the school condition programme of works such as the addition or removal of individual projects.
Reason for recommendation
Approving this programme will allow the necessary repair or replacement works to be progressed on the schools, avoiding the potential impact on their daily operations due to parts of the building fabric being beyond repair, or equipment which is at the end of its life. Ensuring these works are undertaken will minimise the risk of health and safety related issues or the possibility of a school closure occurring.
Policy Overview Committee comments
None at this stage.
3. INFORMATION
3.1PRIMARY SCHOOLS
School Places Forecast
The demand for school places in Hillingdon has been rising in recent years and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates which the GLA are now predicting to be slightly higher than they previously forecast. Demand for new school places is also arising due to new house building and families moving into the Borough. The 2015 update of the pupil forecast has now been completed. Overall, at primary school level, the need for additional school places has largely been met by the successful school places expansion programme to date, with some excess demand forecast in future years, mainly in the north of the borough.
Phase 4 - Primary School Expansions
The latest forecast for school places indicates a residual need for three additional forms of entry in primary schools in the north of the Borough over the next 2-3 years. This additional demand is largely a result of pupils from outside the Borough travelling to primary schools in Hillingdon (an average of 1.5 FE travelling to schools in the East Ruislip area and 1 FE from Hertfordshire attending schools in the Northwood area).
Initial site investigation surveys are complete on schools deemed suitable for potential expansion. Work on potential expansion options for each of these sites have also been completed and presented to Members for consideration.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.