Resolved
RESOLVED – 1. That the information provided by the Deputy Director of Residents Services, Development and Assets be noted.
Corporate Services, Commerce and Communities Policy Overview Committee noted this item on Thursday 10 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – 1. That the information provided by the Deputy Director of Residents Services, Development and Assets be noted.
Procurement/Category Management Overview
Contact Officer: Perry Scott Telephone: 01895 277240
REASON FOR ITEM
For this meeting, Members will be provided with a presentation from the Deputy Director of Residents Services, Development & Assets. At the last meeting of the Committee during consideration of draft budget proposals, Members expressed an interest of hearing about the changes in the Council's Procurement practices which has resulted in savings to the Council.
OPTIONS OPEN TO THE COMMITTEE
1. Members to consider the information contained in the report 2. To receive a presentation
Background and Current Position
1. Following the successful merging of the corporate procurement and commissioning functions in November/December 2013 a number of performance improvements have been achieved including: The successful introduction of a category management approach Improved contract visibility Year on year savings from existing and new contracts Greater ownership and focus of contract and supplier management Ensuring value for money within a structured work plan to deliver savings and projects within faster timescales Improved process and efficiencies by streamlining activity and management within category support and e-Procurement The successful alignment of the team to Council service areas
2. Further minor staffing realignments have taken place over the last two years to ensure adequate procurement support across the directorates. Any alterations made to the team structure were consistent with what was originally agreed in 2013.
3. Whilst there is a category management team in place at LB Hillingdon, the existing category teams undertake a mix of work which can mean that more costly professional resource can be tied up in low value, straightforward procurements that could be undertaken efficiently by other staff.
4. There is now a developing requirement to deliver more complex, strategic or cross-cutting projects including the remodelling of a large number of existing contracts and service delivery models. It was agreed that there needed to be a clearer differentiation between the procurement support requirements of the more complex projects and the support requirements for more straightforward procurements.
Corporate Services & Partnerships Policy Overview Committee – 10 March 2016 Part I – Members, Public and Press 5. In order to deliver this new approach and to achieve a number of additional operational improvements a restructuring exercise has been undertaken. The exercise is currently in the consultation phase with staff and is expected to be concluded by the end of March with implementation commencing in April/May 2016.
Proposed New Category Management Structure
6. It is proposed to provide a dedicated high quality category management team with the capacity to manage in excess of 100 large corporate and cross-cutting procurement projects identified through the MTFF or BID at any given time.
7. An expanded e-Procurement team will take on the lower value more routine procurements for the Council. This team will utilise new software system (Bravo) to manage the Council's quotes and tender process; ensuring compliance and competitiveness on all low value procurement.
8. This improved differentiation of procurement work will allow the professional resource to concentrate on the more complex strategic projects within the MTFF and BID. It will also mean that more straightforward lower value procurements are undertaken by other staff using Bravo. The proposed structure will therefore deliver efficiencies and cost savings as well as providing a higher level of support to key procurements.
9. The proposed new structure and approach to procurement will deliver a series of improvements including:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Procurement in the CouncilReport | 67 KB | DownloadRead as text |
Follow Corporate Services, Commerce and Communities Policy Overview Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Apr 2021 | Minutes of the meeting held on 4 March 2021That the minutes of the meeting dated 4 March 2021 be agreed as an accurate record. | Agreed | Open |
| 6 Apr 2021 | Exclusion of Press and PublicIt was agreed that items 1-11 were in Part I and would be considered in public and, if required, item 12 was in Part ... | Agreed | Open |
| 6 Apr 2021 | Review: Voluntary Sector Response to Covid-19 Pandemic - draft reportRESOLVED That the Corporate Services, Commerce & Communities Policy Overview Committee: 1) Agreed the final report an... | Agreed | Open |
| 6 Apr 2021 | The Committee's Next Review Topic - Ideas / Selection PhaseThat the Committee considered potential topic ideas for their next major review for officers to scope further and rep... | Decided | Open |
| 6 Apr 2021 | Past Review Update: Homophobic, Biphobic & Transphobic Bullying ReviewRESOLVED That the Committee noted the updates on recommendations as agreed by Cabinet in June 2019. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.