That Cabinet note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects. Reasons for decision Cabinet received its regular update on London’s largest school building programme which would invest over £300m in new local education facilities by 2020. This would ensure that every child in the London Borough of Hillingdon would have a quality place at a local school. It was noted that the Council-led secondary school re-build project at Northwood School had progressed well, in comparison to the Abbotsfield and Swakeleys schools re-builds managed by the Education Funding Agency, which had suffered significant delay. Alternative options considered and rejected None. Officer to action: Bobby Finch, Residents Services Classification: Public The report and any background papers relating to this decision by the Cabinet are available to view on the Council's website or by visiting the Civic Centre, Uxbridge.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
That Cabinet note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects.
Cabinet – 17 March 2016 Policy Overview Committee comments
None at this stage.
3. INFORMATION
3.1PRIMARY SCHOOLS
School Places Forecast
The demand for school places in Hillingdon has been rising in recent years and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates which the GLA are now predicting to be slightly higher than they previously forecast. Demand for new school places is also arising due to new house building and families moving into the Borough. Overall, at primary school level, the need for additional school places has largely been met by the successful school places expansion programme to date, with some excess demand forecast in future years, mainly in the north of the Borough.
Phase 4 - Primary School Expansions
The latest forecast for school places indicates a residual need for three additional forms of entry in primary schools in the north of the Borough, which is expected to arise from 2016. This includes demand for places for pupils resident in neighbouring boroughs. At the February 2016 Cabinet meeting approval was received to install modular classroom units at 2 primary schools to be used to accommodate bulge classes. The tender documents required to procure a works contractor for these projects are currently being prepared.
There is also a need for permanent expansions. Members have reviewed the feasibility options on the schools deemed suitable for expansion and officers have provided feedback to schools on the options that have been selected.
3.2SECONDARY SCHOOLS
School Places Forecast
The rising demand for school places is now moving into secondary schools. The latest forecast shows a longer-term sustained pressure for additional secondary school places. The planned expansions of Northwood, Abbotsfield and Swakeleys schools will add 5.5 forms of entry capacity. Over the next five years, 19 additional forms of entry are forecast to be required. The forecast need for additional secondary school places is higher in the northern parts of the Borough, where there tends to be a higher number of pupils living outside the Borough travelling to a Hillingdon school and capacity in existing schools is lower. A new free school, Pinner High School, is opening in Harrow in 2016, close to the border with Hillingdon and this offers an additional choice for Hillingdon residents.
Priority Schools Building Programme (PSBP)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.