That Cabinet: 1) Note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects. 2) Delegate full authority to the Leader of the Council and Cabinet Member for Finance, Property and Business Services, in consultation with the Deputy Chief Executive and Director of Residents Services, to make all necessary procurement and financial decisions, including approving which schools are to expand, the appointment of consultancies and the placing of building contracts required for the permanent expansion of 3 primary schools as part of phase 4 of the primary school expansion programme. Reasons for decision Cabinet received its regular update on London’s largest school building programme to ensure that every child in the London Borough of Hillingdon would have a quality place at a local school. Delegated authority was given to expand further primary schools in the Borough to meet demand. Alternative options considered and rejected None. Officer to action: Bobby Finch, Residents Services Classification: Public The report and any background papers relating to this decision by the Cabinet are available to view on the Council's website or by visiting the Civic Centre, Uxbridge.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
1. Note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects.
Primary School Expansions Phase 4
2. Delegate full authority to the Leader of the Council and Cabinet Member for Finance, Property and Business Services, in consultation with the Deputy Chief Executive and
Cabinet – 21 April 2016 Director of Residents Services, to make all necessary procurement and financial decisions, including approving which schools are to expand, the appointment of consultancies and the placing of building contracts required for the permanent expansion of 3 primary schools as part of phase 4 of the primary school expansion programme.
Reason for recommendation
The Education Act 1996 states that local authorities have a duty to educate children within their administrative area which forms part of the Council's legal requirement to meet the educational needs of the borough. Failure to proceed with providing suitable additional accommodation as part of phase 4 of the school expansion programme will mean that there will be insufficient pupil places to meet the expected demand for places in future years.
Policy Overview Committee comments
None at this stage.
3. INFORMATION
3.1PRIMARY SCHOOLS
School Places Forecast
The demand for school places in Hillingdon has been rising in recent years and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven by rising birth rates which the GLA are now predicting to be slightly higher than they previously forecast. Demand for new school places is also arising due to new house building and families moving into the Borough. Overall, at primary school level, the need for additional school places has largely been met by the successful school places expansion programme to date, with some excess demand forecast in future years, mainly in the north of the Borough.
Phase 4 - Primary School Expansions
The latest forecast for school places indicates a residual need for three additional forms of entry in primary schools in the north of the Borough, which is expected to arise from 2016. This includes demand for places for pupils resident in neighbouring boroughs. At the February 2016 Cabinet meeting approval was received to install modular classroom units at 2 primary schools to be used to accommodate bulge classes. The tender documents required to procure a works contractor for these projects are currently being prepared and will be released during April 2016.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.