Resolved
Resolved - That the application was approved.
Major Applications Planning Committee approved this item on Tuesday 6 December 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved - That the application was approved.
Report of the Head of Planning, Sport and Green Spaces
Address BRIDGE HOUSE, DENBRIDGE IND. ESTATE OXFORD ROAD UXBRIDGE
Development: Demolition of existing office building (Use Class B1(a) and multi-storey car park and redevelopment of the site to provide a new office (Use Class B1(a) building, associated multi-storey car park and ancillary cafe unit (Use Class A1/A3) LBH Ref Nos: 40050/APP/2016/852
Drawing Nos: 13035_(01)-E-001_Existing West and North Elevation Bridge House D and A Statement Part 2 Bridge House D and A Statement Part 3 Bridge House D and A Statement Part 1 MA_3041_1001 Landscape Masterplan MA_3041_2000 Landscape Masterplan Roof Level MA_3041_2001 Level 7 Roof Terrace Illustrative Mas 13035_(03)-P-008_Proposed Roof Plan_PL2. 13035_(03)-P-0B0_Proposed Basement Floor Plan_PL2 13035_(03)-X-001_Proposed Site Section_PL2 13035_(03)-X-002_Proposed Section_PL2 13035_Bridge House_Area Schedule_Planning Submissi 13035_(03)-E-001_Proposed West Elevation_PL2 13035_(01)-E-002_Existing East and South Elevation 13035_(01)-P-001_Existing Typical Floor Plan_PL2 13035_(01)-X-001_Existing Bridge House Section_PL2 13035_(03)-E-002_Proposed North Elevation_PL2 13035_(03)-E-003_Proposed East Elevation_PL2 13035_(03)-E-004_Proposed South Elevation_PL2 13035_(03)-E-005_Proposed Multi Storey Car Park El 13035_(03)-P-001_Proposed First Floor_PL2 13035_(03)-P-002_Proposed Second Floor Plan_PL2 13035_(03)-P-003_Proposed Third Floor Plan_PL2 13035_(03)-P-004_Proposed Fourth Floor_PL2 13035_(03)-P-005_Proposed Fifth Floor Plan_PL2 13035_(03)-P-006_Proposed Sixth Floor Plan_PL2 13035_(03)-P-007_Proposed Seventh Floor Plan_PL2 Site Access Survey Summary MA_3041_1000 Rev F Illustrative Masterplan 13035_(03)-P-0G0_Proposed Ground Floor Plan_PL4 13035_(03)-S-001_Proposed Location Plan_PL3 MA-3041-3000 Rev A Landscape Section A MA-3041-3001 Rev A Landscape Section B MA-3041-3002 Landscape Section C 13035_(03)-S-002_Proposed Site Plan_PL5
Date Plans Received: 29/02/2016 Date(s) of Amendment(s): 11/10/2016 Date Application Valid: 08/03/2016 29/02/2016 02/11/2016 02/08/2016
Major Applications Planning Committee - 6th December 2016 PART 1 - MEMBERS, PUBLIC & PRESS DEFERRED ON 16th November 2016 FOR FURTHER INFORMATION .
This application has previously been presented to the Major Applications Planning Committee on the 16th of November 2016. The resolution of the Committee on the 16th of November 2016 was to defer the application as Members required further information on the proposed highways mitigation measures.
Following Planning Committee's resolution to defer the application a meeting was held between the Applicant's Transport Consultants and the Council's Highways Engineers on the 21st of November 2016. Subsequent to this meeting the Applicant has confirmed acceptance of the requirement to increase the obligation towards improvements to the local highway network from £150,000 to £500,000. This contribution remains independent of other contributions sought to mitigate the impact of the development, such as the £150,000 contribution towards public realm improvements and £30,000 toward improvements to the canal/towpath.
The applicant has also provided an additional plan to show potential highways mitigation works (plan reference MBSK161122-1).
Following the meeting on the 21st of November 2016 the Council's Highways Engineer has provided the additional comments below:
'Following the deferment of this application from the last committee held on 16th November 2016, the developer's traffic consultants arranged a meeting with the Council highways engineers.
The outcome was that their client is seeking a resolution before the end of the year and a transport study of the highway network involving traffic surveys and modelling could take up to 6 months to complete.
In view of this they are agreeable to a sum of £ 500,000 for highway mitigation works. The study would have to be carried out prior to commencement of the development.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Bridge House- 40050/APP/2016/852Report | 55 pages | DownloadRead as text |
Follow Major Applications Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Oct 2023 | To sign and receive the minutes of the previous meetingThat the item be deferred to the meeting of the Hillingdon Planning Committee on 01 November 2023. | Deferred | Open |
| 11 Oct 2023 | West Drayton Leisure Centre - 75127/APP/2023/1646That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 11 Oct 2023 | The Barn Hotel, Ruislip - 7969/APP/2023/1833That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 14 Sep 2023 | To sign and receive the minutes of the previous meetingThat the minutes of the meeting dated 26 July 2023 be agreed as an accurate record. | Agreed | Open |
| 14 Sep 2023 | Pets at Home, Elystan Business Centre, Springfield Road.That the application be approved | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.