That Cabinet note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects. Reasons for decision Cabinet received its monthly update to review progress on the Council’s substantial school building and school condition programmes, investing significant resources in local education facilities over the last few years and into the coming years. It was noted that due to this investment, Hillingdon had just topped the list in West London for families receiving an offer at one of their preferred primary schools, and that Hillingdon had once again ensured that every child was offered a primary school place for September 2017. Alternative options considered and rejected None. Officer to action: Bobby Finch, Residents Services Classification: Public The report and any background papers relating to this decision by the Cabinet are available to view on the Council's website or by visiting the Civic Centre, Uxbridge.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
That Cabinet note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects.
Cabinet – 20 April 2017 Policy Overview Committee comments
None at this stage.
3. INFORMATION
3.1PRIMARY SCHOOLS
School Places Forecast
The demand for school places in Hillingdon has been rising in recent years and is forecast to continue to rise in line with national and London-wide predictions. Demand for reception places at primary school level is being driven in part by rising birth rates, new house building and families moving into the Borough. Overall, at primary school level, the need for additional school places has largely been met by the successful school places expansion programme to date, with some excess demand forecast in future years, in the north of the Borough and particularly in the Hayes / surrounding areas where there has been a loss of school places from Nanaksar Primary School and also where there is a concentration of residential development.
The updated forecast shows that demand for primary places in the north of the Borough appears to be reaching a plateau. However, there remains a residual need for a small number of additional forms of entry. Thirty additional Reception places have been provided at Hillside Infant School for September 2016. Demand for places in the south of the Borough is still forecast to grow, particularly in the Hayes area where there has been significant housing development, with more expected in the future. For 2016, Guru Nanak Academy offered an additional 30 Reception places. There is interest from a potential free school provider for new primary school provision in the south of the Borough.
Phase 4 - Permanent School Expansions
Following planning consent being received for the expansions of Hillside Infants and Junior School and Warrender Primary School in February 2017, the process of procuring a works contractor has now started. The Invitation to Tender has now been issued to the shortlisted contractors and subject to Cabinet Member approval, a contractor is expected to be appointed in May 2017 with works commencing on site at the end of July 2017.
The statutory proposals for the expansion of Hillside Infant and Junior schools and Warrender Primary were approved at the February 2017 Cabinet meeting.
3.2SECONDARY SCHOOLS
School Places Forecast
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt...
Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.