Major Applications Planning Sub-Committee (HS2) approved this item on Monday 12 March 2018. Below is the council's own wording, with the papers it was decided on.
That the application be approved as per officer's recommendation, subject to the informative that the application is carried out in accordance with the Local Transport Traffic Management Plan. That the application be approved as per officer's recommendation, subject to the informative that the application has to happen in accordance with the Local Transport Traffic Management Plan.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report to Major Applications Planning Sub-Committee (HS2)
Summary
This application comprises a submission for approval of construction arrangements under Schedule 17 of the HighSpeed Rail (London-West Midlands) Act 2017 (The Act), in relation to the approval of lorry routes in connection with the Cadent Gas HP06 North and South compounds off Harvil Road, required for a gas pipeline diversion.
The application is the fourth HS2 Schedule 17 planning submission that has been deposited with the Council. These Schedule 17 planning submissions can best be likened to the submission of reserved matters, where outline planning consent has already been granted. However, the role ofthe Planning Authority is heavily restricted as to what can and cannot form the basis of a decision.
The details relate purely to the lorry routes associated with diversion works required to lower an existing gas pipeline to an appropriate level, in order to accommodate the HS2 route, which will be in a cutting at this point.
Two (north & south) 'Gas Pipeline Diversion' site compounds are proposed, situated on the east side of Harvil Road, separated by the existing east/west Chiltern Railway line. The proposed lorry routes for all Large Goods Vehicles (LGVs) will utilise the following roads from the M40 motorway to the site compounds: A40, Swaleleys Road (B467) and Harvil Road. ______________________________________________________________________________________
HS2 Planning committee - 12th March 2018 PART 1 - MEMBERS, PUBLIC AND PRESS There is no statutory obligation to consult with neighbours or other statutory bodies.
The applicant submits that the traffic impacts of the work have been assessed to be in keeping with the HS2 Environmental Minimum Requirements (EMRs), set out in the Planning Memorandum, although in this case, the proposed vehicle numbers/types trigger the need for approval of lorry routes.
HS2 Ltd has designed a proposal to suit the objectives of diverting an existing gas pipeline in order to maintain the continuity of the HS2 project. The routing is understood to have been optimised, but with no functional road network alternatives being available for consideration.
Nevertheless, the suggested construction routes will involve usage of the already heavily trafficked classified and Transport for London road network. The peak morning and afternoon traffic periods are considered to be of most concern, as these roads are running to over-capacity and the proposal will potentially add to current delays and congestion.
It is acknowledged that the majority of movements would be between the Tarmac Site off Harvil Road (to the west) and the HS2 Compounds, 40m further south of Harvil Road (to the east). The limited timeframe for the peak load of traffic, and what our consent is being sought for, is not considered to pose a significant impact on the road network. However, there are concerns about the timing of the traffic movements in general and these will need to be set out in the traffic management plan.
An informative is therefore recommended seeking a traffic management plan specific to the proposed works for this lorry route approval, indicating the measures to reduce impacts on peak hours of traffic (7.30 - 9.30am and 4.30 to 6.30pm).
Recommendation
APPROVAL
INFORMATIVES
1. IHS2 Informative HS2
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Major Applications Planning Sub-Committee (HS2) at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.