501 & 504 Stone Close, Yiewsley - 73585/APP/2018/2484
ApprovedPlanning1 paper
Major Applications Planning Committee approved this item on Wednesday 14 November 2018. Below is the council's own wording, with the papers it was decided on.
That the application be approved, subject to the Head of Planning, Transportation and Regeneration determining measures to address potential contaminated water with the Council’s Flood and Water Management officer. That the application be approved, subject to the Head of Planning, Transportation and Regeneration determining measures to address potential contaminated water with the Council’s Flood and Water Management officer.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report to Major Applications Planning Committee, 30 pages
Report of the Head of Planning, Transportation and Regeneration
Address 501 & 504 STONE CLOSE YIEWSLEY
Development: Demolition of existing buildings and erection of building for the purposes of Use Class B1c/B2/B8 with associated access and parking LBH Ref Nos: 73585/APP/2018/2484
Drawing Nos: Design & Access Statement (16 October 2018) 002 Site Identification Plan 001 Site Location Plan 26992_T Rev. 0 Topographical Survey 26992_T UG Rev. 0 Underground Utility Survey Energy Strategy (Issue 1) Overheating Risk Analysis (Issue 1) Covering Letter (5 July 2018) 17-112 / 300 Rev. P2 Drainage Strategy 4435-PL-010 Ground Floor Plan 4435-PL-011 First Floor Plan 4435-PL-040 Existing Site Plan 4435-PL-041 North Building Floor Plan 4435-PL-042 South Building Floor Plan 4435-PL-043 North Building Elevations and Sections 4435-PL-044 South Building Elevations and Sections Video Inspection Building Plan and Elevations 17-112R_001 Flood Risk Assessment (May 2018) Preliminary Geo-Environmental Risk Assessment (November 2017) External Lighting and CCTV Assessment Issue 3 (May 2018) T&PPB6821R001F0.1 Rev. 0.1/Final Travel Plan (14 May 2018 T&PPB6821R001D0.1 Transport Statement Rev. 0.1/Final (14 May 2018) Applicant Response to Highways Officer Comments (24 October 2018) Applicants Response to TfL Comments (24 October 2018) 4435-PL-020 Rev. D Elevations MSW 5206 October 2018 (Revised) Planning Statement 746.19.04 Rev. B Planting Layout 4435-PL-004 Rev. F Block Plan Showing Operational Parking 4435-PL-002 Rev. E Block Plan L1700001305 Preliminary Ecological Appraisal (6 December 2017) 4435-PL-030 Rev. B Cross Sections 4435-PL-031 Rev. B Site Section 4435-PL-032 Rev. B Site Section showing Design Evolution 4435-PL-003 Rev. E Site Plan External Works Rev. 01/Final Air Quality Assessment (14 May 2018)
Date Plans Received: 05/07/2018 Date(s) of Amendment(s): 13/07/2018 Date Application Valid: 17/07/2018 22/08/2018 28/09/2018 05/07/2018 25/10/2018 06/09/2018
Major Applications Planning Committee - 14th November 2018 PART 1 - MEMBERS, PUBLIC & PRESS 1. SUMMARY The application seeks permission for demolition of two existing and vacant buildings and the erection of one mixed use class B1, B2 or B8 unit and one inspection bay building. The works also include new car parking and landscaping. Subject to conditions and a Section 106 agreement, the proposed development is considered to be acceptable with regard to principle, design, amenity, highways, air quality, noise, lighting, flooding, energy, accessibility, waste and security. 2. RECOMMENDATION That delegated powers be given to the Head of Planning, Transportation and Regeneration to grant planning permission, subject to a Legal agreement securing the following:
1. Highway Works: S278/S38 for required Highways Works 2. Construction Training: A financial contribution to the sum of: Training costs: £2500 per £1m build cost plus Coordinator Costs or an in kind scheme to be provided. 3. Travel Plan to include £20,000 Bond; Low Emission Strategy Travel Plan to include, but not be limited to: a) Setting targets for the increased use of low/zero emission vehicles technologies for the servicing and delivery vehicles; b) Active promotion of cleaner vehicle technologies for all users of the development with targets set for increased trips by zero emission vehicles; c) Active promotion and enforcement of no idling on site 4) Project Management & Monitoring Fee: A financial contribution equal to 5% of the total cash contributions.
B) That the applicant meets the Council's reasonable costs in the preparation of the S106/S278/S38 Agreement and any abortive work as a result of the agreement not being completed.
C) That officers be authorised to negotiate and agree the detailed terms of the proposed agreement and conditions of approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Major Applications Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.