Resolved
RESOLVED That : the minutes of the meetings dated 9 October 2018 and 9 May 2019 be agreed as an accurate record.
Major Applications Planning Sub-Committee (HS2) agreed this item on Tuesday 4 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That : the minutes of the meetings dated 9 October 2018 and 9 May 2019 be agreed as an accurate record.
Minutes
MAJOR APPLICATIONS PLANNING SUB- COMMITTEE (HS2)
9 October 2018
Meeting held at Committee Room 5 - Civic Centre, High Street, Uxbridge
Committee Members Present: Councillors Ian Edwards (Chairman) Eddie Lavery (Vice-Chairman) Nicola Brightman Roy Chamdal Janet Duncan John Oswell David Yarrow
LBH Officers Present: James Rodger, Head of Planning and Enforcement Ian Thynne, Principal Sustainability Officer Raj Alagh, Borough Solicitor
3. APOLOGIES FOR ABSENCE (Agenda Item 1)
There were no apologies for absence.
4. DECLARATIONS OF INTEREST IN MATTERS COMING BEFORE THIS MEETING (Agenda Item 2)
There were no declarations of interest.
5. TO SIGN AND RECEIVE THE MINUTES OF THE PREVIOUS MEETINGS (Agenda Item 3)
RESOLVED That: The minutes of the meetings on 12 March 2018 and 10 May 2018 be approved as an accurate record.
6. MATTERS THAT HAVE BEEN NOTIFIED IN ADVANCE OR URGENT (Agenda Item 4)
None.
7. TO CONFIRM THAT THE ITEMS MARKED IN PART 1 WILL BE CONSIDERED IN PUBLIC AND THOSE ITEMS MARKED IN PART 2 WILL BE HEARD IN PRIVATE (Agenda Item 5)
It was confirmed that all items would be considered in public.
8. MERCK SHARPE DOHME (MSD) SITE OFF BREAKSPEAR ROAD SOUTH - 72870/APP/2018/2952 (Agenda Item 6) Request for approval of lorry routes under condition imposed by Schedule 17 of the High Speed Rail (London - West Midlands) Act 2017 relating to road transport associated with demolition, site clearance and other enabling works at the Merck Sharpe Dohme (MSD) worksites.
Officers introduced the report and presented the plans to the Committee. The report explained that the application related to lorry routes for large goods vehicles (LGVs) associated with demolitions, construction of a new MSD 'haul' road, ground investigations, new above-ground structures and utility works / diversion activities to the existing MSD, Gatesmead Farmhouse and Oak Farm sites. It was anticipated that, on average, a peak of 160 two-way LGV movements would be generated on a daily basis between September 2018 and January 2019 for the construction of the new MSD road, with a drop in activity to an average level of 80 LGVs per day to June 2019. Thereafter, it was estimated that there would be approximately 24 LGV movements per day until July 2019. The Committee was requested to consider whether it was acceptable for the MSD site to be accessed by 24 or more LGVs per day. When leaving the site, LGVs would be directed onto Breakspear Road South and would enter Swakeleys Road before joining the A40. Members were informed that the A40 was not part of the London Borough of Hillingdon network and fell within the remit of TfL.
Councillors were advised that the role of the Committee was to facilitate the will of Parliament in respect of HS2 whilst taking into consideration the needs of local residents. The application was recommended for approval subject to the informative.
Members expressed concern at the lack of information in the report regarding the potential impact on free flowing traffic in the area, particularly during peak periods. Moreover, concern was expressed regarding the informative which appeared inadequate and weak. Councillors commented that Breakspear and Swakeleys Roads were already heavily congested at peak times and felt the problem would be exacerbated by the addition of lorries entering and exiting the MSD site. Members also expressed concern regarding the potential impact on road safety in the area.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
9 October 2018: minutesMinutes | 123 KB | DownloadRead as text |
PDF |
To sign and receive the minutes of the previous meetingMinutes | 99 KB | Download |
Follow Major Applications Planning Sub-Committee (HS2) at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 May 2021 | To sign and receive the minutes of the previous meetings dated 25 November 2020 and 14 January 2021That the minutes of the meetings dated 25 November 2020 and 14 January 2021 be approved as an accurate record. | Approved | Open |
| 4 May 2021 | River Colne, River Alignment, Moorhall Road - 76182/APP/2021/399That the application be approved. | Approved | Open |
| 4 May 2021 | Land Adjacent to Breakspear Road South - 76185/APP/2021/449That the application be approved. That the application be approved. | Approved | Open |
| 14 Jan 2021 | Election of Vice ChairmanThat Councillor Higgins be elected as Vice Chairman of the Major Applications Planning Sub Committee for the remainde... | Decided | Open |
| 25 Nov 2020 | Apologies for AbsenceAll Members were present, but due to technical difficulties, Cllr Brightman was unable to take part and left the meet... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.