Resolved
RESOLVED That: the application be refused.
Major Applications Planning Committee refused this item on Wednesday 20 November 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That: the application be refused.
Report of the Head of Planning, Transportation and Regeneration
Address WATERCRESS BEDS SPRINGWELL LANE HAREFIELD
Development: Change of use of site to a camping site (Use Class D2), alteration of existing building to provide visitors' centre, erection of seven camping pods, associated landscaping and car parking with 18 spaces. LBH Ref Nos: 24597/APP/2018/2373
Drawing Nos: GA1004 GA2001 GA2000 GA1000 GA1003 GA1002 GA1001 Flood Risk & SUDS Assessment with appendices A-E Arboricultural Impact Assessment and Tree Protection Survey Preliminary Ecological Appraisal and Bat Roost Assessment Sustainability Statement Transport Statement Design & Access Statement
Date Plans Received: 26/06/2018 Date(s) of Amendment(s): Date Application Valid: 05/11/2018 1. SUMMARY Planning permission is sought for the change of use of the site known as Watercress Beds, Springwell Lane to a camping (or 'Glamping' site) Use Class D2.
Overall the development would result in an increase of built footprint of approx. 127sqm. The footprint of the visitors centre would be 328sqm which is considered excessive for the proposed use. Furthermore the height of visitors centre would be approx. 5.3m which is unjustified for a single storey building. In addition to the size of the visitors centre, the planning application seeks permission for seven 'glamping pods' and change of use of the whole site to D2 campsite and so the unrestricted use of associated vehicles (e.g. camper vans and/or American RVs) and additional tents could result in excessive visual clutter to the detriment of the overall appearance of the site.
Given the overall size of the visitors centre and the potential for further visual clutter, the development is considered to have an unacceptable impact on the openness of the greenbelt.
Residential use on the site
There are two residential properties on the site with at least one not currently benefiting from planning permission and all are included within the red line. Although these properties fall within the red line plan, no reference to these properties has been made within the current application. Because no information has been submitted a full assessment is not possible. However, it is considered that these properties would contribute cumulatively to
North Planning Committee - 20th November 2019 PART 1 - MEMBERS, PUBLIC & PRESS encroachment into the Green Belt and would have a negative impact on the openness of the Green Belt when assessed alongside the proposed visitors centre and 'glamping pods'.
Flood risk: The site is shown to be a dry island surrounded by Flood Zone 3 of the River Colne. The proposed development has failed to provide an adequate Flood Emergency Plan. Furthermore the FRA does not provide sufficient information to demonstrate that surface water runoff from the site will not increase as a result of the proposed development or that the location and height of proposed pods are above the modelled flood water levels.
The site is located within Source Protection Zone (SPZ) 1 and upon a principal aquifer (with the secondary aquifer in hydraulic continuity with the Principal aquifer). In light of this the proposed development has failed to provide a Preliminary Risk Assessment (PRA) to address the possible risk to controlled waters and has submitted insufficient information on the proposed drainage scheme to determine risks to potable water supplies *SPZ 1.
The proposed development therefore raises significant issues with regards to surface water run off, flood risk and risk to human safety and has failed to address the possible risk to controlled waters and potable water supplies.
Biomass Boiler
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Watercress Beds, Spring Lane, Harefield: 24597/APP/2018/2373Report | 42 pages | DownloadRead as text |
Follow Major Applications Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Oct 2023 | To sign and receive the minutes of the previous meetingThat the item be deferred to the meeting of the Hillingdon Planning Committee on 01 November 2023. | Deferred | Open |
| 11 Oct 2023 | West Drayton Leisure Centre - 75127/APP/2023/1646That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 11 Oct 2023 | The Barn Hotel, Ruislip - 7969/APP/2023/1833That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 14 Sep 2023 | To sign and receive the minutes of the previous meetingThat the minutes of the meeting dated 26 July 2023 be agreed as an accurate record. | Agreed | Open |
| 14 Sep 2023 | Pets at Home, Elystan Business Centre, Springfield Road.That the application be approved | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.