Resolved
That the application be approved. That the application be approved.
Major Applications Planning Sub-Committee (HS2) approved this item on Wednesday 8 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the application be approved. That the application be approved.
This application comprises a Plans and Specifications submission under Schedule 17 of the High Speed Rail (London-West Midlands) Act 2017 (The Act), in relation to permanent above ground features associated with new road works serving the Merck Sharpe and Dohme (MSD) site. The details relate purely to 2 no. parking spaces adjacent to the new security entrance, fencing and external lighting.
The application is the the latest HS2 Schedule 17 planning submission that has been deposited with the Council. These Schedule 17 planning submissions can best be likened to the submission of reserved matters, where outline planning consent has already been granted. However, the role of the Planning Authority is heavily restricted as to what can and cannot form the basis of a decision.
The approved route of Phase One of HS2 will necessitate the removal of certain buildings and associated development currently found within the MSD site. Part of the necessary works is the alternative provision of the MSD access road elsewhere, such that it does not conflict with the route of HS2 and associated main works construction. The alternative location has already been
PLHS2OFFC(ODB) 2 of 12 indicated on the approved plans and comprises of a Schedule 1 Work ('Scheduled Work') and ancillary works. The principle of the new road, its layout, materials or route do not therefore form part of this plans and speciications request for approval.
The applicant explains that the associated permanent features that form the scope of this Schedule 17 Plans and Specifications application are necessary supporting infrastructure for the new road. Lighting columns and the provision of car parking spaces will provide clear safety benefits for road users, whereas the installation of fencing and its location will seek to ensure that site security is maintained.
There is no statutory obligation to consult with neighbours. However Natural England and Historic England have been consulted and raise no objections.
No objections are raised to the proposed car parking, fencing and lighting.
APPROVAL
INFORMATIVES
3. CONSIDERATIONS
3.1Site and Locality
The site is located within a plot of land previously owned by Merck Sharpe and Dohme (MSD) pharmaceutical company, but now acquired by the Secretary of State for Transport.
At present, the route of a Statutory Bridleway (ref. U42) runs north west to south east where it connects to Breakspear Road South, following the route of the current MSD site access for part of the way. This bridleway is found to the east of the MSD site and associated security fencing.
To the east of the bridleway route is underused pasture land with scattered scrub, trees and hedgerows. Topography this land is observed to be generally flat.
At present, the site is accessed via an unnamed private road running northwest from a junction with Breakspear Road South, which joins the A40 approximately 2.6km to the south.
The site of the former Gatemead Farm and its surrounding curtilage is found on the eastern flank of the current MSD access. This property has been acquired by HS2 under the provisions of the Act.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Merck Sharpe Dohme (MSD) Site off Breakspear Road, South Harefield: 72870/APP/2019/2597Report | 296 KB | DownloadRead as text |
Follow Major Applications Planning Sub-Committee (HS2) at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 May 2021 | To sign and receive the minutes of the previous meetings dated 25 November 2020 and 14 January 2021That the minutes of the meetings dated 25 November 2020 and 14 January 2021 be approved as an accurate record. | Approved | Open |
| 4 May 2021 | River Colne, River Alignment, Moorhall Road - 76182/APP/2021/399That the application be approved. | Approved | Open |
| 4 May 2021 | Land Adjacent to Breakspear Road South - 76185/APP/2021/449That the application be approved. That the application be approved. | Approved | Open |
| 14 Jan 2021 | Election of Vice ChairmanThat Councillor Higgins be elected as Vice Chairman of the Major Applications Planning Sub Committee for the remainde... | Decided | Open |
| 25 Nov 2020 | Apologies for AbsenceAll Members were present, but due to technical difficulties, Cllr Brightman was unable to take part and left the meet... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.