1) That the Audit Committee noted the IA Progress Report for 2019/20 Quarter 3 and approval be given to the 2019/20 Quarter 4 Internal Audit Plan; 2) That the Committee noted the coverage, performance and results of Business Assurance Internal Audit activity within this quarter.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
2.1Since the last IA Progress Report to CMT and the Audit Committee dated 30th September 2019, 5 assurance reviews (including 2 follow-ups) have concluded, 2 grant claims have been certified and 3 consultancy reviews have been finalised. Progress has been steady this quarter, with three new staff members settling into the IA team, everyone is working diligently to complete the IA Plan to the required high standards. The team are therefore on track to complete this year’s programme of IA work for 2019/20, as depicted below: Chart 1 - 2019/20 IA Work Undertaken To Date
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.