Report of the Head of Planning, Transportation and Regeneration
Address SLOUGH BOROUGH COUNCIL OUTBOROUGH MIDDLESEX
Development: Out of Borough consultation for a replacement Energy from Waste (EfW) facility including a High Temperature Incinerator (HTI), provision of a new access road and new junction with the A4, visitor centre, car parking, temporary construction compound, associated works, ancillary buildings and structures. LBH Ref Nos: 39710/APP/2020/17
Drawing Nos: Letter dated 13 December 2019
Date Plans Received: 06/01/2020 Date(s) of Amendment(s): Date Application Valid: 16/01/2020 1. SUMMARY This application is being reported to the Major Applications Planning Committee so officers may issue another objection on behalf of the London Borough of Hillingdon (LBH) to Slough Borough Council (SBC) for the the construction and operation of a replacement Energy from Waste (EfW) facility and High Temperature Incinerator (HTI) on land located to the west of the Iver South Sludge De-watering Centre and south of the M4 motorway, in Slough.
Following the Court of Appeal decision issued on 28 February 2020, LBH strongly objects to the application. There is no policy justification or Very Special Circumstance case to allow this development in the Green Belt. In an email dated 27-02-2020, the Officer at Slough Borough Council noted that in the event that the Third Runway does not go ahead, the existing facility will simply demolished. The fact that the existing facility will be demolished to make way for a facility on a nearby land parcel does not make this development acceptable in planning terms.
LBH maintain strong objection to the proposal. The proposal was based solely on the delivery of Heathrow Expansion which is unlikely to go ahead and as such, there is no need for a new EfW and HTI.
The proposal is subject to an environmental impact assessment (EIA) and the current EIA is considered to be deficient as it does not properly address the above matters. LBH request that the application is refused by SBC. 2. RECOMMENDATION OBJECTION:
The London Borough of Hillingdon objects to the replacement facility which is inextricably linked to the Heathrow Expansion. This proposal represents inappropriate development in the Green Belt and the Very Special Circumstances case has fallen away in light of the Court of Appeal decision dated 27-02-2020 and this application should be refused.
Major Applications Planning Committee - 18th March 2020 PART 1 - MEMBERS, PUBLIC & PRESS 3. CONSIDERATIONS
3.1Site and Locality The application site is situated to the south of the M4 and to the west of the M25. The entire site lies within the Metropolitan Green Belt. The West London Waste Authority currently hold a contract for a portion of West London's Waste to be processed through the existing facility. LBH sent more than 31,000 tonnes to the facility in 2018/19.
3.2Proposed Scheme The site is located approximately 600m to the north west of the existing Lakeside EfW and HTI facility at Colnbrook, Slough. The site comprises 13.7ha which includes:
- 3.5 ha for EfW and HTI facilities; - 1ha for junction with the Colnbrook bypass, access road, footpath and cycleway; - 4ha for batters, grass verges, native planting and sustainable drainage features; - 2.4 ha temporary working area (required during the early stages of earthworks/construction only); and - 2.8 ha temporary construction compound that will be reinstated after use.
The proposal is not located close to any LBH residential properties. If it is solely a replacement facility then highway imapcts should be no greater than the existing facility. 3.3 Relevant Planning History
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Slough Borough Council, Out of Borough, Middlesex: 39710/APP/2020/17Report | 12 KB | DownloadRead as text |
Follow Major Applications Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Oct 2023 | To sign and receive the minutes of the previous meetingThat the item be deferred to the meeting of the Hillingdon Planning Committee on 01 November 2023. | Deferred | Open |
| 11 Oct 2023 | West Drayton Leisure Centre - 75127/APP/2023/1646That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 11 Oct 2023 | The Barn Hotel, Ruislip - 7969/APP/2023/1833That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 14 Sep 2023 | To sign and receive the minutes of the previous meetingThat the minutes of the meeting dated 26 July 2023 be agreed as an accurate record. | Agreed | Open |
| 14 Sep 2023 | Pets at Home, Elystan Business Centre, Springfield Road.That the application be approved | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.