Major Applications Planning Committee approved this item on Wednesday 24 February 2021. Below is the council's own wording, with the papers it was decided on.
That the application be approved, and 2. That delegated authority be given to the Head of Planning to agree additional wording and conditions relating to noise, acoustic wall maintenance, and bus maintenance. 1. That the application be approved, and 2. That delegated authority be given to the Head of Planning to agree additional wording and conditions relating to noise, acoustic wall maintenance, audits and bus maintenance.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report of the Head of Planning, Transportation and Regeneration
Address THE COTTAGE IN THE WALL DAWLEY ROAD HAYES
Development: Demolition of existing buildings and use of site as bus depot with new office/welfare building, bus wash and fueling facilities with access from Dawley Road. LBH Ref Nos: 3886/APP/2020/3751
Drawing Nos: DS29092001.03-B Arboricultural Impact Plan and Tree Protection Plan 76646 Rev. 01 Interim Travel Plan (Dated 9th November 2020) Supporting Planning Statement (Dated November 2020) Tree Survey Report (Dated 13th October 2020) Utility Statement (Dated November 2020) 76625-CUR-00-XX-RP-C-00002 V01 Drainage Strategy Report (Dated 30th October 2020) 076625-CUR-00-XX-RP-C-00001 V02 Flood Risk Assessment (Dated 27th October 2020) 076625-CUR-00-XX-RP-GE-001 Phase 1 Preliminary Site Assessment (Dated 11th August 2020) Preliminary Ecological Appraisal V 2.0 ENE-0972_Rev4 Air Quality Assessment (Dated 9th December 2020) 76646 Rev. 04 Transport Assessment (Dated 28th January 2021) 1051-059 Rev. C 1051-053 Rev. E 1051-058 Rev. B 1051-060 Rev. A Design, Access and Heritage Statement Rev. B 1051-051 Rev. K 1051-054 Rev. E 1051-055 Rev. F 1051-065 Rev. E 1051-066 Rev. C 20-15481-1B 90001 Rev. P02 Alternative Site Options for Abellio London (Dated October 2020) Noise Impact Assessment (Dated November 2020) 76646 Construction Logistics Plan (Dated 6th November 2020) Construction Method Statement (Dated November 2020) 1051-050 1051-049 Cover Letter (Dated 13th November 2020) Proposed Noise Mitigation Plan (Dated January 2021)
Date Plans Received: 16/11/2020 Date(s) of Amendment(s): 16/11/2020 Date Application Valid: 16/11/2020 22/01/2021
1. SUMMARY This application seeks permission for the proposed demolition of existing buildings and use of the site as bus depot with new office/welfare building, bus wash and fueling
Major Applications Planning Committee - 24th February 2021 PART 1 - MEMBERS, PUBLIC & PRESS facilities. Whilst the application is a Minor development, the Major Applications planning committee considered a recent planning application which resulted in the loss/displacement of the existing Bus depot on North Hyde Gardens. It is therefore felt expedient that this application is also presented to the Major Applications planning committee.
Although the proposed development would result in a loss of industrial floorspace, it would not result in a loss of industrial land. Development decisions should also allow for a sufficient supply of land sustainable transport functions including intermodal freight interchanges, rail and bus infrastructure. When fully occupied, the site would also employ approximately 180 full time staff. If recommended for approval, a Section 106 legal agreement would ensure that local residents would benefit from jobs and training. The principle of development is therefore supported in this respect.
The proposal would also result in the loss of two residential buildings, although these would appear to have been implemented without the benefit of prior planning permission. Notwithstanding this, the delivery of essential local transport infrastructure and the availability of sites to deliver this use is a key consideration and a case of exceptional circumstances. The existing location of the residential units immediately adjacent to industrial uses is also a poor location for residential units due to the impact on their amenity.
The application site is located within the Green Belt and would intensify the use of the site. Although the volume of built development on site would be reduced, the impact of storing 56 buses on this site would have a greater impact on the openness of the Green Belt when compared to the existing site. Accordingly, the proposed development is considered to constitute inappropriate development in the Green which requires very special circumstances.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Major Applications Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.