That the application be approved. 1) That delegated authority be granted to the Head of Planning to reword Point 2 on page 44 of the agenda pack to read ‘within six months of the plant no longer being required’; and 2) That the application be approved.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report of the Head of Planning, Transportation and Regeneration
Address HARMONDSWORTH LANDFILL SITE HARMONDSWORTH LANE HARMONDSWORTH Development: The installation of a leachate pre-treatment plant and piped connection to sewer at Harmondsworth closed landfill site LBH Ref Nos: 43155/APP/2020/4267
Date Plans Received: 18/12/2020 Date(s) of Amendment(s): Date Application Valid: 23/12/2020 1. SUMMARY Planning permission is sought for the installation of a leachate pre-treatment plant and piped connection to the Thames Water sewer at Harmondsworth closed landfill site.This application seeks to improve the existing leachate disposal system at Harmondsworth Landfill by removing dissolved methane from the leachate on site, to enable discharge of the leachate into the nearby mains sewer system under an appropriate discharge consent.
The closed landfill site currently produces leachate which needs to be treated to remove dissolved methane before it can be safely discharged into the main sewer. It is therefore a process which supports the wider landfill operation, and is not considered to be inappropriate development in the Green Belt.
The development will create fewer vehicular trips than the existing situation and there will be no changes to the access. There are therefore no highway objections to this proposal. In terms of air quality, design of the structure will prevent any odour releases, whilst it is not anticipated that the proposed plant will have any impact upon noise levels at sensitive receptors.
The plant would be a visible feature when viewed locally within the wider landfill site, but is modest in size at less than 1.5m tall, especially when compared to the existing leachate holding tank. It is considered that any harm which may arise to the openness of the Green Belt is clearly outweighed by the greater sustainability benefits.
Both Thames Water and the Environment Agency raise no objections to the proposed development, subject to a Trade Effluent Consent and a variation to the Landfill Environmental Permit under the Environmental Permitting (England and Wales) Regulations 2016.
Approval is recommended accordingly, subject to conditions. .
Central & South Planning Committee - 4th May 2021 PART 1 - MEMBERS, PUBLIC & PRESS .
2. RECOMMENDATION APPROVAL subject to the following:
1 COM3 Time Limit The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
REASON To comply with Section 91 of the Town and Country Planning Act 1990. 2 B17 Temporary Permissions The development shall be removed as soon as reasonably practicable after the plant is no longer required under the Environmental Permit for the landfill site, as regulated by the Environment Agency and land on which the development was mounted or into which the development was set is restored, as soon as reasonably practicable to its condition before the development took place, or restored to such condition as may have been agreed in writing with the Local Planning Authority.
REASON
To safeguard the visual amenity of the Green Belt, in compliance with policy EM2 of the Local Plan Part 1 (2012), policies DMEI 4 and DMEI 6 of the Hillingdon Local Plan Part 2- Development Management Policies (2020), Policy G2 of the London Plan (2021) and the NPPF. . 3 COM4 Accordance with Approved Plans The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers, Hsp-PLN-1020-01 Rev. A, Hsp-SC-0320-01a, Hsp-PLN-1020-02 and Hsp-PLN-1020-03 and shall thereafter be retained/maintained for as long as the development remains in existence.
REASON To ensure the development complies with the provisions Hillingdon Local Plan Parts 1 (November 2012) and 2 (January 2020) and the London Plan (2021). INFORMATIVES
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.