School Capital Programme Update

Noted Executive 1 paper

CABINET noted this item on Thursday 2 September 2021. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That Cabinet: 1. Note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects. 2. Delegates full authority to the appropriate Cabinet Members, in consultation with the Corporate Director of Infrastructure, Transport & Building Services, to make all necessary procurement and financial decisions, including the appointment of consultancies and the placing of building contracts for School Condition Programme. Reasons for decision Cabinet received an update on the Council’s school expansion programme and also the school condition programme, improving the fabric of local schools. Cabinet agreed to delegate authority to progress the school condition programme. The Cabinet Member for Families, Education & Wellbeing noted the success of the schools expansion programme to-date which had enabled the Council to meet its statutory requirements to provide sufficient school places. The latest pupil projections were noted and to meet this, the Cabinet Member updated Cabinet on the secondary school expansion projects, along with other expansion plans at local special educational needs schools. Alternative options considered and rejected None. Relevant Select Committee Families, Health & Wellbeing Expiry date for any scrutiny call-in / date decision can be implemented (if no call-in) Decision no.2 above can be called in by 5pm, Friday 10 September 2021. Decision no.1 above cannot be called in as it was to ‘note’. Officer(s) to action Bobby Finch / Michael Naughton Directorate Infrastructure, Transport & Building Services Classification Public The report and any background papers relating to this decision by the Cabinet are available to view on the Council's website or by visiting the Civic Centre, Uxbridge.
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to CABINET, 9 pages

SCHOOL CAPITAL PROGRAMME – UPDATE Cabinet Member(s) Councillor Susan O'Brien Councillor Jonathan Bianco

Cabinet Portfolio(s) Cabinet Member for Families, Education & Wellbeing Cabinet Member for Property and Infrastructure

Officer Contact(s) Bobby Finch, Infrastructure, Transport & Building Services

Papers with report None

HEADLINES Summary This report provides an update on the primary and secondary school expansions, the school condition works programme and other school capital works.

Putting our Putting our Residents First, Our Built Environment; Our People; Residents First Financial Management Investment in schools to adequately address the impact of the population increase within the London Borough of Hillingdon on existing school places. This project also forms part of the Hillingdon Improvement Programme.

Financial Cost The revised budget and forecast expenditure on the existing Schools expansions capital programme from 2021-2026 is £16,847k. Including expenditure of £38,546k incurred in prior years, total investment on the existing programme amounts to £55,393k.

Relevant Select Corporate, Finance & Property Committees Families, Health and Wellbeing

Relevant Ward(s) All Wards

RECOMMENDATIONS That Cabinet:

1. Note the progress made with primary and secondary school expansions, the school condition programme and other school capital projects.

2. Delegates full authority to the appropriate Cabinet Members, in consultation with the Corporate Director of Infrastructure, Transport & Building Services, to make all necessary procurement and financial decisions, including the appointment of consultancies and the placing of building contracts for School Condition Programme.

Cabinet report – 2 September 2021 Classification: Part 1 – Public Reasons for recommendation

School expansions will meet the changing need for school places in the Borough. Progressing the School Condition Programme will allow the necessary repair or replacement works to be progressed in the schools to avoid the potential impact on their daily operations due to parts of the building fabric being beyond repair, or equipment which is at the end of its life. Ensuring these works are undertaken will minimise the risk of health and safety related issues or the possibility of a school closure occurring.

Select Committee Comments

None at this stage.

SUPPORTING INFORMATION 1. PRIMARY SCHOOLS

School places forecast

The demand for primary places in Hillingdon rose for over ten years up to 2018, then stabilised and has fell slightly in 2020-21. In May 2021 census total primary rolls are 2% lower than in October 2019. This is after two years of volatility, seen across greater London as the economic impacts of Brexit and Covid have led families to leave London, and it is not yet clear if this is a new continuing trend or will stabilise or reverse. In some areas house sales have stalled and more households have no school age children.

Birth rates are now stable or falling, but there is still some migration of pupils into the Borough and new housing developments under construction. A few schools have experienced larger decreases, a few have had rising rolls and nearly half of all primary schools are full in every year group. Ideally there would be a few places in each school to enable parental choice and cope with new families moving in.

Officers are working closely with schools to meet residents demands and present options to reduce operational capacity in some instances to respond to changing demand from residents, whilst continuing to monitor the changing demand including movements across the Borough boundary.

2. SECONDARY SCHOOLS

School places forecast

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
School Capital Programme UpdateReport 9 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
IE
Councillor Ian EdwardsChair, present
JB
Councillor Jonathan BiancoVice-Chair, apologies
DM
Councillor Douglas MillsCommittee Member, present
MG
Councillor Martin GoddardCommittee Member, present
SO
Councillor Susan O'BrienCommittee Member, present
JP
Councillor Jane PalmerCommittee Member, present
EL
Councillor Eddie LaveryCommittee Member, present
JR
Councillor John RileyCommittee Member, present
DF
Councillor Duncan FlynnAttendee of the Cabinet meeting as Chief Whip - non-voting, present

On this subject at Hillingdon

Search all
  1. School Capital Programme UpdateThis decision
  2. School Capital Programme UpdateNoted
  3. School Capital Programme UpdateNoted
  4. School Capital Programme UpdateNoted
  5. School Capital Programme UpdateNoted
  6. School Capital Programme UpdateNoted

More from Hillingdon CABINET

All decisions
MeetingDecisionOutcome
19 Nov 2026 Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt... Approved Open
19 Nov 2026 Strategic Review of Library Services and Future Delivery ModelThat Cabinet: 1) Approves the launch of the Strategic Review of Library Services and Future Delivery Model, the devel... Approved Open
19 Nov 2026 Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T... Agreed Open
19 Nov 2026 Old Vinyl Factory, Hayes: Conservation Area AppraisalThat Cabinet: 1) Duly considers the public consultation responses to the draft Appraisal for The Old Vinyl Factory Co... Approved Open
19 Nov 2026 Carers Strategy UpdateThat Cabinet: 1) Note the report and agree that officers bring forward an annual progress report to Cabinet on suppor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies