Report of the Head of Planning, Transportation and Regeneration
Address AREA OF ICKENHAM GREEN, SOUTH WEST OF THE GREENWAY ICKENHAM Development: Sewer diversion works including temporary modifications to the existing
construction access adjoining Ickenham High Road; temporary working and welfare compounds; temporary access track; and a temporary bridge for a watercourse crossing.
LBH Ref Nos: 44457/APP/2021/2212
Drawing Nos: J923.01 TW HS2 NCO - Greenway Heritage Statemen Construction Logistics Plan Statement of Community Involvement Geo-Environmental Interpretive Repor Ground Investigation Factual Repor Geotechnical Report - H582-05_1 &Z HS2_Code_of_Construction_Practice Design and Optioneering Repori Planning Statement. Stage 2 Tree Report (Mains Works). J923.01-DN-LON-004-TN-Z-0001 FRA Technical Note 11 - J923_01-AJ-TS001304-101-DR-C-0002 - Utilities 12 - H582_05-HI-TS001304-101-DR-C-0147_P02 - Brid¢ Greenway Sewer Diversion - Cover Letter. 02 - J923_01-AJ-TS001304-101-DR-C-0036 - Site Plar 03 - J923_01-AJ-TS001304-101-DR-C-0037 - Access Ex 04 - J923_01-AJ-TS001304-101-DR-C-0030 - Site Plar 05 - J923_01-AJ-TS001304-101-DR-C-0031 - Site Plar 06 - J923_01-AJ-TS001304-101-DR-C-0032 - Site Plar 07 - J923_01-AJ-TS001304-101-DR-C-0033 - Site Plar 08 - J923_01-AJ-TS001304-101-DR-C-0034 - Temporary 01 - J923_01-AJ-TS001304-101-DR-P-0010 - Site Loc 16 - J923_01-AJ-TS001304-101-DR-C-0051 - Habitat F 17 - Landscape Plans - J923_01-AJ-TS001304-101-DR: Jacobs_MODEL_AUDIT_River_Pinr Ecology Report May 2021
Date Plans Received: 01/06/2021 Date(s) of Amendment(s): Date Application Valid: 03/06/2021 1. SUMMARY
This application seeks planning permission for works in connection with the construction of anew section of below ground sewer, of approximately 580 metres in length, to the west of the existing sewer. The new sewer will be tunnelled under the existing railway line, The Greenway and residential dwellings. To enable the proposed works, a reception shaft, a temporary working compound and temporary welfare compound are to be located to the south of the railway line and The Greenway, within Registered Common Land, including an allotment area, Council-owned woodland and open space areas to the north- west of the Soldiers Return Public House. It is proposed to access the southern site
Major Applications Planning Committee - 14th October 2021 PART 1 - MEMBERS, PUBLIC & PRESS compound via an existing access off High Road, Ickenham, to the west of the Soldiers Return Public House, which will need widening and improving.
A temporary bridge will be required over the Ickenham Stream, as the existing bridge is not suitable for construction traffic.
The diverted sewer is to be constructed entirely below ground at a depth of approximately 10 metres below ground level. The temporary site compounds, working areas and access tracks are to be removed on completion of construction and any affected land, including the allotments, is to be reinstated to its original condition.
Although the sewer diversion forms part of the enabling works for the HS2 railway, the diversion works fall within Thames Water's (TW's) remit. Thames Water has a duty to provide, improve and extend a system of public sewers and to make provision for the treatment of sewage under the Water Industry Act 1991. This sewer diversion work is essential to ensure that Thames Water continues to provide wastewater services to residents in the surrounding area in its capacity as a statutory undertaker.
The temporary work on the southern side of the railway line requires temporary planning consent, as it is not permitted under Part 2 Class B of Schedule 2 of the GPDO. The application site area therefore includes the main working compound area, the access track and bridge, and the welfare compound. As such, the application therefore covers the full site, including the allotments and not just the modified access.
70 responses have been received from public consultation, objecting to the proposals.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Area of Ickenham Green, South West of The Greenway: 44457/APP/2021/2212Report | 38 pages | DownloadRead as text |
Follow Major Applications Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Oct 2023 | To sign and receive the minutes of the previous meetingThat the item be deferred to the meeting of the Hillingdon Planning Committee on 01 November 2023. | Deferred | Open |
| 11 Oct 2023 | West Drayton Leisure Centre - 75127/APP/2023/1646That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 11 Oct 2023 | The Barn Hotel, Ruislip - 7969/APP/2023/1833That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 14 Sep 2023 | To sign and receive the minutes of the previous meetingThat the minutes of the meeting dated 26 July 2023 be agreed as an accurate record. | Agreed | Open |
| 14 Sep 2023 | Pets at Home, Elystan Business Centre, Springfield Road.That the application be approved | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.