London Borough of Hillingdon
CABINET, Thursday 17 February 2022 at 7.00pm

Monthly Council Budget Monitoring Report: Month 9

Noted Executive 1 paper

CABINET noted this item on Thursday 17 February 2022. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That the Cabinet: 1. Note the budget monitoring position and treasury management update as at December 2021 (Month 9) as outlined in Part A of this report. 2. Approve the financial recommendations set out in Part B below: a) Ratify an Emergency Decision by the Leader of the Council taken on 4 January 2022 to grant a 6-month extension of the temporary licence to the NHS North West London Clinical Commissioning Group to use the Winston Churchill Hall in Ruislip as a COVID-19 Vaccination Centre. b) Approve acceptance of gift funding in relation to a Planning Performance Agreement in accordance with the provisions of Section 93 of the Local Government Act 2003 for; I. St Andrew’s TCE - £60,000 II. Southall Gasworks - £26,000 III. 14-18 Pield Heath Road - £17,500 c) Approve acceptance of £20k grant funding from the Department for Levelling Up, Housing and Communities for set-up costs associated with the implementation of temporary pavement license provisions and the subsequent running costs not covered by fees. d) Approves virements of £190k and £268k from the general capital contingency budget to the Corporate Technology and Innovation and Environmental and Recreational Initiatives capital budgets respectively, for the replacement of public PCs for libraries and adult education centres (£190k) and flood mitigation measures at Elephant and Court Park (£268k). e) Accept a grant award of £52k from the England and Wales Cricket Board for the installation of cricket facilities at Grassy Meadow and Cowley recreation ground. f) Approve the increase of grant allocation to Shop Mobility from the Voluntary Sector Grants budget by £10k from £5k approved at Cabinet (Dec 2021 Item 7) to £15k for 2022/23. g) Approve the receipt of additional New Burdens Grant funding of £127,300 from the Department for Business, Energy & Industrial Strategy to the Revenues Service in respect of work completed on Restart and Additional Restrictions Grants. Reasons for decision Cabinet was informed of the forecast revenue, capital and treasury position for the current year 2021/22 to ensure the Council achieved its budgetary and service objectives. The Cabinet Member for Finance noted that the overall financial position of the Council was one of strength and stability, despite exceptional pressures arising from Covid-19. On the Dedicated Schools Grant, the Cabinet Member updated Cabinet on the discussions with the Department for Education. Other financial recommendations approved by the Cabinet included the acceptance of grants, ratification of an emergency decision to extend the lease for the vaccination site at Winston Churchill Hall and budget virements . The Leader of the Council thanked the Cabinet Member and the Council’s Officer Team in managing the budget well this year. Alternative options considered and rejected None. Relevant Select Committee Corporate, Finance and Property Expiry date for any scrutiny call-in / date decision can be implemented (if no call-in) Decisions 2 b) to g) can be called in by 5pm, Friday 25 February 2022 Officer(s) to action Paul Whaymand Directorate Finance Classification Public The report and any background papers relating to this decision by the Cabinet are available to view on the Council's website or by visiting the Civic Centre, Uxbridge. This item was also circulated less than 5 clear working days before the Cabinet meeting and it was considered by the Chairman to be urgent, and therefore, considered.
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to CABINET

Reasons for recommendation

1. The reason for Recommendation 1 is to ensure that the Council achieves its budgetary objectives, providing Cabinet with the update on performance at Month 9 against budgets approved by Council on 25 February 2021 contained within Part A of this report. An update on the Council's Treasury Management activities is included within this section of the report.

2. Recommendation 2 seeks approval for the range of financial recommendations set out within Part B of this report, which may include approval of above establishment agency appointments, acceptance of grant funding, revisions to fees & charges and ratification of decisions taken under special urgency provisions.

Alternative options considered / risk management

3. There are no other options proposed for consideration.

Select Committee comments

4. None at this stage.

Cabinet -17 February 2022 (Part 1 Public) PART A: MONTHLY BUDGET MONITORING SUMMARY GENERAL FUND REVENUE

5. General Fund pressures totalling £19,008k are projected in relation to the impacts of the COVID-19 pandemic and the Council’s response in 2021/22. With total forecast pressures of £52,383k since the pandemic began in early March 2020, including the forecast pressure for the current financial year alongside £1,883k in 2019/20 and £31,492k in 2020/21. There has been a £298k increase in projected COVID-19 pressures from the position reported at Month 7.

6. Prior year COVID-19 pressures were fully funded from external funding, with a further £20,327k of such grants confirmed for the 2021/22 financial year available to supplement £10,126k of the Council’s own reserves set aside for management of the pandemic. This gives scope to fund reported pressures of £19,008k for the 2021/22 financial year, while leaving headroom of £11,313k to meet emerging or ongoing pressures.

7. Beyond the ongoing impact of the pandemic, an underspend of £478k is projected across General Fund budgets at Month 9, with this position being driven by underspends against Capital Financing of £291k and Development and Risk Contingency of £767k, primarily related to a reduced call on the waste and homelessness contingencies, offset by a pressure reported against Service Operating Budgets of £580k.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Monthly Council Budget Monitoring Report: Month 9Report 290 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
IE
Councillor Ian EdwardsChair, present
JB
Councillor Jonathan BiancoVice-Chair, present
DM
Councillor Douglas MillsCommittee Member, present
MG
Councillor Martin GoddardCommittee Member, present
SO
Councillor Susan O'BrienCommittee Member, present
JP
Councillor Jane PalmerCommittee Member, present
EL
Councillor Eddie LaveryCommittee Member, present
JR
Councillor John RileyCommittee Member, apologies
DF
Councillor Duncan FlynnAttendee of the Cabinet meeting as Chief Whip - non-voting, present
KP
Councillor Kerri PrinceCompany Director, in attendance

On this subject at Hillingdon

Search all
  1. Monthly Council Budget Monitoring Report: Month 9This decision
  2. Monthly Budget Monitoring Report: Month 4Noted
  3. Monthly Council Budget Monitoring Report: M2Noted
  4. Monthly Council Budget Monitoring Report: Month 10Agreed
  5. Monthly Council Budget Monitoring Report: Month 9Approved
  6. Monthly Council Budget Monitoring Report: Month 7Noted

More from Hillingdon CABINET

All decisions
MeetingDecisionOutcome
19 Nov 2026 Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt... Approved Open
19 Nov 2026 Strategic Review of Library Services and Future Delivery ModelThat Cabinet: 1) Approves the launch of the Strategic Review of Library Services and Future Delivery Model, the devel... Approved Open
19 Nov 2026 Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T... Agreed Open
19 Nov 2026 Old Vinyl Factory, Hayes: Conservation Area AppraisalThat Cabinet: 1) Duly considers the public consultation responses to the draft Appraisal for The Old Vinyl Factory Co... Approved Open
19 Nov 2026 Carers Strategy UpdateThat Cabinet: 1) Note the report and agree that officers bring forward an annual progress report to Cabinet on suppor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies