Resolved
That the Audit Committee noted the Risk Management Report and progress to improve the risk management arrangements
Audit Committee noted this item on Wednesday 22 November 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Audit Committee noted the Risk Management Report and progress to improve the risk management arrangements
That the Audit Committee:
1. Note the Risk Management Report and progress to improve the risk management arrangements.
SUPPORTING INFORMATION
None.
None.
Audit Committee – 22 November 2023 Part I – Public RISK MANAGEMENT REPORT Q2 2022/23 30 September 2023 HILLINGDON COUNCIL RISK MANAGEMENT REPORT
CONTENTS
The key contacts in Page connection with this document are: 1. INTRODUCTION 3
Claire Baker 2. DIRECTORATE RISK REGISTER UPDATE 3 Head of Internal Audit [email protected] 3. CORPORATE RISK REGISTER UPDATE 5
4. FORWARD PLAN 5
APPENDIX A: SUMMARY OF CORPORATE RISK REGISTER 6
APPENDIX B: RISK SCORING METHODOLOGY 7
Q2 2023/24 2 HILLINGDON COUNCIL RISK MANAGEMENT REPORT
1. INTRODUCTION 1.1 Hillingdon Council has a statutory responsibility to ensure arrangements are in place for managing risks. Risk management is about managing opportunities and threats to objectives to help create an environment of “no surprises”. It is a crucial element of good management and a key part of corporate governance. Although risks can never be entirely eliminated, proportionate and targeted action can be taken to reduce risks to an acceptable level. 1.2 Managing risk should be viewed as a mainstream activity and something that is an integral part of everyday management. Risk Management involves the early identification of risks, assessing their potential consequences, and determining the most effective way to reduce the likelihood and/or impact of the risk. The Council’s Risk Management Policy provides a framework to ensure there are clear roles, responsibilities and methodologies for identifying, recording and managing risks. 1.3 This report summarises the Council’s Risk Register as at the end of quarter two and outlines the work undertaken during the quarter to improve risk management arrangements. It is intended to support the Audit Committee to monitor and review (but not direct) the authority’s risk management arrangements, as per the Committee’s terms of reference.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
23-24 Q2 Corporate Risk RegisterReport | 8 pages | DownloadRead as text |
Follow Audit Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Feb 2026 | Minutes of the Meeting held on 18 November 2025That the minutes of the previous meeting be agreed as a correct record | Agreed | Open |
| 10 Feb 2026 | Counter Fraud Progress ReportThat the Audit Committee noted the for 2025/26 Quarter 3 | Noted | Open |
| 10 Feb 2026 | Counter Fraud Operational WorkplanThat the Audit Committee noted the Counter Fraud Annual Operational Plan for 2026/27 | Noted | Open |
| 10 Feb 2026 | Work ProgrammeThat the Audit Committee noted the dates for Audit Committee meetings | Noted | Open |
| 18 Nov 2025 | Minutes of the Meeting held on 28 August 2025That the minutes of the previous meeting be agreed as a correct record | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.