Hayes Bridge Retail Park and Heathrow Interchange, Uxbridge Road - 78343/APP/2025/719

Approved Planning 1 paper

Hillingdon Planning Committee approved this item on Thursday 2 October 2025. Below is the council's own wording, with the papers it was decided on.

Item93

Resolved

That the application be approved subject to a section 106 legal agreement and the conditions set out if the officer’s report; and 2. That the drafting of an additional informative to ensure local Wi-Fi connectivity was not compromised be delegated to the Area Planning Service Manager, in consultation with the Chair. 1. That the application be approved subject to a section 106 legal agreement and the conditions set out if the officer’s report; and 2. That the drafting of an additional informative to ensure local Wi-Fi connectivity was not compromised be delegated to the Area Planning Service Manager, in consultation with the Chair.
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to Hillingdon Planning Committee, 151 pages

Report of the Head of Development Management and Building Control Committee Report

Case Officer: Michael Briginshaw 78343/APP/2025/719

Date Application 28.03.2025 Statutory / Agreed 09.10.2025 Valid: Determination Deadline: Application Full Ward: Wood End Type:

Applicant: Colt Data Centre Services

Site Address: Hayes Bridge Retail Park and Heathrow Interchange, Uxbridge Road

Proposal This hybrid planning application seeks permission (Summarised): for a four-phased redevelopment to deliver a data centre campus comprising: Full planning permission for a data centre building and associated infrastructure/works (Phase 1); Outline planning permission for an Innovation Hub and infrastructure/works (Phase 2); Outline planning permission for a data centre building and associated infrastructure/works (Phase 3); and Outline planning permission for a data centre building and associated infrastructure/works (Phase 4). All matters are reserved for the Outline phases of development.

Summary of GRANT planning permission subject to section Recommendation: 106 legal agreement and conditions

Reason Reported Required under Part 1 of the Planning Scheme of to Committee: Delegation (Major application recommended for approval)

Hillingdon Planning Committee – 2nd October 2025

PART 1 – Members, Public & Press Summary of Recommendation:

GRANT planning permission subject to the completion of a satisfactory section 106 legal agreement to secure the heads of terms set out below, and subject to the conditions as set out in Appendix 1. Mayor of London Stage 2 Referral & S106 Legal Agreement Heads of Terms

It is recommended that delegated powers be given to the Director of Planning and Sustainable Growth to grant planning permission subject to the following:

A) That the application be referred to the Mayor under Article 5 of the Town and Country Planning (Mayor of London) Order 2008.

B) That the Council enter into a legal agreement with the applicant under Section 106 of the Town and Country Planning Act 1990 (as amended) or any other legislation to secure the following:

i. Innovation Hub: To secure the Innovation Hub as genuinely affordable workspace (including peppercorn rents) with publicly accessible ancillary floorspace for sale of food and drink. ii. Public Art: To secure high quality public art as part of the Innovation Hub development, to be delivered in conjunction with Phase 2. iii. Air Quality Contribution: Financial contributions shall be paid to the Council to address air quality impacts arising from the development. £1,026,166 shall be paid for Phase 1 (LON6). The obligation shall secure the payment of contributions for Phases 2, 3 and 4 but these shall be calculated at the relevant reserved matters application stage. The contributions could rise to more depending on emission monitoring results in year 2 of operation of each phase of development and subsequent years, in accordance with the air quality conditions. iv. Architect Retention: Retention of the developer’s architectural design team to the completion of the project. v. Carbon Offset Contribution: A financial contribution of £1,830,527 for Phase 1 (LON6). The obligation shall secure the payment of contributions for Phases 2, 3 and 4 but these shall be calculated at the relevant reserved matters application stage. vi. Travel Plan: A full Travel Plan to be approved in writing by the Local Planning Authority (for each phase). vii. Healthy Streets/Active Travel Zone Contribution: A financial contribution of £209,660 payable to cover all four phases. viii. Section 278 Agreement: A Section 278 agreement to implement the site highways works on Uxbridge Road consisting of the remodelling of the junction bellmouth to include a straight across toucan crossing for cyclists and pedestrians at the site entrance. Hillingdon Planning Committee – 2nd October 2025

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hayes Bridge Retail Park and Heathrow Interchange, Uxbridge Road: 78343/APP/2025/719Report 151 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
HH
Councillor Henry HigginsChair, present
AB
Councillor Adam BennettVice-Chair, present
KB
Councillor Keith BurrowsCommittee Member, apologies, sent representative
RC
Councillor Roy ChamdalCommittee Member, present
EG
Councillor Elizabeth GarelickCommittee Member, present
JS
Councillor Jagjit SinghCommittee Member, present
RS
Councillor Raju SansarpuriCommittee Member, apologies
DD
Councillor Darran DaviesCommittee Member, present as substitute
SA
Councillor Shehryar Ahmad-WallanaCompany Director, in attendance
CB
Chris BradyOfficer, in attendance
MB
Michael BriginshawOfficer, in attendance
KC
Katie CrosbieOfficer, in attendance

All 17 on the meeting page

On this subject at Hillingdon

Search all
  1. Hayes Bridge Retail Park and Heathrow Interchange, Uxbridge Road - 78343/APP/2025/719This decision
  2. Hayes Bridge Retail Park - 78343/APP/2025/2925Approved
  3. Major App: Hayes Bridge Retail Park, Uxbridge Road - 1911/APP/2022/1853Approved
  4. Hyatt Place, 27 Uxbridge Road, HayesDeferred
  5. Unit B, Hayes 180 1-3, Uxbridge Road, Hayes - 75918/APP/2020/3171Approved
  6. Out of Borough consultation, Unit 5 Bulls Bridge Industrial Estate Hayes - 39705/APP/2020/1560Decided

More from Hillingdon Hillingdon Planning Committee

All decisions
MeetingDecisionOutcome
17 Nov 2026 Apologies for absenceThere were no apologies for absence. Decided Open
17 Nov 2026 Declarations of Interest in matters coming before this meetingCouncillor John Garner declared a non-pecuniary interest in agenda item 6 as he had prior involvement in the applicat... Decided Open
17 Nov 2026 To receive the minutes of the meetings on 6 October 2026 and 14 October 2026That the minutes from the meetings on 6 October 2026 and 14 October 2026 be confirmed as an accurate record. That the... Decided Open
17 Nov 2026 Matters that have been notified in advance or urgentNone. Decided Open
17 Nov 2026 To confirm that the items of business marked Part I will be considered in Public and the items marked Part II will be considered in PrivateIt was confirmed that all items would be heard in Part I. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies