Resolved
That the update on the Hayes Estate Regeneration Project be noted.
AI summaryLondon Borough of Hillingdon's Corporate Resources & Infrastructure Select Committee noted the Hayes Estate regeneration update [D]. Hayes Town Centre Phase 1 is nearing completion, further planning applications are expected, and the existing £160,982,000 programme budget is expected to be exceeded [P12][P14][P40][P41].
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That the update on the Hayes Estate Regeneration Project be noted.
Hayes Town Centre Estate, sometimes known as Austin Road Estate, consists of 260 homes including 79 leasehold properties built in the 1970s consisting of medium rise flats and maisonettes with a high-rise point block of 15 storeys, made up of a mixture of 1,2 and 3 bedroom homes.
The Avondale Drive Estate, also in Hayes, contains 144 homes, of which 28 are leasehold properties. The Estate consists of three ‘system built’ 12 storey point blocks constructed in the late 1960s and all flats have two bedrooms.
In response to concerns raised by residents about building condition and anti-social behaviour on these estates, the Council has been exploring ways to improve the standard of residential provision for current residents.
It has also taken into account the opportunity to deliver additional housing supply and a high- quality public realm, which is in line with its planning policies for Hayes town centre, the Hayes Housing Zone and the Borough generally.
Following options appraisal, in October 2020 Cabinet agreed that officers should undertake further design work on a redevelopment option for both estates, in consultation with residents, with final proposals on the re-housing offer and indicative design to be put to residents in a GLA
Classification: Public Corporate Resources and Infrastructure Select Committee – 19 November 2025 compliant resident ballot. In May 2021 the results of the two ballots were both positive, 79% in favour at Hayes Town Centre and 94% in favour at Avondale Drive.
To ensure that the redevelopment could be delivered, in June 2021 the Cabinet authorised officers to undertake a developer procurement exercise for the two estates, and a strategic pipeline of projects. They also authorised the submission of two hybrid planning applications for the first two estates identified (Hayes Town Centre and Avondale Drive), alongside the acquisition strategy and possession strategy to facilitate an early start on site once a developer partner had been procured.
On 24 March 2022 Cabinet approved Higgins PLC as the preferred bidder and granted delegated authority to approve the final contract terms to the Leader of the Council and Cabinet Members for Property and Infrastructure, Environment, Housing & Regeneration and Finance, in consultation with the Corporate Director of Place.
On 11 July 2022 the Leader of the Council and Cabinet Members approved the final award of contract to Higgins Partnerships 1961 PLC as the developer partner for Hayes Town Centre and Avondale Drive Estates to facilitate their redevelopment and for the strategic pipeline of potential developments described in the procurement documents.
In September 2022, the Council obtained planning consent for the scheme that residents were consulted on and the Council entered into contract with Higgins Partnerships to build new homes for the residents of the Estates. The Planning Consent was for 740 new homes across both sites.
Following the decision by the Council to proceed with Higgins on Hayes Town Centre (HTC) phases 1 and Avondale Drive 1A, a Deed of Variation (DoV) to the Development Agreement has been progressed with Higgins and it is the basis for the current construction works.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Hayes Estate Regeneration Progress ReportReport | 5 pages | DownloadRead as text |
Follow Corporate Resources & Infrastructure Select Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jul 2026 | Minutes of the previous meetingThat the minutes of the meeting held on 17 June 2026 be agreed. | Agreed | Open |
| 29 Jul 2026 | West London Waste PlanThat the Corporate Resources & Infrastructure Select Committee noted the contents of the report and appendices | Noted | Open |
| 29 Jul 2026 | Growth AgendaThat the Committee noted the Growth Plan | Noted | Open |
| 29 Jul 2026 | Policy Review Discussion & GuidanceThat the Committee: Noted the guidance on undertaking policy reviews in Appendix 1; Sought to make use of the scoreca... | Noted | Open |
| 29 Jul 2026 | Forward PlanThat the Committee considered the Cabinet | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.