Occupational Therapy Service Update

Deferred Committee 1 paper

AI summaryLondon Borough of Hillingdon’s Health and Wellbeing Board postponed the occupational therapy service update to the March 2026 meeting. [D] The recovery plan will remain under review. [P11]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredThe occupational therapy service update was postponed. [D]
MoneyNot stated
What happens nextMarch 2026 meeting [D]The item returns while the recovery plan remains under review. [D][P11]
Who it affectsChildren and young people affected [P4]Some missed statutory OT contacts during 2024 / 25. [P4][P9]

What was decided

The Health and Wellbeing Board postponed the occupational therapy service update to the March 2026 meeting. [D]

Why

CNWL and the council were working closely to agree a plan to recover from the occupational therapy backlog. [P1] Report P1

A national shortage of occupational therapists, maternity leave, recruitment challenges and other factors reduced workforce and service capacity. [P2][P3] Report P2, P3

Some children and young people did not receive their statutory number of contacts during the last academic year. [P4] Report P4

What happens next

Assess the therapy needs of affected children and develop plans with input from children, families, therapists and schools. [P7] Report P7

CNWL was aiming to commission additional capacity from the independent therapy market before the end of December. [P8] Report P8

Continue discussions, keep the recovery plan under review and update plans as necessary. Appropriate OT provision for children affected during the 2024 / 25 academic year was expected by the end of the Spring term at the end of March. [P9][P11] Report P9, P11

Options considered

  • Chosen: Postpone consideration until March 2026
  • Chosen: Commission additional capacity from the independent therapy market. To provide appropriate therapy for all children and keep pace with increased assessment demand. Report P8
  • Chosen: Use separate commissioning arrangements for children with no contacts. To recover contacts for children who received none. Report P6
  • Chosen: Develop individual assessment and therapy plans. To ensure individual needs are met appropriately. Report P7

Implications

  • Legal: Some children and young people missed their statutory number of contacts, and corrective work was under way. [P4] Report P4
  • Staffing: Recruitment and retention challenges, maternity leave and other factors reduced the OT workforce and capacity for a prolonged period. [P2][P3] Report P2, P3
  • Other: CNWL planned additional independent therapy capacity to provide appropriate therapy and keep pace with assessment demand. [P8] Report P8
  • Other: Some planned recovery contacts had already been delivered through separate commissioning arrangements with families. [P6] Report P6
  • Risk: All scheduled OT statutory contacts were forecast to be delivered by the end of the Autumn term at the end of December because of additional capacity. [P10] Report P10
  • Risk: Appropriate OT provision for children affected during the 2024 / 25 academic year was expected by the end of the Spring term at the end of March. [P9] Report P9
  • Other: The recovery plan aimed to deliver appropriate therapeutic input as set out in children’s and young people’s EHCPs. [P11] Report P11
  • Risk: The recovery plan remained under review and plans would be updated as necessary. [P11] Report P11

Who and where

  • Children and young people who missed statutory contacts Report P4
  • Children with no contacts covered by separate commissioning Report P6
  • Children whose therapy needs are being assessed Report P7
  • Children and young people needing appropriate OT under their EHCPs Report P8, P11
  • Families supporting recovery arrangements Report P6, P7
  • Therapists and schools contributing to assessments and plans Report P7
  • The OT workforce facing recruitment and retention challenges Report P2, P3

Timeline

  • during the 2024 / 25 academic year: Some children and young people did not receive their statutory number of contacts. [P4][P9] Report P4, P9
  • 2 December 2025: The Health and Wellbeing Board postponed the occupational therapy service update. [P12][D] Report P12
  • before the end of December: CNWL was aiming to have additional independent therapy capacity commissioned. [P8] Report P8
  • end of the Autumn term at the end of December: All scheduled OT statutory contacts were forecast to be delivered as planned. [P10] Report P10
  • end of the Spring term at the end of March: Appropriate OT provision was expected for children affected during the 2024 / 25 academic year. [P9] Report P9
  • March 2026 meeting: The postponed item will be considered. [D]

Plain English for the jargon

  • OT: Occupational therapy. [P2][P8]
  • EHCP: The plan outlining required therapeutic input. [P8][P11]
  • CNWL: The organisation working with the council and commissioning OT services. [P1][P8]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item66

Resolved

That the item be deferred to the March 2026 meeting.
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to Health and Wellbeing Board, 3 pages

Background

6. This issue was highlighted to CNWL during the last academic year, and CNWL have been working closely with the Head of Commissioning in the Council to agree a plan to recover from the backlog.

7. There is a national shortage of OTs due to a range of factors which are impacting service delivery across many regions, and CNWL has not been immune to the recruitment and retention challenges in the country. This has impacted the current workforce, and in turn, the capacity to deliver all statutory contacts.

8. These pressures have been evident through a reduced workforce due to maternity leave, recruitment challenges and other factors, and has reduced the OT capacity for a prolonged period of time, despite CNWL efforts to recruit to the appropriate staffing levels.

9. As a result, there are a number of children and young people who have not received their statutory number of contacts during the last academic year as outlined above, and work is underway to correct this as set out below.

Recovery Plan

10. Where a child or young person has been identified for not receiving any contacts, plans have been put in place to recover these through separate commissioning arrangements in conjunction with families, and some of these have been delivered already.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Occupational Therapy Service UpdateReport 3 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 19 attended
JP
Councillor Jane Palmer (Co-Chair)Co-Chair, present
KS
Keith SpencerCo-Chair, present
SO
Councillor Susan O'BrienVice-Chair, apologies
SB
Sean BidewellCommittee Member, present
AC
Amanda Carey-McDermottCommittee Member, present
CE
Claire EvesCommittee Member, present as substitute
PI
Professor Ian GoodmanCommittee Member, apologies
RG
Dr Richard Grocott MasonCommittee Member, present
JK
Julie KellyCommittee Member, apologies
AM
Dr Alan McGlennanCommittee Member, present as substitute
SN
Samreen NawshinCommittee Member, apologies
VO
Vanessa OdlinCommittee Member, apologies, sent representative

All 19 on the meeting page

On this subject at Hillingdon

Search all
  1. Occupational Therapy Service UpdateThis decision
  2. Occupational Therapy Service UpdateNoted

More from Hillingdon Health and Wellbeing Board

All decisions
MeetingDecisionOutcome
17 Jun 2026 To approve the minutes of the meeting on 18 March 2026That the minutes of the meeting held on 18 March 2026 be agreed as a correct record. Agreed Open
17 Jun 2026 2026/27 Better Care Fund UpdateThat: the 2026/27 Better Care Fund Plan as described in the report be approved, including the proposed financial arra... Approved Open
17 Jun 2026 Occupational Therapy Service UpdateThat the content of the report be noted. Noted Open
17 Jun 2026 Board Planner & Future Agenda ItemsThat the Board Planner be agreed subject to the addition of the following reports: 9 September 2026 - SEND JSNA; and ... Agreed Open
18 Mar 2026 To approve the minutes of the meeting on 2 December 2025That the minutes of the meeting held on 2 December 2025 be agreed as a correct record. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies