AI summaryCabinet approved the draft 2026/27 budget for consultation lasting 6 weeks, with a £59 million gap requiring Exceptional Financial Support [D]. The final budget is scheduled for Full Council on 26 February 2026 [D].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDraft General Fund and housing budgets enter consultation [D]
Money£59 million budget gap [D]A £60m EFS request is pending [P7.3]
What happens nextConsultation starts 24th December [D]Cabinet receives results in February 2026 [D]
Who it affectsResidents and businesses [P13]Council Tax, rents, service charges and fees are covered [D]

What was decided

Cabinet approved the draft General Fund and Housing Revenue Account budgets, including growth, savings, fees, charges and capital programme proposals for 2026/27 and beyond. Cabinet noted the circumstances, assumptions and risks behind the medium term strategy. These proposals form the basis for consultation rather than final approval. Report P1, P2, P4, P11

Cabinet authorised consultation from 24th December for 6 weeks. Results will go to Cabinet in February 2026. The final budget will go to Cabinet on 19 February 2026 and then to Full Council on 26 February 2026. Report P4

Cabinet approved the new leisure centre fees and charges operated by GLL, with effect December 2025. It authorised officers to implement suitable efficiency and invest to save proposals early in 2025/26 where they do not affect the public and have no equality impacts. It also authorised the Corporate Director of Finance, in consultation with the Cabinet Member for Finance & Transformation, to respond to the Provisional LGFS and the Mayor of London’s budget consultation. Report P64

Why

The council has a statutory duty to set a balanced budget each year. Available reserves cannot fund the gap, so it needs Exceptional Financial Support from central government. Report P1, 1.2, 6.4, 7.2

Service demand and inflation are increasing costs, especially in adult and children’s social care and temporary accommodation. The draft includes £69.5m of service growth and £22.3m of service savings for 2026/27. Report 1.3, 1.4, 6.15, 6.16

Government funding will phase in over three years, leaving the council underfunded until 2028/29. Business rates revaluation also creates cashflow and retained income risk if appeals succeed. Report 1.6, 1.7, 7.5

What happens next

Consultation with the business community and residents starts on 24th December for 6 weeks. Select Committees will review the budget in January 2026, and their feedback will accompany the final budget report. Report P4, P13, P15

The final General Fund revenue budget, capital strategy and programme, HRA budget, business plan and Treasury Management Strategy Statement will go to Cabinet on 19 February 2026. Cabinet will recommend approval to Full Council on 26 February 2026. These decisions are not subject to call in and take immediate effect.

Officers will continue seeking Exceptional Financial Support from MHCLG and will update the 2026/27 medium term financial strategy until the Final Local Government Finance Settlement is confirmed. They will assess appeal risk and maintain an appropriate business rates provision. The business rates retention budget will be submitted to MHCLG before the end of January 2026. Report 4.10, 7.5

The money

  • £59 million Current 2026/27 budget gap, largely due to transitional funding arrangements
  • £60m Exceptional Financial Support request backed by borrowing for 2026/27
  • £22.3m Proposed service savings for 2026/27 Report P8, 1.3
  • £69.5m Proposed service growth for 2026/27 Report 1.3, 6.15
  • £75 million 2026/27 capital programme after a review to reduce borrowing
  • £133 million 2026/27 Housing Revenue Account programme for major social housing works
  • £44 million Net cost of remaining underfunded until 2028/29
  • £1.6m 2026/27 cost of Exceptional Financial Support borrowing, rising to £11.5m in 2028/29

Options considered

  • Chosen: Use the draft budget as the consultation basis. This allows Select Committees, businesses and residents to comment before final approval. Report P4, P13
  • Chosen: Seek Exceptional Financial Support to balance the budget. Reserves cannot fund the gap and the council must set a balanced budget. Report P1, 6.4, 7.2
  • Rejected: Reduce the £10m risk contingency. This would weaken budget robustness and increase the likelihood of overspends. Report P8
  • Rejected: Add savings, generate more income or reduce growth assumptions. New proposals need rigorous review for deliverability and unintended consequences. Report P8
  • Rejected: Reprioritise or remove capital schemes. A prioritisation review has already been undertaken, so further reductions would involve difficult decisions. Report P9
  • Rejected: Increase fees further or remove discounts. Steep or quick changes could reduce demand. Report P10
  • Rejected: Raise Council Tax above 4.99%. It would require a resident referendum or special dispensation from MHCLG, and neither is currently planned. Report P7

Implications

  • Legal: The council must set a balanced budget under the Local Government Finance Act 1992. Without Exceptional Financial Support, the gap cannot be covered from reserves. Report P1, 1.2, 6.4, 7.2
  • Financial: The draft includes £22.3m of service savings for 2026/27 and an estimated £4.8m carried forward from 2025/26. Delivering them on time and to scale remains key. Report P8, 1.10
  • Financial: The proposed Council Tax rise is 4.99%, including the Social Care Precept, and is modelled to generate circa £7.7m per year in additional revenue. Any rise above 4.99% would need a resident referendum or special dispensation from MHCLG. Fees and charges are assumed to rise by 10%, with resident discounts retained. Report 1.8, P7
  • Financial: The five year General Fund capital programme has gross spend of £228.792m, with £122.618m funded through borrowing. The HRA programme for 2026/27 is £133 million for major social housing works. Report 1.9
  • Risk: The draft business rate revaluation shows an average rateable value increase of 102% for Hillingdon. Heathrow Airport’s proposed valuation rises from £210m to £951m. A successful appeal could require a refund running into the hundreds of millions of pounds, so the council must maintain a substantial appeals provision. Report 1.7, 4.7, 4.8
  • Financial: The funding settlement phases in over three years, leaving more than £40m of underfunding over the next two years. The target is a balanced position by 2028/29. Report 1.6, 1.17, 7.5
  • Equalities: Proposals that affect the public or may have equality impacts must wait for consultation feedback, an equality impact assessment and Full Council approval. Early savings may proceed only where they do not affect the public and have no equality impacts.
  • Staffing: Service modelling and new delivery models include changes in adult social care, children’s homes and temporary accommodation. Report 6.9, 6.10

Who and where

  • Council Taxpayers, with a proposed 4.99% increase including the Social Care Precept Report P7
  • Council service users, with fees and charges assumed to rise by 10% and resident discounts retained
  • Social housing residents, with housing rents, service charges and major works proposals Report P2
  • Adult social care service users, with demand pressure and delivery model changes Report 1.4, 6.16
  • Children using council services, with social care growth and model changes Report 1.4, 6.16
  • Residents needing temporary accommodation, with growth, savings and further review Report 1.4, 6.9, 6.10
  • Council staff, with vacancy and operating model savings Report 6.11, 6.12, 6.13
  • Local businesses and Heathrow Airport, with revaluation and appeal risk Report 1.7, 4.8

Timeline

  • December 2025: New GLL leisure centre fees and charges take effect
  • 24th December: Budget consultation begins and runs for 6 weeks
  • January 2026: Select Committees review the detailed budget and financial strategy Report P15
  • before the end of January 2026: The council submits its business rates retention budget to MHCLG Report 4.10
  • early February 2026: Final Local Government Finance Settlement is announced Report 1.6
  • 19 February 2026: Cabinet receives the updated final budget and consultation feedback Report P15
  • 26 February 2026: Full Council considers the final budget. Once approved, the proposals take effect immediately. Report P4
  • 2028/29: Target date for a balanced position after the full funding uplift is received Report 1.17, 7.5

Plain English for the jargon

  • EFS: Exceptional Financial Support from central government, sought to help the council set a balanced budget [P1] [6.4]
  • MTFS: The council’s financial strategy covering the next three years [P3]
  • LGFS: The Local Government Finance Settlement, the government funding settlement [D] [P71]
  • HRA: Housing Revenue Account [D]
  • GLL: Greenwich Leisure Limited, the leisure centre operator [P64]
  • Core Spending Power: A government measure of the resources available to councils [P77]
  • Prudential Code: Rules giving greater freedom for capital financing and borrowing decisions [P3]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

That the Cabinet: 1) Notes the circumstances that have led to the council’s current financial position and the assumptions used in producing the medium-term financial strategy (MTFS) as set out in this report; 2) Notes the key risks and mitigations associated with this budget strategy as set out in this report; 3) Approves the draft General Fund and Housing Revenue Account budgets, including growth and savings proposals, fees and charges, and Capital Programme proposals for 2026/27 and beyond (as detailed in Appendices B to F) as the basis for consultation with Select Committees and other stakeholders; 4) Authorises officers to commence consultation on the budget and notes that this will commence on 24th December for a period of 6 weeks, with the results to be reported for consideration by Cabinet at the February 2026 Cabinet meeting; 5) Notes that the final General Fund Revenue Budget, Capital Strategy, Capital Programme, HRA 2026/27 Budget and Business Plan and Treasury Management Strategy Statement will be presented to Cabinet on 19 February 2026 to be recommended for approval to the Full Council meeting taking place on 26 February 2026. Furthermore: 6) Authorises officers to action where possible any efficiency and invest to save proposals at the earliest opportunity in 2025/26 where operational savings are not public facing and so not subject to formal consultation and where assessed not to have any equality impacts. All other proposals subject to public consultation and equality impact assessment will only be implemented after Cabinet considers the consultation feedback, and subject to Full Council approval; 7) Notes that the Final Local Government Finance Settlement (LGFS) is awaited from HM Government and that officers will continue to review and update the 2026/27 MTFS up until the point that EFS is confirmed and the final budget setting report is submitted to Cabinet in February 2026; 8) Notes the material scale of the increase in rateable values for Hillingdon businesses and that officers are taking proactive and urgent communication with relevant parties to determine the veracity of those increases and risks to future income and cashflow of the council if those increases are successfully appealed; 9) Authorises the Corporate Director of Finance, in consultation with the Cabinet Member for Finance & Transformation, to respond on behalf of the council to the consultation on the Provisional LGFS and to the Mayor of London’s budget consultation; 10) Notes that support will be required from government in the form of Exceptional Financial Support in order to set a balanced budget for 2026/27, and indicatively for later years in the MTFS period, and authorises officers to continue to work with MHCLG representatives to make the appropriate arrangements to get this in place. In respect of the 2025/26 budget: 11) Approves the new fees and charges for the council’s leisure centres operated by GLL with effect December 2025, as set out within Appendix F. Reasons for decision The Cabinet Member for Finance and Transformation introduced the Cabinet’s budget proposals for 2026/27 and future years. It was proposed to release the consultation budget for a six-week period, after which it would return in February before being presented to full Council for approval. The proposals included a three-year revenue forecast and a five-year capital programme. The 2026/27 capital programme totalled £75 million following a review to reduce borrowing, while the HRA programme of £133 million included major works to improve social housing stock. The Cabinet Member highlighted the continuing financial challenges caused by years of underfunding, recognised in the Fair Funding Review, and explained that transitional relief would leave the Council underfunded until 2028/29 at a net cost of £44 million. Exceptional financial support would be required in later years to achieve a fully balanced budget by 2028/29. Inflationary pressures, rising costs in adult social care, children’s services and homelessness, and additional responsibilities as a Port Authority were noted as key drivers of demand. The proposed Council Tax increase was 4.99%, including the social care precept, and fees and charges were assumed to rise by 10% with resident discounts retained. The current gap for 2026/27 was £59 million, largely due to transitional funding arrangements. The Cabinet Member confirmed that service modelling and new delivery models were being developed to contain costs, including changes in adult social care, children’s homes and temporary accommodation. The HRA was forecast to maintain £15 million in reserves and continue major works programmes, including the significant housing regeneration project in Hayes. Business rates revaluation for Heathrow Airport was highlighted as a potential risk by the Cabinet Member, requiring further engagement with Government and the airport operator. The Cabinet Member thanked the Corporate Director of Finance and his team for their extensive work on the proposals. The Vice-Chair supported the proposals, acknowledging the ongoing pressures in adult social care, SEND and homelessness, and thanked officers and Members for their work in producing a robust consultation budget. Cabinet, therefore, agreed the proposed 2026/27 budget for consultation. Alternative options considered and rejected Alternative proposals considered but rejected by the Cabinet were set out in the public report. Relevant Select Committee All Expiry date for any scrutiny call-in / date decision can be implemented (if no call-in) Those Cabinet decisions related to the 2026/27 Budget and MTFS are not subject to call-in as a budget and policy framework document. This will be considered by select committees and ultimately by full Council as the decision-maker. These decisions take immediate effect to enable the budget consultation to commence. Officer(s) to action Steve Muldoon Directorate Finance Classification Public - The report and any background papers relating to this decision by the Cabinet are available to view on the Council's website or by visiting the Civic Centre, Uxbridge
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to CABINET, 63 pages

2026/27 BUDGET AND FUTURE MEDIUM-TERM FINANCIAL STRATEGY

Cabinet Member & Cllr Eddie Lavery, Portfolio Cabinet Member for Finance and Transformation

Responsible Officer Steve Muldoon, Corporate Director of Finance & S151 Officer

Report Author & Andy Goodwin, Head of Strategic Finance & Deputy Section 151 Directorate Matt Davis, Director of Strategic & Operational Finance

Papers with report Appendices A to F

HEADLINES Summary This report sets out the council’s draft budget for 2026/27 and the medium-term financial strategy through to 2028/29 for revenue and to 2030/31 for capital. The council continues to face significant financial pressures, driven by rising demand for services, high inflation, and the phased implementation of the government’s new funding formula. Despite a substantial uplift in funding over the next three years, the council remains reliant on Exceptional Financial Support (EFS) to set a balanced budget, as the funding is only phasing in over 3 years, and reserves have been depleted by previous years’ overspends and underfunding. The draft proposals include savings and growth measures, a 4.99% Council Tax increase, and a robust approach to risk management. The capital programme has been reprioritised to focus on essential projects, while maintaining investment in community assets. The council will consult widely on these proposals, seeking feedback from residents, businesses, and stakeholders before finalising the budget in February 2026.

Putting our This report supports our ambition for residents / the council of: Residents First An efficient, well-run, digital-enabled council working with partners to deliver services to improve the lives of all our residents Delivering on the Council Strategy This report supports our commitments to residents of: 2022-2026 A Digital-Enabled, Modern, Well-Run Council

Financial Cost This report sets out the draft budget for 2026/27 including savings and growth proposals, and the outline medium-term financial strategy through to 2028/29 for revenue and to 2030/31 for capital expenditure. The projected position requires a substantial level of EFS from central government in order to deliver a balanced budget and which will have financial implications into future years to repay this support. The financial implications are discussed throughout the report.

Cabinet – 23 December 2025 (Part 1 Public) Select Committee All

Ward(s) All

RECOMMENDATIONS That the Cabinet: 1. Notes the circumstances that have led to the council’s current financial position and the assumptions used in producing the medium-term financial strategy (MTFS) as set out in this report;

2. Notes the key risks and mitigations associated with this budget strategy as set out in this report;

3. Approves the draft General Fund and Housing Revenue Account budgets, including growth and savings proposals, fees and charges, and Capital Programme proposals for 2026/27 and beyond (as detailed in Appendices B to F) as the basis for consultation with Select Committees and other stakeholders;

4. Authorises officers to commence consultation on the budget and notes that this will commence on 24th December for a period of 6 weeks, with the results to be reported for consideration by Cabinet at the February 2026 Cabinet meeting;

5. Notes that the final General Fund Revenue Budget, Capital Strategy, Capital Programme, HRA 2026/27 Budget and Business Plan and Treasury Management Strategy Statement will be presented to Cabinet on 19 February 2026 to be recommended for approval to the Full Council meeting taking place on 26 February 2026.

Furthermore:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2026/27 Budget and Future Medium-Term Financial StrategyReport 63 pages DownloadRead as text
PDF
General Fund: RevenueAppendix B 11 pages Download
PDF
General Fund: Capital ProgrammeAppendix C 2 pages Download
PDF
Housing Revenue Account: RevenueAppendix D 3 pages Download
PDF
Housing Revenue Account: Capital ProgrammeAppendix E 2 pages Download
PDF
Fees and ChargesAppendix F 99 pages Download

At this meeting

Whole meeting

Who was there

6 of 9 attended
IE
Councillor Ian EdwardsChair, apologies
JB
Councillor Jonathan BiancoVice-Chair, in the Chair, present
SO
Councillor Susan O'BrienCommittee Member, present
JP
Councillor Jane PalmerCommittee Member, present
EL
Councillor Eddie LaveryCommittee Member, present
ST
Councillor Steve TuckwellCommittee Member, present
WB
Councillor Wayne BridgesCommittee Member, present
SF
Councillor Scott FarleyCouncillor, in attendance
SP
Councillor Sital PunjaCouncillor, in attendance

On this subject at Hillingdon

Search all
  1. 2026/27 Budget and Future Medium-Term Financial StrategyThis decision
  2. 2026/27 Budget and Future Medium-Term Financial Strategy (to recommend to Council)Approved
  3. 2025/26 Budget and Future Medium-Term Financial Strategy & Budget MonitoringApproved
  4. 2025/26 Budget and Future Medium-Term Financial StrategyApproved

More from Hillingdon CABINET

All decisions
MeetingDecisionOutcome
19 Nov 2026 Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt... Approved Open
19 Nov 2026 Strategic Review of Library Services and Future Delivery ModelThat Cabinet: 1) Approves the launch of the Strategic Review of Library Services and Future Delivery Model, the devel... Approved Open
19 Nov 2026 Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T... Agreed Open
19 Nov 2026 Old Vinyl Factory, Hayes: Conservation Area AppraisalThat Cabinet: 1) Duly considers the public consultation responses to the draft Appraisal for The Old Vinyl Factory Co... Approved Open
19 Nov 2026 Carers Strategy UpdateThat Cabinet: 1) Note the report and agree that officers bring forward an annual progress report to Cabinet on suppor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies